Completed · Chair: Lord Hardie · Established July 2014 · Commissioned by Scottish Government

Public inquiry into why the Edinburgh Trams project was delivered late, over budget, and with a reduced scope.

More about this inquiry

Public inquiry into why the Edinburgh Trams project was delivered late, over budget, and with a reduced scope. The project cost £776m against an original estimate of £375m and took 5 years longer than planned.

Where it stands

Public hearings were held on 59 days between September 2017 and May 2018.

Edinburgh Tram Inquiry Report was published on 19 September 2023.

The most recent government response on the record is Response to the Edinburgh Tram Inquiry (item 7.1), dated 14 December 2023.

Government response (24 recommendations)

Delivery (the addressees’ latest statements)

  • No statement from Scottish Government found in the sources searched 17
  • No statement from City of Edinburgh Council found in the sources searched 7

Record checked against the sources 31 January 2026. Latest activity 14 December 2023.

Latest on the recommendations

All 24 recommendations

Reports

Reports and timeline

Recent milestones

  • Inquiry Closed1 September 2026
  • Government Response31 January 2024
  • Final Report Published19 September 2023
Full timeline

Costs

£13,200,000

Reported cost Costs in detail

Parliament

2

mentions in Parliament Parliamentary activity

Recommendations

1 shown (filtered)
Clear filters

ETI-4: Inquiry Cost Transparency

Not accepted · Not Accepted

Recommended

In reporting the cost of a public inquiry Scottish Ministers should report its net cost to the public purse, after discounting expenditure already incurred on accommodation, staff and other resources, as well as the total cost appearing in the accounts of the sponsor department.

Since then (summary written by this site)

In November 2023, Màiri McAllan, Cabinet Secretary for Transport, Net Zero and Just Transition, stated that she did not agree with the recommendation to present only net inquiry costs less accommodation and staff, adding that "Full transparency on costs and publication of them are in the public interest" (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).

Addressed to Scottish Government · Full record

Reports and timeline

Timeline

Inquiry Announced

Scottish Ministers established an inquiry into the Edinburgh Tram Project.

Source

Chair and Terms of Reference announced

Source

Chair appointed by letter

Source

First preliminary hearing

Source

Oral evidence hearings begin

Source

Oral evidence ends

Source

Oral closing submissions concluded

Source

Final Report Published

Report published with 24 recommendations.

Source

Show all 10 milestones

Government Response

Scottish Government response to recommendations.

Inquiry Closed

Lord Hardie notified the First Minister that the inquiry had ended and published an explanatory note.

Source

Parliamentary activity

2 mentions since Mar 2003

European Tram Driver Championship

Early Day Motion House of Commons Christine Jardine · Liberal Democrat

Said: That this House congratulates Edinburgh Trams Drivers Emma White and Jason Moffat on their selection to represent Edinburgh Tram Driver Championship in Warsaw; recognises the skill, expertise and dedication required to compete in the championship which brings together tram drivers from across Europe and beyond; …

EDINBURGH TRAM NETWORK

Early Day Motion House of Commons Mark Lazarowicz · Labour

Said: That this House welcomes the announcement by the Scottish Executive of funding of ú375 million for the proposed Edinburgh tram network; and urges elected representatives at all levels of government in Scotland to put their backing behind these proposals which will benefit the wider Scottish …

View all 2 mentions →

Evidence & impact

AI-generated · 26 Mar 2026
The Edinburgh Tram Inquiry, chaired by Lord Hardie, examined the planning and construction of Edinburgh's tram system, which experienced significant cost overruns and delays. The inquiry published 24 recommendations in August 2023 focusing on project governance, management practices, and legal reforms.

The Scottish Government accepted 14 recommendations (58%), accepted 7 in principle (29%), and placed 3 under consideration (12%). In its November 2023 response, the Government stated that enhanced procedures for documentation management had been embedded within government and that guidance for establishing inquiries was already in development. The Government noted its commitment to collaborative working through the Verity House agreement, whilst maintaining that responsibility for project delivery remains with councils.

City of Edinburgh Council's Chief Executive reported to the Transport and Environment Committee in November 2023, recommending acceptance of several recommendations. Council Leader Cammy Day acknowledged that "serious mistakes were made in the construction of the original tram line" and noted that processes implemented since the original project had helped deliver the successful Trams to Newhaven extension.

The Council reported that scrutiny of ALEOs had "significantly improved" following reviews in 2012 and 2016, resulting in formalised observer roles and increased committee scrutiny. Training on the Member/Officer Protocol was being delivered to senior officers to clarify the distinction between officer and councillor roles.

Three recommendations regarding civil damages provisions and criminal offences for misleading evidence to inquiries remain under consideration by the Scottish Government, which noted that existing remedies may already exist under delictual liability and fraud law.

Whilst both the Scottish Government and City of Edinburgh Council provided initial responses accepting most recommendations, published evidence of specific implementation actions remains limited for many recommendations, particularly those relating to project management expertise requirements, governance structures, and stakeholder co-location practices.
Reforms attributed to this inquiry · AI-generated- Enhanced procedures for minute-taking and documentation management embedded within Scottish Government and Civil Service (Scottish Government statement, November 2023)
- Improved scrutiny arrangements for Arms Length External Organisations (ALEOs) by City of Edinburgh Council, including formalised observer roles and regular committee reporting following 2012 and 2016 reviews
- Member/Officer Protocol training delivered to senior officers at City of Edinburgh Council to clarify distinction between officer and councillor roles
- Guidance for efficient establishment of inquiries developed and shared with recent inquiries (Scottish Government statement, November 2023)
Unfinished business · AI-generated- Recommendations on civil damages provisions and criminal statutory offences for misleading evidence to inquiries remain under consideration by Scottish Government
- No published evidence of action on recommendations regarding project management expertise requirements for light rail projects
- No published evidence of progress on recommendations for governance structure guidance and role clarity in major projects
- No published evidence regarding recommendations on co-location of project stakeholders
- No published evidence of updates to guidance on best practices for light rail delivery, despite Scottish Government stating it already operates in line with best practices

Key facts

Duration: 12 years, 1 month Total reported cost: £13.2m Witnesses: 85 Hearing days: 59 Core participants: 14 Documents disclosed: 6,000,000 Report pages: 961