Select committee: Built Environment Committee
New Towns: Bricks and Mortar
Open
Opened 15 Jun 2026
17 recommendations
100 conclusions
Where it stands
The inquiry is open, opened 15 June 2026.
The committee has published 1 report, most recently 1st Report - New Towns: Commit and Build on 15 October 2026.
The government's response
Government response awaited: deadline 15 December 2026.
Recommendations and conclusions
- Conclusion 1Conclusion
- Recommendation 2Recommendation
- Conclusion 3Conclusion
Reports
- 1st Report - New Towns: Commit and Build15 October 2026 · 117 items
Evidence
- 5 oral evidence sessionsLatest 1 September 2026
- 5 written submissions
- 15 witnesses
Recent activity
- 1st Report - New Towns: Commit and Build15 October 2026, Report published
- Built Environment Committee Meeting15 September 2026, Formal meeting (private meeting) · Room 4A, Palace of Westminster
- Built Environment Committee Meeting8 September 2026, Formal meeting (private meeting) · Room 4A, Palace of Westminster
Recommendations and conclusions 117 shown
Our inquiry has shown there are many challenges which make the completion of the new towns programme difficult. However, the Committee believes that it is both possible and indeed necessary to overcome these.
Recommendation 2
Recommended (the committee's words)The Government must establish new town delivery vehicles with clear powers and terms of reference. Delivery vehicles should have the power and autonomy to carry out their work without interference from the Government, but any terms of reference should stipulate any minimum standards and accountability structures required to ensure timely and effective delivery.
Conclusion 3
Concluded (the committee's words)Supply chains for new towns can be made more resilient to a changing climate and global economic shocks by using a diverse range of building materials, ideally sourced from the UK.
Recommendation 4
Recommended (the committee's words)National infrastructure projects, including new towns, will benefit more from overall confidence that the Government is fully committed to seeing rapid completion, given that the materials sector is demand-led. Therefore, the Government should add information on new towns to NISTA’s pipeline, so that the sector has access to accurate demand forecasting and can make capital investment in the natural extraction and manufacturing of materials accordingly.
Conclusion 5
Concluded (the committee's words)By providing greater leadership and clarity , the Government can provide confidence to the sector that the new towns will be delivered. This confidence in the programme will unlock investment in the domestic building materials sector. Increasing domestic capacity will in turn make national supply chains more resilient, and safeguard the delivery of major projects, including new towns .
Recommendation 6
Recommended (the committee's words)The Government must provide the essential commitments to the building materials and construction products sector that the new towns will be delivered.
Conclusion 7
Concluded (the committee's words)Successive governments have failed to effectively anticipate future demand for water, meaning that major developments, such as new towns, cannot rely on an adequate future supply. The new towns programme is threatened by static supply of energy and water, coupled with increasing and unpredictable demand.
Recommendation 8
Recommended (the committee's words)The Government must ensure that utility providers are involved in the production of a holistic national resilience framework plan as early and fully as possible to safeguard the future of energy and water for megaprojects.
Conclusion 9
Concluded (the committee's words)High standards for water and energy consumption and supply must be embedded in the terms of reference for new town delivery vehicles. This provides a unique opportunity for innovative solutions such as grey water systems, and rainwater harvesting .
Conclusion 10
Concluded (the committee's words)The under supply and incorrect mix of onsite and professional construction skills are a risk to the successful delivery of new towns and expanded settlements.
Conclusion 11
Concluded (the committee's words)As part of the Government ’s construction jobs plan, there should be a national review of non-degree construction training and apprenticeships. It should assess their effectiveness and relevance to modern day construction and to the needs of employers. It should also review the standards of qualifications awarded. The plan should examine the reasons for the high drop-out rates for construction qualifications and should be published later this year, as promised to the Committee .
Conclusion 12
Concluded (the committee's words)The terms of reference for each new town delivery body must include a requirement to establish strong and effective working arrangements with employers and training providers. This should lead to the establishment of accredited training and apprenticeships tailored to the requirements of new town development.
Conclusion 13
Concluded (the committee's words)The Government has a key role to play in legitimising and endorsing innovative, low-carbon materials and technologies to reassure insurers.
Conclusion 14
Concluded (the committee's words)Embracing innovative construction methods, including modern methods of construction and standardisation, can reduce pressures on other parts of the sector, including onsite skill demands.
Recommendation 15
Recommended (the committee's words)The Government should review the potential uses of standardisation in house building and how current practice and the building regulations may need to change to facilitate this.
Recommendation 16
Recommended (the committee's words)The Government should make it easier to procure innovative or novel building materials and methodologies by both encouraging demand and reducing barriers to supply. It should look to remove barriers and where appropriate, incentivise their use in the new towns programme, which should be exemplars of their use.
Conclusion 17
Concluded (the committee's words)At the master planning stage for new towns, specific small plots should be designated for SME developers, as outlined in our earlier report. 4 Delivery vehicles must consider how to involve SME developers at the earliest possible stage.
Conclusion 18
Concluded (the committee's words)By focusing the ‘new towns’ programme on urban extensions and urban regeneration schemes the Government has missed an opportunity to create a truly novel generation of distinct new towns.
Conclusion 19
Concluded (the committee's words)If the Government provides commitments that the sector trusted (such as a long-term timetable, build-out targets, funding and sector support) stakeholders could rapidly scale-up production for materials, utilities and skills.
Conclusion 20
Concluded (the committee's words)The new towns programme will fail unless the built environment sector is given a clear message that the Government will deliver as promised, and as necessary.
Recommendation 21
Recommended (the committee's words)The Government must fully commit to taking ownership of the success of the new towns programme, or risk further weakening the confidence of built environment stakeholders that the Government is willing and able to deliver megaprojects.
Recommendation 22
Recommended (the committee's words)The Government must establish all development corporations or equivalent delivery bodies for the new towns programme within three months of the final selection of the sites.
Conclusion 23
Concluded (the committee's words)We will soon by approaching two and a half years since this Government came to power. There has been a consultation and the launch of a taskforce, but construction —or even the final selection of new towns locations—are yet to take place. Therefore , alongside commitments to the urban extensions and urban regeneration projects , construction work must begin on at least one standalone new town within the lifetime of this parliament.
Conclusion 24
Concluded (the committee's words)We were told that the UK construction sector relies on a relatively narrow range of materials and products. 37 Ms Adams cautioned that such a reliance introduces risks to the UK’s domestic supply chains, and that this risk could be reduced with a diversified range of materials and products, and an emphasis on recycling and reuse. 38
Conclusion 25
Concluded (the committee's words)Through the organisation of supply chains to prioritise domestic materials and products, locally sourced where possible, the environmental impact of transport could be lowered, as many core materials are currently imported from overseas. 39 Furthermore, by using locally sourced materials, the design of the town can be rooted in the local vernacular architectural style, increasing the acceptability of new towns with local populations. 40
Conclusion 26
Concluded (the committee's words)An international supply chain is more affected by global shocks, potentially risking the successful delivery of domestic programmes such as new towns. 41 Prioritising the use of domestic materials and products could, therefore, safeguard national supply chains and expose them to less volatility.
Conclusion 27
Concluded (the committee's words)We heard that around 15–20% of construction materials are wasted on sites in the UK, due to structural inefficiencies, and procurement and ordering processes. 42 Ms Adams noted a growing demand for reused materials, 43 and Mr Hopkins added that recycled materials can find new life in other areas of the built environment, such as roads, which will also be required by new towns. 44
Conclusion 28
Concluded (the committee's words)Supply chains for new towns can be made more resilient to a changing climate and global economic shocks by using a diverse range of building materials, ideally sourced from the UK. National leadership
Conclusion 29
Concluded (the committee's words)The Committee heard concerns about a lack of national strategic oversight for long-term materials planning. 45 We were told that the UK lacks a national understanding of the vulnerabilities in its supply chains, despite robust understanding at a project level. 46 Ms Adams called for a national construction materials strategy to trace capacity and shortages issues, and to identify what materials are needed for large projects. 47
Recommendation 30
Recommended (the committee's words)Beyond tracking supply and demand, we heard that a national strategy could create greater resilience in supply chains, by giving confidence to domestic suppliers that infrastructure will be consented and constructed. 48 The Government should communicate the large national infrastructure projects that they will be committing to, so that the building materials sector can estimate demand and invest in extraction and manufacturing capital accordingly. The National Infrastructure and Service Transformation Authority (NISTA) Infrastructure Pipeline is easily accessible online and is an appropriate vehicle for sharing this information. 49
Recommendation 31
Recommended (the committee's words)National infrastructure projects, including new towns, will benefit more from overall confidence that the Government is fully committed to seeing rapid completion, given that the materials sector is demand-led . Therefore, the Government should add information on new towns to NISTA’s pipeline, so that the sector has access to accurate demand forecasting and can make capital investment in the natural extraction and manufacturing of materials accordingly. Local strategy and coordination
Conclusion 32
Concluded (the committee's words)We were told that the new town delivery vehicles have a critical role in ensuring that supply chains are robust, by working with the materials sector. 50 Mr Hopkins urged the new town delivery vehicles to engage with the sector at an early stage to inform them how a masterplan will be delivered, to enable manufacturers to anticipate future demand in the short, medium and long-term. 51
Conclusion 33
Concluded (the committee's words)One way to enact positive change in the materials and products used in new towns is through procurement. Richard Cook, Group Director of Development at Clarion Housing, told us that “procurement is where innovation can come”. 52 Ms Adams argued that proactive procurement strategies, overseen by central government, can provide “exemplars and assurances” 53 to the wider sector, “removing barriers to innovation and market entry”. 54
Conclusion 34
Concluded (the committee's words)By providing greater leadership and clarity, the Government can provide confidence to the sector that the new towns will be delivered. This confidence in the programme will unlock investment in the domestic building materials sector . Increasing domestic capacity will in turn make national supply chains more resilient, and safeguard the delivery of major projects, including new towns.
Recommendation 35
Recommended (the committee's words)The Government must provide the essential commitments to the building materials and construction products sector that the new towns will be delivered. Box 2: Case Study - Queen Elizabeth Olympic Park We heard that the procurement strategy for the Queen Elizabeth Olympic Park, Stratford, demonstrated the value of supply-chain intervention, early engagement with suppliers, and robust contingency and legacy planning. Ms Larkin explained that the delivery team engaged at a very early stage with suppliers and embedded a materials and products strategy to give certainty to the sector. Through this engagement, the sector could mobilise and work proactively with the clients, contractors and designers to ensure that the supply chain could best support the project. The Queen Elizabeth Olympic Park is also a case study for the procurement of innovative building materials. The scale of the project, alongside its backing from central government and coordination from its development vehicle, allowed the use of novel building materials in its construction, giving confidence to the wider sector and proving their effectiveness. Dr Adams explained that if a novel material has been used somewhere successfully at scale, it is much easier to use elsewhere, adding “having that testbed is really important”. 55 15 See for example Q 2 (Katherine Adams, Rebecca Larkin, David Hopkins). 16 See for example QQ 2–3 (Katherine Adams). 17 Q 2 (Rebecca Larkin, Katherine Adams) 18 Q 13 (Katherine Adams) 19 Q 2 (Rebecca Larkin) 20 Q 6 (Rebecca Larkin) 21 Q 2 (Katherin Adams) 22 Q 3 (Katherine Adams) 23 Q 4 (Rebecca Larkin) 24 Written evidence from the Construction Products Association ( NTB0018 ) 25 Q 3 (Rebecca Larkin) 26 Ibid. 27 Q 2 (David Hopkins) 28 Ibid. 29 Ibid. 30 Written evidence from the Construction Products Association ( NTB0018 ) 31 Written evidence from Albion Stone PLC ( NTB0003) 32 Q 6 (David Hopkins) 33 Ibid. 34 Written evidence from the Construction Products Association ( NTB0018 ) 35 Q 3 (Rebecca Larkin) 36 Ibid. 37 Written evidence from Albion Stone PLC ( NTB0003 ) 38 Q 4 (Katherine Adams) 39 Written evidence from Albion Stone PLC ( NTB0003 ) 40 Written evidence from the Stone Federation of Great Britain ( NTB0033 ) 41 Q 3 (Katherine Adams) 42 Q 9 (Katherine Adams) 43 Ibid. 44 Q 9 (David Hopkins) 45 Q 3 (Katherine Adams, Rebecca Larkin) 46 Q 3 (Katherine Adams) 47 Ibid. 48 Ibid. 49 NISTA, Infrastructure Pipeline , March 2026 50 See for example Q 4 (David Hopkins, Rebecca Larkin). 51 Q 4 (David Hopkins) 52 Q 30 (Richard Cook) 53 Q 13 (Katherine Adams) 54 Ibid. 55 Ibid. < Back Next > © Parliamentary copyright 2026 A-Z index Glossary Contact us Freedom of Information Jobs Using this website Copyright Privacy notice Cookie policy Cookie Manager House of Lords - New Towns: Commit and Build - Built Environment Committee Accessibility Email alerts RSS feeds Contact us Home Parliamentary business MPs, Lords & offices About Parliament Get involved Visiting Education House of Commons House of Lords What's on Bills & legislation Committees Publications & records Parliament TV News Topics New Towns: Commit and Build Contents Chapter 3: Utilities and infrastructure Connections, demand and sequencing
Conclusion 36
Concluded (the committee's words)New towns will require a constant supply of water, energy and digital connectivity for their new inhabitants. Unfortunately (and deeply regrettably) this presents a challenge for the Government, because of decades of poor planning and a lack of effective preparation for the future. A changing climate, an increase in extreme weather events, greater demands for digital technologies and a move towards an electrified economy have all been predicted for decades, and yet vulnerabilities in the UK utilities sector—sometimes caused by these changes—continue to be exposed. As such, any construction of new towns will coincide with times of scarcity and fragility for our national system of utilities, driven by the entirely predictable interplay of increasing demand and static supply.
Conclusion 37
Concluded (the committee's words)Connecting these utilities to national networks during construction presents additional challenges. New towns are megaproject-scale endeavours, requiring complex logistical planning, especially for “sequencing” (the scheduling and execution of different stages of the building process.) Sequencing is time-critical, because each milestone in a construction process relies on other stages having been completed. For example, if new utilities are installed on differing timescales, rather than in a co-ordinated way, before a road surface is laid, this is not cost effective and can lead to delays. 56 Rather, effective sequencing will mean that new homes are being built in step with the installation of new utility connections. 57 As Dr Tariq Umar told the Committee: “a new town is not simply a large housing site; it comprises land assembly, remediation, transport, energy, water, digital networks, schools, health facilities, public realm and several housing markets. Delay in one critical system can prevent occupation even when homes are physically complete.” 58
Conclusion 38
Concluded (the committee's words)Sequencing is inherently complex and relies on the coordination of multiple interested parties, including housebuilders, local authorities, regulators, specialist engineers and utility companies. 59 The Committee heard of less successful developments, where sequencing was poor and over-optimistic announcements about timescales failed to take constraints on progress into account. 60 Witnesses emphasised the essential requirement for a single delivery vehicle which could take responsibility for infrastructure and ensure that it is installed in advance with housing, 61 taking an “infrastructure first” approach. 62
Conclusion 39
Concluded (the committee's words)The Committee primarily received evidence on water and electricity, but gas supplies, community heating systems, drainage and road connections are other important types of infrastructure. Digital connectivity enables other technologies which will make infrastructure and utilities more efficient and resilient: for example, smart meters for electricity demand. All these other utilities need to be adequately supplied, correctly sequenced and effectively coordinated in the construction process if new towns are going to be successfully delivered. Challenges for water
Conclusion 40
Concluded (the committee's words)The construction of new towns will cause two challenges for the water industry: first, new homes and amenities will need to be connected to the mains water supply. Secondly, the wider national supply of water will need to meet the increased demand that these new homes will create.
Conclusion 41
Concluded (the committee's words)There is minimal spare capacity in the UK’s water supply, making it vulnerable to droughts and increases in demand. 63 Stuart Colville, Deputy Chief Executive of WaterUK, told the Committee that “in some parts of the country, headroom—spare water—is down to 2%. Clearly, if any shock comes along—if you have a new town or whatever it is—there is far too much fragility within the system.” 64
Conclusion 42
Concluded (the committee's words)For decades, successive governments, water companies and regulators have failed to work together to anticipate effectively future demand for water. 65 Meanwhile, the water industry has not factored major future demands (such as new towns or data centres) into its planning. 66 An example of this failure in resource planning is that the UK has not built a new reservoir for over 30 years. As they take around 10–15 years to build, long-term and sustainable increases in water storage capacity appear to be an unacceptably distant prospect. 67 New towns should not be competing with other developments (such as data centres or industry) for connection to the water supply. Rather, the Government and the water industry should be working closely together to ensure that infrastructure is in place to provide a resilient and abundant supply of water for the long-term. Challenges for energy
Conclusion 43
Concluded (the committee's words)New towns will need to be connected to the National Grid before houses can be occupied. The Grid will need to meet the increase in demand which new towns will require. In addition to these challenges, the construction of new towns will occur at a time when the UK is transitioning away from fossil fuels towards an electrified economy, while demands for energy, such as for electric car charging and data centres, are increasing. 68
Conclusion 44
Concluded (the committee's words)New towns will therefore compete with new and increased demand for electricity connectivity and supply. While they are critical for economic growth, the rapid development of data centres presents a challenge to the utilities industries, as they have significant water and energy uses. 69 New towns are being strategically located in areas with potential for economic growth and regeneration, links to transport and ready supply of utilities. Yet these are also the areas that may be prioritised for any new industry and data centres. Competing demand for energy may create a challenge for such areas, potentially requiring better local energy planning, so that new infrastructure can be seamlessly connected to the Grid. 70
Conclusion 45
Concluded (the committee's words)There should not be competition between data centres and new towns. This reflects decades of underinvestment in critical utilities infrastructure, which has left us unable to effectively advance projects which would support economic growth and job creation. Utilities and resilience
Conclusion 46
Concluded (the committee's words)Building new towns, connecting them to utilities and then populating them—but without ensuring that they have a sustainable supply of water and energy—would constitute a risk to national resilience. This would be irresponsible. Mr Colville alerted the Committee to the lack of minimum standards for water utilities in relation to resilience. He said that “there are no rules about single sources of supply” 71 for water connections to new towns, meaning that a settlement could have only one connection to the water mains, making it more vulnerable to damage or sabotage. Mr Colville warned the Committee “do not have a massive town with a single water connection going into it.” 72
Conclusion 47
Concluded (the committee's words)We heard how new towns could benefit from new technologies that will make the electricity supply more resilient. 73 Lawrence Slade, Chief Executive of the Energy Networks Association, mentioned the use of batteries at a community level as a way of making electricity supply more resilient. 74 New towns present an opportunity to design communities that exhibit resilience in multiple domains, from climate change to civil defence. 75 They should act as exemplars that will demonstrate best practice in resilient design, future-proofing developments for a century where essential supplies may become more vulnerable to shocks and shortages than at present. Opportunities for best practice and innovation
Conclusion 48
Concluded (the committee's words)Distinct new towns on greenfield sites are a blank slate for developers, making it more straightforward to integrate best practice for managing water and energy demand into their design. 76 Urban extensions have a different advantage: as much of the infrastructure is already in place, the volume of new utility connections needed is reduced. 77
Conclusion 49
Concluded (the committee's words)New towns provide an opportunity to plan more deliberately how buildings can be designed to reduce demand for utilities. 78 Likewise, there is a need (and an opportunity) for more innovative thinking on how to overcome perceived barriers to supply. These may include off-peak electricity use, combined heat and power, and community energy generation. 79 New towns should be an example of excellent, purpose-driven design, where these demand-reducing features can be incorporated as standard. John Marsh, Chief Innovation Officer of BUUK Infrastructure, told the Committee that ideally new towns would have homes which already have “the right insulation levels, with PV [solar photovoltaic panels], a heat pump and smart appliances ready to be linked up”. 80
Conclusion 50
Concluded (the committee's words)Got right, effective utility connections could make new towns even more attractive places to live. If micro-renewables (like solar panels) are combined with community power schemes and adequate connections to the National Grid, the possibility of negative energy bills arises. This will mean that householders are paid for the energy generated at their homes. 81 This could mean reduced bills, offset by these payments, or even net-negative bills. However, this needs to be balanced against the capital cost of these schemes and the implications for home affordability.
Conclusion 51
Concluded (the committee's words)The Committee heard how greywater recycling presents an exciting opportunity to make new towns more resilient to water shortages (whether caused by climate change or faults with mains infrastructure) and cheaper to live in. Drinking water does not necessarily need to be used for gardens or flushing lavatories: new towns can be designed with rainwater harvesting as standard, so that these systems can be included in construction, rather than expensively retrofitted. 82
Conclusion 52
Concluded (the committee's words)New towns are a once-in-a-generation opportunity: purpose-built communities which will be built in one cohesive effort. These are the perfect blank canvases to demonstrate best practice for infrastructure and utilities and act as proving grounds for innovative technologies. As Mr Colville told the Committee in relation to water reclamation technologies: “if we cannot do it with these new towns, we will never do it.” 83
Conclusion 53
Concluded (the committee's words)Successive governments have failed to effectively anticipate future demand for water, meaning that major developments, such as new towns, cannot rely on an adequate future supply. The new towns programme is threatened by static supply of energy and water, coupled with increasing and unpredictable demand.
Recommendation 54
Recommended (the committee's words)The Government must ensure that utility providers are involved in the production of a holistic national resilience framework plan as early and fully as possible to safeguard the future of energy and water for megaprojects.
Conclusion 55
Concluded (the committee's words)High standards for water and energy consumption and supply must be embedded in the terms of reference for new town delivery vehicles. This provides a unique opportunity for innovative solutions such as grey water systems, and rainwater harvesting. 56 Q 35 (John Marsh) 57 Written evidence from the Royal Institute of British Architects ( NTB0024 ), Dr Tariq Umar ( NTB0017 ) and Mr Rami Saadi ( NTB0027 ) 58 Written evidence from Dr Tariq Umar ( NTB0017 ) 59 Written evidence from Mr Rami Saadi ( NTB0027 ) 60 Written evidence from Dr Alexander Budzier ( NTB0034 ) 61 Written evidence from the Landmark Information Group ( NTB0012 ), Dr Tariq Umar ( NTB0017 ), and Places for People ( NTB0028 ) 62 Written evidence from Royal Town Planning Institute ( NTB0023 ), QQ 44 (Professor Juliano Denicol), 49 (Dr Alexander Budzier) 63 Q 35 (Stuart Colville) and written evidence from the Royal Town Planning Institute ( NTB0023 ) 64 Q 37 (Stuart Colville) 65 Q 34 (Stuart Colville) and written evidence from Peabody ( NTB0037 ) 66 Q 34 (Stuart Colville) and written evidence from Dr Tariq Umar ( NTB0017 ) 67 Q 34 (Stuart Colville) and written evidence from the Royal Town Planning Institute ( NTB0023 ) 68 Q 34 (Lawrence Slade) 69 Q 39 (Stuart Colville) 70 Q 39 (Lawrence Slade) 71 Q 42 (Stuart Colville) 72 Ibid. 73 Written evidence from Peabody ( NTB0037 ), BUUK Infrastructure ( NTB0039 ), Q 40 (John Marsh) 74 Q 42 (Lawrence Slade) 75 See, for example, Q 42 (Stuart Colville) and written evidence the Landmark Information Group ( NTB0012 ) and the Royal Town Planning Institute ( NTB0023 ). 76 Q 36 (Lawrence Slade) and Q 38 (Lawrence Slade, Stuart Coville) 77 Q 6 (David Hopkins) 78 Q 36 (Lawrence Slade) 79 Written evidence from Peabody ( NTB0037 ); Q 40 (John Marsh) 80 Q 42 (John Marsh) 81 Q 43 (John Marsh) 82 Written evidence from Peabody ( NTB0037 ); Q 36 (Stuart Colville) 83 Q 36 (Stuart Colville) < Back Next > © Parliamentary copyright 2026 A-Z index Glossary Contact us Freedom of Information Jobs Using this website Copyright Privacy notice Cookie policy Cookie Manager House of Lords - New Towns: Commit and Build - Built Environment Committee Accessibility Email alerts RSS feeds Contact us Home Parliamentary business MPs, Lords & offices About Parliament Get involved Visiting Education House of Commons House of Lords What's on Bills & legislation Committees Publications & records Parliament TV News Topics New Towns: Commit and Build Contents Chapter 4: Construction skills A permacrisis?
Conclusion 56
Concluded (the committee's words)A 2026 report by the Built Environment Futures Assembly argued that the built environment faces a “permacrisis” in skills, as “demand outpaces the workforce’s ability to adapt.” 84 A lack of construction skills is a stubborn issue for the sector, worsening in recent years due to an ageing workforce and fewer young people entering the industry. 85 Skills England research indicates that there is demand for just over one million workers needed by 2035, with Jonathan Mitchell, Deputy Director at Skills England, describing it as a “significant challenge”. 86
Conclusion 57
Concluded (the committee's words)The Government intends the next generation of new towns and expanded settlements to be exemplars in their design and construction. 87 Creating true exemplars will demand a robust, highly skilled workforce both at an onsite and professional level, which David Hopkins, Chief Executive of Timber UK, warned does not necessarily exist. 88
Conclusion 58
Concluded (the committee's words)Mr Mitchell told us that “there is no question that skills shortages are a real delivery risk for new towns”. 89 He added that the issue is not just the number of people entering the construction sector, but also achieving the right mix of trades, technical specialities and professional roles, all over the country. 90 We heard that skills shortages are more acute for certain roles, particularly for innovative and environmental sustainability specialities, which are expected to become more in demand. 91
Conclusion 59
Concluded (the committee's words)The challenges of construction skills shortages are compounded by the fragmented nature of the sector, which is heavily reliant on small and medium enterprises (SMEs), including micro-businesses. 92 Mr Mitchell said that as the sector is highly project-based there is a fragmented demand for skills, making long-term workplace planning even more challenging. 93
Conclusion 60
Concluded (the committee's words)The under supply and incorrect mix of onsite and professional construction skills are a risk to the successful delivery of new towns and expanded settlements. Training and education
Conclusion 61
Concluded (the committee's words)While much of the historical discussion on construction skills focused on the quantity of workers, the Committee also heard that the quality of skills education is also a challenge. 94 Sam Egan, Group Director of Construction at the Bedford College Group, said that some construction employers have complained that some students are not ‘site ready’ after their education. 95 We were told that construction education does not provide a good picture of what a career in the sector is like in practice, frustrating learners and employers. 96 For example, we heard that bricklaying is primarily taught indoors, but Ms Egan said that “in real life it is cold outside”. 97 She told us that this is partially due to a lack of funding leading to poorer facilities and fewer hands-on experiences. 98
Conclusion 62
Concluded (the committee's words)While student places are often oversubscribed at training colleges, Ms Egan told us that there is difficulty filling construction teaching roles due to low pay compared with similar roles in the sector, compounding the perception of a poorer quality of education. 99
Conclusion 63
Concluded (the committee's words)We heard that the fragmented nature of the construction sector presents a barrier to improving employer engagement with training opportunities, with employers and subcontractors moving frequently between sites and projects, making it difficult to provide continuity of supervision and mentoring. 100 City & Guilds suggested that this discourages some employers from taking on apprenticeships, and creates uncertainty for learners seeking a stable route into the industry. 101
Conclusion 64
Concluded (the committee's words)We heard that construction training programmes are often highly fragmented themselves and rely on multiple different routes, which can be challenging to navigate for learners. 102 Ms Egan suggested that streamlining qualification routes could provide greater clarity. 103 We were told that greater alignment between qualifications and employer needs could strengthen recruitment and outcomes in the sector. 104 Drop-out rates
Conclusion 65
Concluded (the committee's words)Rebecca Larkin, Head of Construction Research at the Construction Products Association, said that there is a 50% drop-out rate for male construction trainees and a 70% female drop-out rate. 105 Once in employment, we were told that the sector experiences workplace attrition from early career entrants leaving relatively quickly. 106
Conclusion 66
Concluded (the committee's words)We heard that the reasons for high drop-out rates are complex with many contributing factors, including poor access to mentoring, especially for women, 107 differences in expectations and reality onsite, 108 and a perceived poor quality of education. 109
Conclusion 67
Concluded (the committee's words)We welcome the commitment made by Matthew Pennycook (Minister for Housing and Planning), during our evidence session, to publish a construction jobs plan later this year. 110
Conclusion 68
Concluded (the committee's words)As part of the Government’s construction jobs plan, there should be a national review of non-degree construction training and apprenticeships. It should assess their effectiveness and relevance to modern day construction and to the needs of employers. It should also review the standards of qualifications awarded. The plan should examine the reasons for the high drop-out rates for construction qualifications and should be published later this year, as promised to the Committee. An opportunity for success
Conclusion 69
Concluded (the committee's words)Despite the many challenges related to construction skills, Simon Rawlinson, Deputy Chair of the Construction Industry Council, remained optimistic that the new towns programme could provide a “particularly interesting opportunity to apply the new skill sets that the industry needs”. 111 Mr Mitchell said that it will demand a mix of all types of construction skills, including new skills associated with innovative methods. 112 We heard from Mr Rawlinson that new towns are an opportunity to develop a new multidisciplinary workforce which is well equipped to engage with the latest construction and manufacturing skills. 113
Conclusion 70
Concluded (the committee's words)The long-term outlook of the new towns programme allows a clear pipeline of demand for skilled workers, providing confidence for investors in construction skills. 114 City & Guilds stressed that long-term workforce planning for new towns will be critical, identifying the number of workers needed and the mix of skills. 115
Conclusion 71
Concluded (the committee's words)In order to effectively capitalise on the opportunity that new towns can provide, Mr Hopkins urged delivery vehicles to ensure that there are sufficient training facilities available in the early stages of development. 116 Ms Egan argued that delivery bodies should look to engage with further education providers in order to integrate teaching into development. 117 Through the integration of early development with training opportunities, the delivery vehicles can ensure the incoming workforce is well equipped to deliver the needs of the emerging settlements.
Conclusion 72
Concluded (the committee's words)The terms of reference for each new town delivery body must include a requirement to establish strong and effective working arrangements with employers and training providers. This should lead to the establishment of accredited training and apprenticeships tailored to the requirements of new town development. The Role of Government
Conclusion 73
Concluded (the committee's words)While we were grateful for the oral evidence from of Skills England, the Committee are concerned that they lack the necessary oversight to tackle the construction skills crisis. Skills England were indeed able to provide much of the necessary data on construction skills, but we were disappointed to learn of the extremely limited nature of their remit, which seems to limit their ability to take responsibility for and develop solutions. 118
Conclusion 74
Concluded (the committee's words)Furthermore, we were concerned to learn that Mr Pennycook and Mr Mitchell hold different opinions on the degree to which the skills crisis will impact the delivery of new towns the former suggesting it is “no specific …challenge” 119 with the latter telling us there was no question it was a “delivery risk”. 120 84 Construction Industry Council, New report calls for data-led workforce planning to confront Built Environment skills permacrisis, 4 June 2026 85 Ibid. 86 Q 15 (Jonathan Mitchell) 87 Ministry of Housing, Communities and Local Government, Building new towns for the future , 12 February 2025 88 Q 5 (David Hopkins) 89 Q 15 (Jonathan Mitchell) 90 Ibid. 91 Written evidence from City & Guilds ( NTB0014 ) 92 Q 18 (Jonathan Mitchell), and written evidence from the Bedford College Group ( NTB0009 ) 93 Q 18 (Jonathan Mitchell) 94 See for example Q 15 (Sam Egan), and written evidence from the Bedford College Group ( NTB0009 ). 95 Q 15 (Sam Egan) 96 Written evidence from the Bedford College Group ( NTB0009 ) 97 Q 18 (Sam Egan) 98 Q 15 (Sam Egan) 99 Ibid. 100 Written evidence from the Bedford College Group ( NTB0009 ) 101 Written evidence from City & Guild ( NTB0014 ) 102 Written evidence from City & Guild ( NTB0014 ) 103 Q 23 (Sam Egan) 104 Written evidence from the Bedford College Group ( NTB0009 ) 105 Q 10 (Rebecca Larkin) 106 Written evidence from the Bedford College Group ( NTB0009 ) 107 Q 18 (Sam Egan) 108 Written evidence from the Bedford College Group ( NTB0009 ) 109 Written evidence from City & Guilds ( NTB0014 ) 110 Q 61 (Minister of State for Housing and Planning) 111 Q 15 (Simon Rawlinson) 112 Q 15 (Jonathan Mitchell) 113 Q 15 (Simon Rawlinson) 114 Q 19 (Jonathan Mitchell) 115 Written evidence from City & Guilds ( NTB0014 ) 116 Q 10 (David Hopkins) 117 Q 23 (Sam Egan) 118 Q 16 (Jonathan Mitchell) 119 Q 61 (Minister of State for Housing and Planning) 120 Q 15 (Jonathan Mitchell) < Back Next > © Parliamentary copyright 2026 A-Z index Glossary Contact us Freedom of Information Jobs Using this website Copyright Privacy notice Cookie policy Cookie Manager House of Lords - New Towns: Commit and Build - Built Environment Committee Accessibility Email alerts RSS feeds Contact us Home Parliamentary business MPs, Lords & offices About Parliament Get involved Visiting Education House of Commons House of Lords What's on Bills & legislation Committees Publications & records Parliament TV News Topics New Towns: Commit and Build Contents Chapter 5: Technology, innovation and best practice An opportunity for excellence
Conclusion 75
Concluded (the committee's words)The Government has consistently reiterated its intentions for the next generation of new towns and expanded settlements to be exemplars, demonstrating the best of planning, design and construction. 121 In its 2025 interim report to the Government, the New Towns Taskforce identified an additional aim for the programme: to “contribute to transforming the way that large settlements are delivered”, 122 seeking to improve and innovate methods of settlement delivery.
Conclusion 76
Concluded (the committee's words)During our inquiry we heard that the new towns programme presents an opportunity to embed innovative methods of construction and project delivery into development. 123 As large Government-backed projects, the new towns could prove the effectiveness of new products or materials, as well as innovative methods of construction and delivery. This could confer legitimacy on them as safe and sustainable materials and products which could be used throughout the wider built environment sector in future. Construction materials
Conclusion 77
Concluded (the committee's words)Evidence highlighted many different types of building materials that are successfully used in the construction sector in the UK, although not necessarily at a large scale. These included hemp, 124 wool-fibre insulation 125 and stone. 126 We were told such materials often have a lower carbon footprint than mainstream alternatives, as well as being rooted in heritage traditions and local historical vernaculars. 127
Conclusion 78
Concluded (the committee's words)The lower environmental impact of certain building materials (including low-carbon cement and straw) could help meet the Government’s ambitions for the new towns to be environmentally sustainable and climate resilient. 128 David Hopkins, Chief Executive of Timber UK, argued that the new towns programme presents a “good opportunity to reimagine” construction supply chains and consider more opportunities for recycling building materials. 129
Conclusion 79
Concluded (the committee's words)Despite the potential for novel materials, Katherine Adams, Technical Director at the Alliance for Sustainable Building Products, warned that the use of certain products can make it difficult to insure buildings. 130 She explained that any perceived risk, including the utilisation of novel building materials, adds cost to a project. 131 Mr Hopkins thought that the construction sector is “very conservative and does not change very quickly”, 132 relying instead on long-standing methods and products, increasing the perception of risk.
Conclusion 80
Concluded (the committee's words)Evidence emphasised that the scale of the new towns programme could demonstrate the applicability of different novel materials and provide confidence to insurers and developers when considering the use of innovative products. 133 Dr Adams urged the Government to “[remove] barriers to innovation” and act as “an exemplar in how they build and procure”. 134
Conclusion 81
Concluded (the committee's words)The Government has a key role to play in legitimising and endorsing innovative, low-carbon materials and technologies to reassure insurers. Construction methods
Conclusion 82
Concluded (the committee's words)Richard Cook, Chief Development Officer at Clarion Housing Group, commented that “the sector has really struggled” with innovation in construction methods. 135 As with construction materials, innovative methods create additional perceived risk to the project, incurring higher costs over time. 136 We heard this is particularly true with modern methods of construction (MMC), where the warranty market is fragmented due to historical challenges. 137 Box 3: Modern methods of construction Modern methods of construction (MMC) is a collective term for building methods that are designed to be more efficient and effective than traditional construction methods. Methods covered by the term range from factory-produced structures that are built entirely offsite to modular components that enable structures to be assembled more quickly or easily onsite. The Built Environment Committee conducted an inquiry on the MMC industry and published a letter to the Government on the topic in 2024. 138
Conclusion 83
Concluded (the committee's words)However, much evidence argued that innovative construction methods, including MMC, digital design and standardisation, has potential to improve delivery and productivity onsite. 139 Simon Rawlinson, Vice Chair of the Construction Industry Council, told us that MMC has been broadly successful in the UK in certain sectors including education, healthcare and defence. 140 We were told that MMC can make sites more productive by assembling construction products off-site, especially where MMC exists within a cohesive system of production, transport and installation. 141
Conclusion 84
Concluded (the committee's words)Jonathan Mitchell, Deputy Director at Skills England, told us that innovative construction methods could reduce pressure on in-demand construction skills by increasing factory-based manufacturing. 142 Sam Egan, Group Director at the Bedford College Group, added that technical training colleges are moving towards more innovative construction methods in their teaching, although she cautioned that it is very expensive to invest in. 143 She suggested that the technical training colleges would need stronger signals from the sector and employers to increase training. 144
Conclusion 85
Concluded (the committee's words)In Chapter 3, we highlighted the pressures facing the construction skills workforce, the challenges of attracting and retaining talent, poor educational outcomes, and differences between expectations and the reality of working on a construction site. Mr Hopkins said that factory skills are “easier to ramp up than on site skills”, adding that “Putting people into factories and training them up to use machinery is a quicker process to get a high-quality product at the other end than trying to train people on building sites”. 145 While individuals would still be needed onsite, he indicated that a move towards more innovative construction methods could help with the skills shortage. 146
Conclusion 86
Concluded (the committee's words)Mr Rawlinson did not believe the UK housing sector was large enough to support use of MMC at significant scale. 147 Mr Hopkins was supportive of greater use of innovative construction methodologies but felt that “demand is too low” and “the financial situation is just not strong enough”. 148 He explained that construction manufacturing facilities are often expensive to run and need to be in constant use. 149 Standardisation
Conclusion 87
Concluded (the committee's words)Standardisation is the use of modules, assemblies, components, methods or processes that are repeated throughout a project and from project to project. It was frequently highlighted in evidence as a method to improve the delivery of new towns. 150 We heard that certain elements of all new towns could be standardised, including energy performance requirements, 151 building code standards 152 and the basic design for affordable housing. 153 Mr Hopkins explained that through standardising components across multiple projects, such as the individual new towns, manufacturers and contractors would be able to scale up production, and have increased certainty over their pipeline. 154
Conclusion 88
Concluded (the committee's words)Mr Hopkins thought that standardisation would not necessarily lead to conformity in aesthetic design for the new towns. 155 Standardising core parts of construction like energy performance expectations and building codes would have no effect on the visual identity of new towns and be imperceptible to most individuals. Dr Tariq Umar, an academic at the University of the West of England, argued that the new towns should have strong design guidelines to ensure visual diversity, whilst standardising certain core elements to support effective delivery. 156
Conclusion 89
Concluded (the committee's words)Embracing innovative construction methods, including modern methods of construction and standardisation, can reduce pressures on other parts of the sector, including onsite skill demands.
Recommendation 90
Recommended (the committee's words)The Government should review the potential uses of standardisation in house building and how current practice and the building regulations may need to change to facilitate this.
Recommendation 91
Recommended (the committee's words)The Government should make it easier to procure innovative or novel building materials and methodologies by both encouraging demand and reducing barriers to supply. It should look to remove barriers and where appropriate, incentivise their use in the new towns programme, which should be exemplars of their use. SME involvement
Conclusion 92
Concluded (the committee's words)While we heard many examples of innovative or novel materials or methods that could improve the delivery of the new generation of new towns, we were often cautioned that their use could incur higher costs from perceived risk. 157 This would be felt most acutely by SME developers, potentially discouraging their involvement in the wider programme. 158
Conclusion 93
Concluded (the committee's words)Dr Adeyemi Akintola and Dr Basirat Oyalowo said “SMEs occupy a paradoxical position” in relation to innovation. 159 SMEs are often actively engaged in innovative schemes, yet face higher risk from innovation failures as they cannot diversify that risk across multiple concurrent projects. 160
Conclusion 94
Concluded (the committee's words)At the master planning stage for new towns, specific small plots should be designated for SME developers, as outlined in our earlier report. 161 Delivery vehicles must consider how to involve SME developers at the earliest possible stage. Standalone sites and innovation
Conclusion 95
Concluded (the committee's words)Of particular interest in using the current new towns programme to demonstrate examples of effective and innovatory practice, is the need to show how new approaches work on distinct, standalone sites. However, none of the seven locations proposed to be taken forward in the Government’s March 2026 consultation 162 is described as “standalone” site—although the Committee recognises that one may be described as being rural.
Conclusion 96
Concluded (the committee's words)By focusing the ‘new towns’ programme on urban extensions and urban regeneration schemes the Government has missed an opportunity to create a truly novel generation of distinct new towns. 121 Ministry of Housing, Communities & Local Government, Policy statement on new towns , 31 July 2024, 122 Ministry of Housing, Communities & Local Government, Building new towns for the future , 13 February 2025 123 Q 6 (David Hopkins, Katherine Adams) 124 Q 6 (Katherine Adams) 125 Ibid. 126 Written evidence from Mr Pierre Bidaud ( NTB0008 ) and the Stone Federation of Great Britain ( NTB0033 ) 127 Q 6 (Katherine Adams) 128 Q 13 (Katherine Adams) 129 Q 9 (David Hopkins) 130 Q 6 (Katherine Adams) 131 Ibid. 132 Q 6 (David Hopkins 133 See for example QQ 6 (Rebecca Larkin), 30 (Richard Cook) 134 Q 13 (Katherine Adams) 135 Q 29 (Richard Cook) 136 Ibid. 137 See for example QQ 21 (Simon Rawlinson), 29 (Richard Cook) and 30 (Alison Crofton) 138 Built Environment Committee, MMC sector may continue to struggle without a fresh approach from the Government , 26 January 2024 139 See for example written evidence from Mr Pierre Bidaud ( NTB0008 ), Dr Tariq Umar ( NTB0017 ), the Royal Institute of British Architects ( NTB0024 ), the National House Building Council ( NTB0026 ), Dr Vijay Pawar and Dr Colin Rose ( NTB0029 ) 140 Q 21 (Simon Rawlinson) 141 Written evidence from Dr Vijay Pawar and Dr Colin Rose ( NTB0029 ) 142 Q 21 (Jonathan Mitchell) 143 Q 21 (Sam Egan) 144 Q 21 (Sam Egan) 145 Q 4 (David Hopkins) 146 Ibid. 147 Q 21 (Simon Rawlinson) 148 Q 10 (David Hopkins) 149 Ibid. 150 See for example QQ 4 (Katherine Adams), 5 (David Hopkins), 44 (Professor Juliano Denicol), and written evidence from the National House Building Council ( NTB0026 ) and Mr Rami Saadi ( NTB0027 ). 151 Q 5 (David Hopkins) 152 Written evidence from Mr Pierre Bidaud ( NTB0008 ) 153 Q 4 (Katherin Adams) 154 Q 5 (David Hopkins) 155 Ibid. 156 Written evidence from Dr Tariq Umar ( NTB0017 ) 157 See for example QQ 6 (Rebecca Larkin), 31 (Richard Cook). 158 Written evidence from Dr Adeyemi Akintola and Dr Basirat Oyalowo ( NTB0030 ) 159 Ibid. 160 Written evidence from Dr Adeyemi Akintola and Dr Basirat Oyalowo ( NTB0030 ) 161 Built Environment Committee, New Towns: Laying the Foundations (2nd Report, Session 2024–26, HL Paper 183) 162 Ministry of Housing, Communities and Local Government, New Towns Draft Programme , 23 March 2026 < Back Next > © Parliamentary copyright 2026 A-Z index Glossary Contact us Freedom of Information Jobs Using this website Copyright Privacy notice Cookie policy Cookie Manager House of Lords - New Towns: Commit and Build - Built Environment Committee Accessibility Email alerts RSS feeds Contact us Home Parliamentary business MPs, Lords & offices About Parliament Get involved Visiting Education House of Commons House of Lords What's on Bills & legislation Committees Publications & records Parliament TV News Topics New Towns: Commit and Build Contents Chapter 6: Conclusion
Conclusion 97
Concluded (the committee's words)A key message emerging from this module of our inquiry also featured in the previous two modules: that central Government must take overall control of this programme and should treat it as a major national project. It should do this through its own actions and through setting up accountable mechanisms for that control.
Conclusion 98
Concluded (the committee's words)Such actions include establishing a transparent funding stream for new towns; 163 committing to, and requiring, infrastructure-first delivery; 164 requiring delivery vehicles to commit to a phased 165 timescale for building out specific phases of each new town; 166 and, above all, setting a strong framework within which delivery vehicles can operate with minimum bureaucratic barriers.
Conclusion 99
Concluded (the committee's words)A clear message of commitment and intent would be if the Government established all the mechanisms, bodies and any legislative orders required for the new towns programme during this parliament, meaning that successive governments had the measures in place to commence development of all the new towns. We welcomed the news from Mr Pennycook that each individual new town would have a specific funding package and believe this is a valuable step in fostering confidence in the programme. 167
Conclusion 100
Concluded (the committee's words)A clear ‘pipeline’ (a concept raised frequently 168 in evidence) would address the criticism that shortages of materials and labour arise because demand 169 for them is not explicit and committed. As Peabody stated, “ultimately, the greatest barrier is uncertainty.” 170
Conclusion 101
Concluded (the committee's words)This will be a long-term endeavour: in addition to political will today, new towns will require patient capital for decades to come. Investors will need to be confident that construction of new towns will begin soon and - crucially - will continue, giving them confidence that they will realise a financial return over the longer-term.
Conclusion 102
Concluded (the committee's words)We were pleased to hear that Mr Pennycook “remains absolutely committed “to delivering the new town programme, and that they “will have spades in the ground on at least three [new towns] … in this Parliament”. 171 More than just commitment, we were impressed at this ambition 172 . The next steps will be critical, and publishing the funding plans for each town will be another vital measure in fostering confidence within the sector.
Conclusion 103
Concluded (the committee's words)Throughout our inquiry we heard clear signals from the built environment sector that they would be capable of scaling up manufacturing, skills, and capacity if they believed the programme will go ahead. 173 Moreover, many individuals and organisations expressed a fundamental belief in the principle of the programme, actively wanting to be involved. 174
Conclusion 104
Concluded (the committee's words)If the Government provides commitments that the sector trusted (such as a long -term timetable, build-out targets, funding and sector support) stakeholders could rapidly scale-up production for materials, utilities and skills .
Conclusion 105
Concluded (the committee's words)The new towns programme will fail unless the built environment sector is given a clear message that the Government will deliver as promised, and as necessary. Commit and build
Conclusion 106
Concluded (the committee's words)Mr Pennycook has now appeared twice in front of the Committee to discuss the new towns programme. Both times he has reiterated his support of the new towns, and indeed support from wider government, stating during the most recent evidence session that they “have a commitment from every department in government”. 175
Conclusion 107
Concluded (the committee's words)Despite this, witnesses have repeatedly told us that they believe more can be done. 176 Over the course of this inquiry, we have been impressed at the capabilities, ambition, and drive of the built environment sector, and we believe that if given the correct signals, they are capable of realising and delivering the Government’s vision of exemplary new settlements.
Conclusion 108
Concluded (the committee's words)Central Government must take overall control of the new towns programme and should treat it as a major national project. All the problems identified in this report could be solved more easily if the key players involved could be sure that current government is committed to seeing the programme through to completion. Developers, the construction sector, training providers, utility firms and others all need the confidence to invest and expand production. New towns could be a powerful stimulant for this, but only if the key players involved can trust the Government’s commitment to the programme.
Conclusion 109
Concluded (the committee's words)The original New Towns of the mid-twentieth century were not ancillary to the then Government’s housing policy. Rather, they were a deliberate and central part of national government policy and were key to achieving the housebuilding targets of the day. Those New Towns and the planning and design principles behind them—for better or worse—continue to shape the UK’s built environment to this day. 177
Conclusion 110
Concluded (the committee's words)Today’s Government can only expect the same magnitude of impact and achievement if they are prepared to undertake the work and expend the funding needed to deliver the next generation of new towns. Otherwise, they will be setting the built environment sector and the wider public up for disappointment.
Conclusion 111
Concluded (the committee's words)Government commitment is needed to give confidence to interested parties at all stages in the building process. For example, suppliers of building materials will need to be sure that the Government is committed to projects of this scale before they make the capital investment necessary to increase output. 178 Likewise, housebuilding firms will only seek involvement in new towns if they can expect the Government to follow-through and permit the construction of large, cohesive settlements, with links to transport and infrastructure, which will give them an acceptable return on investment. 179
Conclusion 112
Concluded (the committee's words)Dr Budzier gave the example of the cancellation of the northern leg of HS2 to show why, by analogy, interested parties required Government commitment to the new towns programme. He said that the cancellation of the northern leg “led to a massive deficit of trust”. 180 He added that the effect of low confidence on the new towns programme is that “nobody in the industry wants to invest in capabilities. Saying that this [the new towns programme] will be cancelled now will have exactly the same effect of people saying, “Well, why did I hire all these apprentices then? I believed the Government”, and there will be a trust deficit again.” 181
Conclusion 113
Concluded (the committee's words)It is therefore up the Government to provide basic guarantees that they want these megaprojects to happen. Only then will then will the other key interested parties in this process—skills providers, producers of building materials, local authorities, utilities providers and more—feel able to commit to playing their essential part in the delivery of the new towns.
Recommendation 114
Recommended (the committee's words)Ultimately, therefore, the Government must decide whether they really want to deliver the next generation of new towns. To undertake this programme in a half-hearted and desultory manner would lead to failure, because none of the other interested parties needed to make new towns a success will be able to make the long-term commitment to contribute. This is therefore a policy that the Government must pursue relentlessly—in partnership with housebuilders, colleges, industry and wider society—or one that they should give up on.
Recommendation 115
Recommended (the committee's words)The Government must fully commit to taking ownership of the success of the new towns programme , or risk further weakening the confidence of built environment stakeholders that the Government is willing and able to deliver megaprojects .
Recommendation 116
Recommended (the committee's words)The Government must establish all development corporations or equivalent delivery bodies for the new towns programme within three months of the final selection of the sites.
Conclusion 117
Concluded (the committee's words)We will soon by approaching two and a half years since this Government came to power. There has been a consultation and the launch of a taskforce, but construction — or even the final selection of new towns locations — are yet to take place. Therefore , alongside commitments to the urban extensions and urban regeneration projects , construction work must begin on at least one standalone new town within the lifetime of this parliament. 163 Written evidence from Henley Business School, , University of Reading ( NTB0011 ) and Places for People ( NTB0028) 164 Written evidence from Peabody ( NTB0037 ), Q 25 (Alison Crofton) 165 Written evidence from Dr Nigel Moor and Prof Doug Clelland ( NTB0015 ) 166 Written evidence from the National House Building Council ( NTB0026 ) 167 Q 72 (Minister of State for Housing and Planning) 168 Written evidence from Mr Pierre Bidaud ( NTB0008 ) and City & Guilds ( NTB0014 ), Dr Tariq Umar ( NTB0017 ), Royal Institute of British Architects ( NTB0024 ) and Mr Rami Saadi ( NTB0027 ) 169 Q 18 (Simon Rawlinson) 170 Written evidence from Peabody ( NTB0037 ) 171 Q 50 (Minister of State for Housing and Planning) 172 Ibid. 173 See for example QQ 4 (David Hopkins), 6 (Katherine Adams), 21 (Sam Egan) 174 See for example QQ 6 (Katherine Adams), 15 (Simon Rawlinson), 29 (Richard Cook) 175 Q 63 (Minister of State for Housing and Planning) 176 See for example QQ 4 (David Hopkins), 6 (Katherine Adams), 25 (Richard Cook) 177 Q 46 (Dr Alex Budzier) 178 Q 6 (David Hopkins) 179 Q 25 (Richard Cook) 180 Q 56 (Dr Alex Budzier) 181 Ibid. < Back Next > © Parliamentary copyright 2026 A-Z index Glossary Contact us Freedom of Information Jobs Using this website Copyright Privacy notice Cookie policy Cookie Manager House of Lords - New Towns: Commit and Build - Built Environment Committee Accessibility Email alerts RSS feeds Contact us Home Parliamentary business MPs, Lords & offices About Parliament Get involved Visiting Education House of Commons House of Lords What's on Bills & legislation Committees Publications & records Parliament TV News Topics New Towns: Commit and Build Contents
Reports
1st Report - New Towns: Commit and Build
- HC No.
- Not recorded
- Published
- 15 Oct 2026
- Items
- 117
- Government response
- Government response awaited: deadline 15 December 2026.
Oral evidence sessions
On smaller screens, scroll horizontally to read every column. Keyboard users can focus the table region and use the arrow keys.
| Date | Session and witnesses | Source |
|---|---|---|
| 1 Sep 2026 |
Built Environment Committee Meeting
Lise-Anne Boissiere · Ministry of Housing, Communities and Local Government,
The Rt Hon Matthew Pennycook MP · Ministry of Housing, Communities and Local Government
|
View ↗ |
| 14 Jul 2026 |
Built Environment Committee Meeting
Dr Alexander Budzier · Saïd Business School, University of Oxford,
Professor Juliano Denicol · University College London (UCL)
|
View ↗ |
| 7 Jul 2026 |
Built Environment Committee Meeting
John Marsh · BUUK Infrastructure,
Lawrence Slade · Energy Networks Association,
Stuart Colville · Water UK
|
View ↗ |
| 30 Jun 2026 |
Built Environment Committee Meeting
Alison Crofton · Homes England,
Jonathan Mitchell · Skills England,
Richard Cook · Clarion Housing,
Sam Egan · Bedford Colleges Group,
Simon Rawlinson · Construction Industry Council
|
View ↗ |
| 23 Jun 2026 |
Built Environment Committee Meeting
David Hopkins · Timber Development UK,
Katherine Adams · Alliance for Sustainable Building Products,
Rebecca Larkin · Construction Products Association
|
View ↗ |
Written evidence
On smaller screens, scroll horizontally to read every column. Keyboard users can focus the table region and use the arrow keys.
Who gave evidence
On smaller screens, scroll horizontally to read every column. Keyboard users can focus the table region and use the arrow keys.
| Witness | Organisation | Sessions |
|---|---|---|
| Alison Crofton · Chief Regional Development Officer | Homes England | 1 |
| David Hopkins · Chief Executive | Timber Development UK | 1 |
| Dr Alexander Budzier · Fellow in Management Practice | Saïd Business School, University of Oxford | 1 |
| John Marsh · Chief Innovation Officer | BUUK Infrastructure | 1 |
| Jonathan Mitchell · Deputy Director | Skills England | 1 |
| Katherine Adams · Technical Director | Alliance for Sustainable Building Products | 1 |
| Lawrence Slade · Chief Executive | Energy Networks Association | 1 |
| Lise-Anne Boissiere · Co-Director for New Towns, Infrastructure and Housing Delivery | Ministry of Housing, Communities and Local Government | 1 |
| Professor Juliano Denicol · Professor of Megaproject Management | University College London (UCL) | 1 |
| Rebecca Larkin · Head of Construction Research | Construction Products Association | 1 |
| Richard Cook · Chief Development Officer | Clarion Housing | 1 |
| Sam Egan · Group Director of Construction | Bedford Colleges Group | 1 |
| Simon Rawlinson · Deputy Chair | Construction Industry Council | 1 |
| Stuart Colville · Deputy CEO | Water UK | 1 |
| The Rt Hon Matthew Pennycook MP · Minister of State for Housing and Planning | Ministry of Housing, Communities and Local Government | 1 |
Meetings & visits
On smaller screens, scroll horizontally to read every column. Keyboard users can focus the table region and use the arrow keys.
| Date | Type | Detail | Source |
|---|---|---|---|
| 15 Sep 2026 | Formal meeting (private meeting) | Built Environment Committee Meeting · Room 4A, Palace of Westminster | |
| 8 Sep 2026 | Formal meeting (private meeting) | Built Environment Committee Meeting · Room 4A, Palace of Westminster |