Themes | Environment & Climate | The Accountability Index

Electricity Grid Connection Delays

Recent grid connection reforms failing to reduce queue times, which continue to lengthen, hindering energy infrastructure development.

Strongest theme matches

Mixed across source types and ranked by classifier confidence plus text match strength.

Indicative ranking
Committee recommendation
100match
#19 - Electricity grid connection processes remain unfit for purpose, delaying charge point rollout
Public Accounts Committee
As with motorway service areas, many of these locations are limited by the strength of the local electricity network and the ability to enhance and connect to it. The Government recognises that the processes to receive electricity grid connections are increasingly unfit for purpose and take too long, and the Department for Energy Security and Net Zero and...
Matched on terms: connection, delay, electricity, grid
Committee recommendation
100match
#11 - Strengthen NPS guidance on grid connection weight and clarify future connection prospects assessment.
Energy Security and Net Zero Committee
The National Policy Statements should give significant weight to the availability of a grid connection, as a paramount consideration in determining where electricity generation projects can be located. However, by the same token, where a project has not yet secured a grid connection, the prospects of doing so should also be a material consideration weighing for or against...
Matched on terms: connection, electricity, grid
Committee recommendation
95match
#45 - Enable National Grid ESO to require projects meet strengthened grid connection milestones.
Business, Innovation, Science and Trade Committee
The UK’s “first come first served” approach to grid connections is failing to deliver the volume of connections required. Projects which may be speculative or slow-moving risk being prioritised over those that are more viable. While we welcome National Grid ESO’s five-point plan to tackle queue management issues at the transmission level, we do not believe this has...
Matched on terms: connection, grid
Committee recommendation
95match
#41 - Inadequate grid network capacity and connection delays are hampering low-carbon power delivery.
Business, Innovation, Science and Trade Committee
A lack of network capacity and delays to securing grid connections are together hampering the delivery of low-carbon power and driving potential investments overseas. For too long, transmission and distribution network owners have been able to delay or avoid the level of anticipatory investment required to deliver a network capable of meeting the needs of the country. Ofgem’s...
Matched on terms: connection, delay, grid
Committee recommendation
95match
#24 - Government delay in shore power policy for UK ports is unwelcome during grid connection challenges.
Environmental Audit Committee
It is regrettable that the Government has changed course on its policy on the provision of shore power to UK ports. In a period where grid connections are currently at a premium and demand for electricity supply is increasing, the delay in determining policy on how to provide power to the zero-emission ports of the future is unwelcome.
Matched on terms: connection, delay, electricity, grid
Committee recommendation
95match
#10 - Review interaction between development consent and grid connection application processes for greater coordination.
Energy Security and Net Zero Committee
There needs to be more coordination between the application processes for development consent and a grid connection, given that each is highly relevant to the other and both will be influenced by the Clean Power 2030 Action Plan, the Strategic Spatial Energy Plan, and the Land Use Framework. It is essential that developers are not left stuck in...
Matched on terms: connection, grid
Committee recommendation
94match
#31 - First Report - Grid Capacity in Wales
Welsh Affairs Committee
The grid network has been built piecemeal on the basis of the energy needs of the nation over time. The energy system in the UK is changing and electricity grid network design needs to adapt to meet this change. We are encouraged to see the Government shifting to a more strategic, planned approach to the network and welcome...
Matched on terms: electricity, grid
Committee recommendation
93match
#8 - 3rd Report - The cost of energy
Energy Security and Net Zero Committee
With electricity demand rising after years of decline and much existing infrastructure ageing, new infrastructure will be needed with concomitant costs. The energy transition needs a grid that can accommodate more distributed generation but, which by design, will experience higher constraints. The pace of connections reform is crucial if billpayers are to see the benefits of the Clean...
Matched on terms: connection, electricity, grid
Committee recommendation
90match
#29 - First Report - Grid Capacity in Wales
Welsh Affairs Committee
The UK Government should use National Grid ESO’s Future Energy Scenarios to work with energy companies and grid infrastructure owners to determine areas where anticipatory investment in grid infrastructure would be justified to achieve net zero targets. Where anticipatory investment in grid infrastructure is deemed justified, the UK Government should encourage the development of multi-connection substations in order...
Matched on terms: connection, grid
Committee recommendation
85match
#95 - 1st Report - EV strategy: rapid recharge needed
Environment and Climate Change Committee
We welcome the recently announced Connections Action Plan and urge the Government to move quickly to implement the crucial changes to address the delays currently experienced in the queue for grid connections. We recommend that the Government considers how best to prioritise EV chargepoints in the queue as projects of strategic and national importance.
Matched on terms: connection, delay, grid
Committee recommendation
85match
#11 - 1st Report - Get connected: How community energy can turbocharge the transition
Energy Security and Net Zero Committee
The lack of progress towards the delivery of the 8GW of community energy by 2030 highlights the need for the Government to reduce the disproportionately high costs and long delays community energy projects face when seeking grid connections. (Conclusion, Paragraph 48)
Matched on terms: connection, delay, grid
Committee recommendation
83match
#42 - 1st Report - Long-duration energy storage: get on with it
Science and Technology Committee
Ofgem and the ESO should reduce the grid connection queue urgently and speed up timelines to connect projects to the grid. They should publish updates on how the reforms are progressing reducing the queue of proposed projects. They should consider prioritising storage projects for accessing the queue given their additional benefits such as alleviating grid constraints as well...
Matched on terms: connection, grid
Committee recommendation
83match
#41 - 1st Report - Long-duration energy storage: get on with it
Science and Technology Committee
We heard from would-be long-duration energy storage project developers that connecting to the grid is a barrier that can prove fatal to projects. The Committee welcomes the recent announcement that Ofgem is reforming the queue to remove non-viable projects, as well as the reforms proposed in the Connection Action Plan. This will be critical to ensuring a pipeline...
Matched on terms: connection, grid
Committee recommendation
82match
#9 - First Report - Grid Capacity in Wales
Welsh Affairs Committee
Upfront connection costs can be prohibitive and prevent the development of energy projects. This results in a “chicken and egg” situation whereby developers wait for other developers to commit to the funding of connection costs.
Matched on terms: connection, grid
Committee recommendation
81match
#94 - 1st Report - EV strategy: rapid recharge needed
Environment and Climate Change Committee
We recommend that the Government designate low-carbon and renewable energy generation projects as strategically important net zero projects and fast track their progress through permitting and grid connection to achieve a decarbonised electricity grid as soon as possible and to support consumer confidence in EVs as a low-carbon technology.
Matched on terms: connection, electricity, grid
Committee recommendation
80match
#32 - First Report - Grid Capacity in Wales
Welsh Affairs Committee
Due to the urgency of the situation the UK Government needs to take control of electricity grid network design by setting deadlines and targets for Ofgem, grid Grid capacity in Wales 41 infrastructure owners and other significant bodies including National Grid ESO. The UK Government needs to provide the leadership and strategic planning to deliver a complicated set...
Matched on terms: electricity, grid
Committee recommendation
80match
#3 - First Report - Grid Capacity in Wales
Welsh Affairs Committee
To ensure that communities and business in Wales can decarbonise in line with government targets, grid infrastructure must be able to meet the projected increase in demand for electricity. The evidence we received suggested that the grid in Wales will not be suitable to facilitate the decarbonisation of heat and transport across Wales.
Matched on terms: electricity, grid
Committee recommendation
78match
#6 - First Report - Grid Capacity in Wales
Welsh Affairs Committee
We recognise the strengths of an electricity grid that serves the whole of Great Britain. However, we conclude that there are distinct challenges and opportunities relating to grid infrastructure in Wales that require specific focus and intervention from the UK Government.
Matched on terms: electricity, grid
Committee recommendation
78match
#5 - First Report - Grid Capacity in Wales
Welsh Affairs Committee
We recommend that the UK Government task the new Electricity Networks Commissioner to determine the grid infrastructure necessary to enable industry, communities and businesses in Wales to decarbonise heat and transport in line with net zero targets.
Matched on terms: electricity, grid
Committee recommendation
77match
#44 - 1st Report - New Towns: Commit and Build
Built Environment Committee
New towns will therefore compete with new and increased demand for electricity connectivity and supply. While they are critical for economic growth, the rapid development of data centres presents a challenge to the utilities industries, as they have significant water and energy uses. 69 New towns are being strategically located in areas with potential for economic growth and...
Matched on terms: electricity, grid
Committee recommendation
76match
#33 - First Report - Grid Capacity in Wales
Welsh Affairs Committee
As well as considering the grid in Wales as part of a Great Britain enterprise, the UK Government must recognise the distinctive challenges and opportunities associated with the grid in Wales. The UK Government should engage directly and regularly with the Welsh Government to deliver a coordinated and strategic approach to electricity grid network design.
Matched on terms: electricity, grid
Committee recommendation
76match
#30 - First Report - Grid Capacity in Wales
Welsh Affairs Committee
In order to utilise the opportunities for renewable energy generation in Wales a system of anticipatory investment in grid infrastructure needs to be created and implemented urgently. In the government response to this report, we request further information on the nature of the changes to Ofgem’s powers and the timeline for this to be implemented. The UK Government...
Matched on terms: grid
Committee recommendation
73match
#56 - 1st Report - Long-duration energy storage: get on with it
Science and Technology Committee
Transportation and transmission networks for hydrogen and electricity will need to be substantially improved and expanded. There is a need for sensible coordination in the design of hydrogen and electricity systems. Co-locating electrolysers and hydrogen-to-power generation with storage seems the most efficient option, but this will require significant electricity transmission infrastructure connecting storage sites to generation and to...
Matched on terms: electricity, grid
Committee recommendation
73match
#1 - 1st Report - Long-duration energy storage: get on with it
Science and Technology Committee
Energy storage can provide benefits to the grid. It can reduce curtailment and grid congestion, avoiding wasting energy and reducing the cost of renewable electricity. Energy storage facilities provide power that can be turned on and off at will, enhancing grid flexibility. Long-duration energy storage therefore reduces costs elsewhere in the system and allows a greater proportion of...
Matched on terms: electricity, grid
Committee recommendation
73match
#13 - 6th Report - The UK-US economic relationship: 250 years on
Business, Innovation, Science and Trade Committee
To improve investment into the UK, the Government should focus on the factor conditions rather than government-to-government deals. These are competitive energy costs, faster grid connections, expeditious planning processes, and governance simplicity for investors. We reiterate the recommendations in our recent report on Investing in the UK economy. (Recommendation, Paragraph 68)
Matched on terms: connection, grid
Committee recommendation
73match
#10 - 1st Report - Get connected: How community energy can turbocharge the transition
Energy Security and Net Zero Committee
The grid connection reforms process has not benefitted community energy. The regulatory framework disproportionately disadvantages community energy projects compared to commercial developers and jeopardises their financial viability. The lack of a regulatory definition, ownership agnosticism and the absence of clear mandates for the delivery of the 8GW raises concerns as to how this target can be achieved. (Conclusion,...
Matched on terms: connection, grid
Committee recommendation
71match
#93 - 1st Report - EV strategy: rapid recharge needed
Environment and Climate Change Committee
We welcome recent announcements to improve queue management for transmission projects and to speed up the time needed to build new transmission infrastructure. However, these still do not allow for strategic prioritisation of low-carbon or renewable energy projects ahead of other energy generation. In order for the positive environmental impact of EVs to be maximised, they need to...
Matched on terms: grid
Committee recommendation
70match
#24 - First Report - Grid Capacity in Wales
Welsh Affairs Committee
We recommend that the Government engage directly with community energy projects in Wales to understand the difficulties they face connecting to the grid. The UK Government should lead a working group made up of the Welsh Government, grid infrastructure owners, energy companies and communities to explore how access to the grid for community energy projects can be improved...
Matched on terms: grid
Committee recommendation
70match
#8 - First Report - Grid Capacity in Wales
Welsh Affairs Committee
We note the work by the Welsh Government to develop a long-term plan for energy networks in Wales and call on the UK Government to explain how it is engaging with this. The UK Government needs to explain how it is taking into account Wales-specific 38 Grid capacity in Wales challenges and opportunities when considering grid design and...
Matched on terms: grid
Committee recommendation
70match
#7 - First Report - Grid Capacity in Wales
Welsh Affairs Committee
The Committee welcomes that Celtic Sea projects have been included in the list of infrastructure projects in the UK Government’s Growth Plan and notes the recent decision by The Crown Estate to seek to accelerate the leasing process where possible. This appears only to be possible in Wales if improvement to grid infrastructure is also accelerated and we...
Matched on terms: grid
Committee recommendation
70match
#18 - Complex electricity network decisions demand earlier strategic settlement and community involvement.
Energy Security and Net Zero Committee
The complex judgments involved in evaluating different options for electricity network infrastructure not only raise a strong argument for settling these strategic considerations at an earlier stage, but also heighten the need for affected communities to be involved in those decisions. (Conclusion, Paragraph 53)
Matched on terms: electricity
Committee recommendation
70match
#17 - Review removing specific electricity distribution infrastructure from NSIP regime for faster delivery.
Energy Security and Net Zero Committee
The Government should review whether some types of electricity distribution infrastructure should be removed from the Nationally Significant Infrastructure Projects regime and instead consented under section 37 of the Electricity Act 1989, to speed up delivery critical to Clean Power by 2030. These may include 132kV wood poles. (Recommendation, Paragraph 49) The role of community engagement in building...
Matched on terms: electricity
Committee recommendation
69match
#11 - Strengthen National Policy Statement for Ports to support shore power and electric vessel charging
Transport Committee
The Government should strengthen the National Policy Statement for Ports to better support the provision of shore power and electric vessel charging infrastructure as decarbonisation options, recognising the critical interface between ports and the energy grid. It would also assist in reducing pollution from ships which affects nearby communities. The NPS should clearly set 32 out expectations for...
Matched on terms: grid
Committee recommendation
66match
#23 - First Report - Grid Capacity in Wales
Welsh Affairs Committee
We have heard that community energy projects face specific difficulties in connecting to the grid, and that the UK Government is not aware of those difficulties.
Matched on terms: grid
Committee recommendation
66match
#4 - First Report - Grid Capacity in Wales
Welsh Affairs Committee
While we understand that the UK Government must consider the energy and network needs of the UK as a whole, we consider that it would be inequitable if the UK were to benefit from Wales’ natural resources for renewable energy generation while Welsh households, businesses and industry were not adequately connected to the grid.
Matched on terms: grid
Committee recommendation
66match
#42 - Accelerate investment in future grid capacity ahead of need to prevent generation curtailment costs.
Business, Innovation, Science and Trade Committee
We join many other organisations from across the sector in calling on Ministers, Ofgem and network owners to help recover lost ground by accelerating investment in future grid capacity now ahead of need. The increasing costs associated with turning off generation sites due to a lack of transmission capacity must be halted. Investment should be considered to increase...
Matched on terms: grid
Committee recommendation
65match
#43 - 1st Report - New Towns: Commit and Build
Built Environment Committee
New towns will need to be connected to the National Grid before houses can be occupied. The Grid will need to meet the increase in demand which new towns will require. In addition to these challenges, the construction of new towns will occur at a time when the UK is transitioning away from fossil fuels towards an electrified...
Matched on terms: grid
Committee recommendation
61match
#57 - 1st Report - Long-duration energy storage: get on with it
Science and Technology Committee
There is an urgent need for key strategic decisions and investment into the transportation networks for both electricity and hydrogen. These network decisions should support the deployment of large-scale long-duration energy storage and a strategic energy reserve. These decisions should be communicated as part of the Strategic Spatial Energy Plan and delivered by a cross-departmental Ministerial Working Group,...
Matched on terms: electricity
Committee recommendation
61match
#11 - 1st Report - Long-duration energy storage: get on with it
Science and Technology Committee
There are long lead-in times for delivering energy storage—typically estimated around 7–10 years for most technologies. If the Government waits until there is a clear picture of exactly how supply, demand and the energy system will evolve, it cannot possibly develop storage in time for a decarbonised grid by 2035.
Matched on terms: grid
Committee recommendation
61match
#13 - Second Report - Renewable energy in Wales
Welsh Affairs Committee
The UK Government should focus on maintaining a close working relationship with the Welsh Government, particularly in regard to major energy systems challenges such a grid capacity and port infrastructure. To facilitate effective collaboration, where renewable energy projects in Wales are under consideration, the UK Government should invite Welsh Government Ministers to attend and participate in the Ministerial...
Matched on terms: grid
Committee recommendation
61match
#2 - Fourth Report - Renewable energy in Scotland
Scottish Affairs Committee
The grid is critical for renewable energy to reach consumers. Urgent investment is needed in the grid to ensure that net zero targets are met. The grid needs to be reinforced and expanded to ensure that renewable energy generated in Scotland can connect to the grid and benefit the rest of the UK. We recommend that Ofgem completes...
Matched on terms: grid
Committee recommendation
57match
#99 - 1st Report - EV strategy: rapid recharge needed
Environment and Climate Change Committee
We recommend that the Government define and label grid upgrades to support chargepoint installations as ‘Nationally Critical Infrastructure’ projects and prioritise the grid upgrades needed to deliver EV infrastructure.
Matched on terms: grid
Committee recommendation
57match
#2 - 1st Report - Long-duration energy storage: get on with it
Science and Technology Committee
Domestic energy storage is not just about a resilient decarbonised grid—it is about the security and stability of the whole economy. The global energy crisis that began in 2021 has been an object lesson in the UK’s vulnerability to global wholesale energy price fluctuations, and the consequent effects on inflation. The UK had less storage capacity than comparator...
Matched on terms: grid
Committee recommendation
53match
#100 - 1st Report - EV strategy: rapid recharge needed
Environment and Climate Change Committee
The Committee heard that under current planning regulations, the full planning and land rights process is triggered even for small amounts of upgrade work. This process can be further delayed if landowners do not reach a negotiated settlement. All of this can add significant delays to relatively straightforward upgrade work.
Matched on terms: delay
Committee recommendation
53match
#98 - 1st Report - EV strategy: rapid recharge needed
Environment and Climate Change Committee
We recommend that the Government consult Ofgem and industry to identify opportunities to increase anticipatory investment in grid upgrades for the distribution network to future-proof local grids for the EV transition.
Matched on terms: grid
Committee recommendation
53match
#10 - 1st Report - Clean Power by 2030: A fair deal for Scotland?
Scottish Affairs Committee
Grid capacity is one of the biggest barriers to achieving Clean Power by
Matched on terms: grid
Committee recommendation
45match
#7 - 3rd Report - The cost of energy
Energy Security and Net Zero Committee
Furthermore, there is an immediate need to improve the capacity of interconnectors and we recommend that the Government should secure the removal of barriers to efficient cross-border trading by Winter 2026. (Recommendation, Paragraph 36) Network costs
Matched on classifier match
Committee recommendation
45match
#96 - 1st Report - EV strategy: rapid recharge needed
Environment and Climate Change Committee
We recommend that the Government considers how best to prioritise EV chargepoints in the queue as projects of strategic and national importance.
Matched on classifier match
Committee recommendation
41match
#101 - 1st Report - EV strategy: rapid recharge needed
Environment and Climate Change Committee
We recommend that the Government review the planning regulations for the upgrade of power lines and simplify the process where possible to speed up upgrades, particularly in rural communities while still ensuring proper protection of the environment and heritage.
Matched on classifier match
Committee recommendation
41match
#97 - 1st Report - EV strategy: rapid recharge needed
Environment and Climate Change Committee
We note the changes made to the RIIO price control to allow for more anticipatory investment and emphasise that this additional investment is essential to support chargepoint deployment at pace. However, we heard concern that this may still be insufficient.
Matched on classifier match
← Back to all themes