Public Inquiry
Edinburgh Tram Inquiry
Status: Completed
Chair: Lord Hardie
Established: Oct 2014
Report: Sep 2023
Commissioned by: Scottish Government
Public inquiry into why the Edinburgh Trams project was delivered late, over budget, and with a reduced scope. The project cost £776m against an original estimate of £375m and took 5 years longer than planned.
Response breakdown
Evidence & impact
The Edinburgh Tram Inquiry, chaired by Lord Hardie, examined the planning and construction of Edinburgh's tram system, which experienced significant cost overruns and delays. The inquiry published 24 recommendations in August 2023 focusing on project governance, management practices, and legal reforms.
The Scottish Government accepted 14 recommendations (58%), accepted 7 in principle (29%), and placed 3 under consideration (12%). In its November 2023 response, the Government stated that enhanced procedures for documentation management had been embedded within government and that guidance for establishing inquiries was already in development. The Government noted its commitment to collaborative working through the Verity House agreement, whilst maintaining that responsibility for project delivery remains with councils.
City of Edinburgh Council's Chief Executive reported to the Transport and Environment Committee in November 2023, recommending acceptance of several recommendations. Council Leader Cammy Day acknowledged that "serious mistakes were made in the construction of the original tram line" and noted that processes implemented since the original project had helped deliver the successful Trams to Newhaven extension.
The Council reported that scrutiny of ALEOs had "significantly improved" following reviews in 2012 and 2016, resulting in formalised observer roles and increased committee scrutiny. Training on the Member/Officer Protocol was being delivered to senior officers to clarify the distinction between officer and councillor roles.
Three recommendations regarding civil damages provisions and criminal offences for misleading evidence to inquiries remain under consideration by the Scottish Government, which noted that existing remedies may already exist under delictual liability and fraud law.
Whilst both the Scottish Government and City of Edinburgh Council provided initial responses accepting most recommendations, published evidence of specific implementation actions remains limited for many recommendations, particularly those relating to project management expertise requirements, governance structures, and stakeholder co-location practices.
The Scottish Government accepted 14 recommendations (58%), accepted 7 in principle (29%), and placed 3 under consideration (12%). In its November 2023 response, the Government stated that enhanced procedures for documentation management had been embedded within government and that guidance for establishing inquiries was already in development. The Government noted its commitment to collaborative working through the Verity House agreement, whilst maintaining that responsibility for project delivery remains with councils.
City of Edinburgh Council's Chief Executive reported to the Transport and Environment Committee in November 2023, recommending acceptance of several recommendations. Council Leader Cammy Day acknowledged that "serious mistakes were made in the construction of the original tram line" and noted that processes implemented since the original project had helped deliver the successful Trams to Newhaven extension.
The Council reported that scrutiny of ALEOs had "significantly improved" following reviews in 2012 and 2016, resulting in formalised observer roles and increased committee scrutiny. Training on the Member/Officer Protocol was being delivered to senior officers to clarify the distinction between officer and councillor roles.
Three recommendations regarding civil damages provisions and criminal offences for misleading evidence to inquiries remain under consideration by the Scottish Government, which noted that existing remedies may already exist under delictual liability and fraud law.
Whilst both the Scottish Government and City of Edinburgh Council provided initial responses accepting most recommendations, published evidence of specific implementation actions remains limited for many recommendations, particularly those relating to project management expertise requirements, governance structures, and stakeholder co-location practices.
Reports & milestones
Reports
Timeline
05 Jun 2014
Inquiry Announced
Scottish Ministers established an inquiry into the Edinburgh Tram Project.
· Source
03 Jul 2014
Chair Appointed
Lord Hardie appointed as Chair.
08 Sep 2014
Terms of Referenc…
Inquiry to examine why project was delayed and over budget.
09 Mar 2017
Hearings Begin
Evidence hearings commenced.
31 Jan 2024
Government Respon…
Scottish Government response to recommendations.
Recommendations
| Code | Recommendation | Addressed to | Response | |
|---|---|---|---|---|
| ETI-5 |
Where Business Cases assume pre-contract completion of design, approvals, or utility diversions, contract negotiations should await completion; otherwise, a revised Business Case …
|
Scottish Government | Accepted | View → |
| ETI-6 |
All Business Case versions must include risk assessments accounting for optimism bias per published government guidance.
|
Scottish Government | Accepted | View → |
| ETI-7 |
Each Business Case risk assessment should undergo peer review by external consultants experienced in large-scale transportation infrastructure, submitting reports sufficiently before contract …
|
Scottish Government | Accepted | View → |
| ETI-9 |
Risk identification and management should be integral to major public-sector contracts, employing probabilistic forecasts, critical review of mitigation claims, constant governance challenge, …
|
Scottish Government | Accepted | View → |
| ETI-12 |
For transparency, Scottish Ministers should maintain minutes documenting: discussions and decisions between Ministers and civil servants regarding publicly-funded project involvement; discussions with …
|
Scottish Government | Accepted | View → |
| ETI-13 |
Light rail procurement strategies must adequately address utility location uncertainties, requiring route exposure and clearance well before construction, specifying elapsed time between …
|
Scottish Government | Accepted | View → |
| ETI-14 |
While acknowledging utility diversion approaches, promoters should demonstrate adequate risk management proposals without prescriptive requirements regarding MUDFA versus bow wave methods.
|
Scottish Government | Accepted | View → |
| ETI-15 |
Project promoters should appoint procurement and project managers with qualified, experienced permanent employees who have successfully delivered similar projects on time and …
|
City of Edinburgh Council | Accepted | View → |
| ETI-16 |
Following designer appointment, continuous engagement with promoters, owners, project managers, planning authorities, utility companies, and affected landowners should clarify design criteria, with …
|
City of Edinburgh Council | Accepted | View → |
| ETI-17 |
The governance structure for the delivery of a major project such as a light rail scheme should follow published guidance and ensure …
|
City of Edinburgh Council | Accepted | View → |
| ETI-18 |
There should be effective communication and reporting at all stages of the project, including accurate progress reports to councillors and stakeholders, with …
|
City of Edinburgh Council | Accepted | View → |
| ETI-19 |
At all stages of the project there should be a collaborative approach to delivering it, including co-location of representatives from each organisation …
|
City of Edinburgh Council | Accepted | View → |
| ETI-20 |
The directors, employees and consultants of the company responsible for the procurement and delivery of the project as project managers, including an …
|
City of Edinburgh Council | Accepted | View → |
| ETI-21 |
Local authority officials should be mindful at all times of the distinction in roles between them and councillors, who are solely responsible …
|
City of Edinburgh Council | Accepted | View → |