Select committee: Defence Committee

Service Accommodation

Closed Opened 13 Jul 2023 Closed 3 Sep 2025 8 recommendations 21 conclusions
Inquiry scope (the committee's words)
In this inquiry into Service Accommodation, the Committee is considering current issues with service accommodation; the Ministry of Defence’s plans to improve services and modernise and invest in single living and service families’ accommodation; and what should be included in the Future Accommodation offer. This inquiry was originally conducted during the 2019 Parliament and was interrupted by the 2024 general election. In November 2024 the new Committee agreed to complete the inquiry.

Where it stands

The inquiry is closed, opened 13 July 2023.

The committee has published 1 report, most recently 1st Report – Service Accommodation on 11 December 2024.

The government's response

Published 3 March 2025. The deadline was 11 February 2025.

Summary written by Accountability Index from the government's response. It is not the government's own words.

The MOD accepts most of the Committee's recommendations on service accommodation, partially accepting or agreeing with a small number of conclusions, and points to the Annington buy-back and a forthcoming military housing strategy as the basis for improvement.

  • On damp and mould, the MOD accepts the conclusion and recommendation and says "Detailed statistics will be published as requested by June 2025." It also says cases are likely to continue emerging until the worst housing stock is replaced.
  • The MOD says the Annington buy-back opens the way to a new military housing strategy, "to be published this year", with a stock condition survey to report by 30 April 2025.
  • On the Home Hub portal, the MOD accepts the recommendations and says the DIO "anticipate launching Home Hub to a closed user group in Spring 2025", with wider access once user testing is complete.
  • On winter preparedness and communication of the new accommodation offer, the MOD "partially accepts" conclusion 14 and "partially agrees" with conclusion 25. On the allocation of Service Family Accommodation, it says an announcement "will be made in due course".

Read the government's response ↗ Report an error

Recommendations and conclusions 29 shown

2: DIO's poor contract oversight caused significant problems with FDIS accommodation rollout.

Conclusion · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Concluded (the committee's words)
There have understandably been serious concerns about the Defence Infrastructure Organisation’s contract oversight of the implementation of the FDIS contracts for the maintenance and repair of Service Family Accommodation. DIO is accountable for the fact that there was no contractual relationship between the suppliers and no lead prime to take overall responsibility: this contributed substantially to the problems with the rollout of the new accommodation service. (Conclusion, Paragraph 35)

Link to this item · Read this item

4: Outline assurance processes and review performance measures for service families' satisfaction.

Conclusion · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Concluded (the committee's words)
The DIO and its contractors should outline the assurance processes they have in place to ensure maintenance and repairs meet the needs of service families. The DIO should also review the performance measures in the RAMS and NAMS contracts to assess how they could more effectively take account of service families’ satisfaction. (Recommendation, Paragraph 44)

Link to this item · Read this item

5: MOD's performance recovery claims demand demonstrable improvement in customer experience and trust.

Conclusion · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Concluded (the committee's words)
The MOD’s claims of a recovery in performance need to be borne out in a demonstrable improvement in the customer experience and markedly increased customer satisfaction. Service families’ trust has been affected and the DIO and service providers need to demonstrate a genuine “family first” approach to earn that trust back. (Conclusion, Paragraph 45) 41

Link to this item · Read this item

6: Improved communication on maintenance for service families requires Home Hub portal.

Recommendation · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Recommended (the committee's words)
There needs to be better communication with service families about maintenance work. Part of the solution lies in the introduction of the promised Home Hub portal, to give families access to information about maintenance work and the ability to book their own appointments online. (Conclusion, Paragraph 52)

Link to this item · Read this item

8: Ensure Pinnacle's housing officers effectively resolve issues and complaints with partners.

Recommendation · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Recommended (the committee's words)
If the housing officer role is to continue being undertaken by Pinnacle, then Pinnacle’s representatives must be more effective at resolving outstanding issues and complaints, working collaboratively with their contract partners. (Conclusion, Paragraph 59)

Link to this item · Read this item

9: Summarise findings and outcomes of MOD complaints policy review in report response.

Conclusion · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Concluded (the committee's words)
We understand that MOD were conducting a review of the complaints policy and process, and of the quality of contractors’ responses to complaints to improve the customer experience. We trust that work on this review is now complete and ask the Government to summarise its findings and outcomes in their response to this Report. (Recommendation, Paragraph 60)

Link to this item · Read this item

14: MOD preparedness relied on additional resources, raising concerns for future service levels.

Conclusion · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Concluded (the committee's words)
The MOD successfully delivered in winter 2023–24 on its preparedness planning and carried out the remediation work that it promised. However, this was only achieved through additional resources. Service families need reassurance that DIO and its contractors can continue to provide the same level of service in the future, when substantial emergency uplifts to funding may not be available. (Conclusion, Paragraph 70) 42

Link to this item · Read this item

16: Resolve outstanding damp and mould issues and publish annual remediation statistics by June 2025.

Recommendation · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Recommended (the committee's words)
The DIO must resolve outstanding problems with damp and mould across the estate. In its response to this report, the Government should detail the ongoing work to eliminate damp and mould in SFA, including a timeline for remediation of the Estate as a whole. Detailed statistics should be published by June 2025 on the number of properties affected by damp and mould across the whole of the Defence Estate, and its severity, and these should be updated and published annually thereafter. (Recommendation, Paragraph 74)

Link to this item · Read this item

17: Implement measures to prevent recurrence of overdue gas safety certificates in service accommodation.

Conclusion · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Concluded (the committee's words)
In a situation in which the contractor has no way of gaining entry to service accommodation without the occupier’s consent to carry out safety checks, and no option to cut supply, a very small number of properties are likely to have overdue gas safety certificates. However, the situation in 2023 with overdue certificates had clearly got out of control. The DIO must put in place measures to ensure that a similar situation cannot happen again. (Recommendation, Paragraph 80)

Link to this item · Read this item

19: Review adequacy standards and the assessment process for Single Living Accommodation.

Conclusion · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Concluded (the committee's words)
While we welcome the MOD’s work in parallel with DLUHC to develop a new Enhanced Target Standard (ETS) for SFA, the MOD needs to review not only the standards it uses to assess the adequacy of accommodation, but also critically the assessment process itself. It needs to have justified confidence in both. (Recommendation, Paragraph 87) Single Living Accommodation (SLA)

Link to this item · Read this item

23: New Defence Minimum Standard for SLA welcomed, conditional on rectifying unacceptable conditions.

Conclusion · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Concluded (the committee's words)
The introduction of a new Defence Minimum Standard (DMS) for SLA is a long-awaited and very welcome step forward, if it ensures that personnel are no longer living in unacceptable conditions and does not simply result in sub-standard accommodation being recognised but not rectified. (Conclusion, Paragraph 114)

Link to this item · Read this item

24: Provide update on measuring SLA improvements and impact on morale after new DMS implementation.

Recommendation · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Recommended (the committee's words)
The Government should provide us with an update following the implementation of the new DMS, clarifying how they are measuring improvements to the condition of SLA and to what extent the new standards are making a difference to morale and meeting their expectations. (Recommendation, Paragraph 115) Allocation of Housing

Link to this item · Read this item

25: MoD's communication of new SFA accommodation offer proved inadequate for affected personnel.

Conclusion · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Concluded (the committee's words)
The MoD’s communication of its new accommodation offer for SFA was inadequate for those adversely affected by the policy change, including those with rank-based benefits, to understand and respond to its impact on them. (Conclusion, Paragraph 133)

Link to this item · Read this item

26: Support for pausing SFA accommodation offer review, acknowledging personnel disappointment.

Conclusion · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Concluded (the committee's words)
We support the MOD’s decision to pause and conduct a review of the accommodation offer for SFA because of concerns around retention of personnel. However, we recognise that this decision has caused potential disappointment for the 45,000 personnel in long-term relationships and/ or with non-resident children, who might have hoped to become entitled to SFA in March 2024, and personnel who had expected to benefit from the new needs-based allocation. (Conclusion, Paragraph 134)

Link to this item · Read this item

27: Provide update to Service personnel on SFA allocation approach, timescales, and impact assessment.

Recommendation · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Recommended (the committee's words)
The Government should provide an update to us, and more importantly to Service personnel, on its approach to allocation of SFA, with timescales and metrics for implementation. This should take into account the different needs of the three Services and include a full impact assessment of any potential revisions to the accommodation policy for SFA. (Recommendation, Paragraph 135)

Link to this item · Read this item

28: Mishandling Modernised Accommodation Offer caused personnel grievance, impacting morale and retention.

Conclusion · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Concluded (the committee's words)
By mishandling the implementation of the Modernised Accommodation Offer (MAO), the MOD has created a situation in which groups of service personnel are now more likely to feel aggrieved, whatever form the scheme takes. With a limited supply of housing, some personnel will inevitably lose out. It is vital that the Government manages the morale and retention consequences. (Conclusion, Paragraph 136)

Link to this item · Read this item

29: No announcement made on new accommodation offer for service families after government change.

Conclusion · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Concluded (the committee's words)
The former Minister of State said that the Secretary of State would report the findings from the review in the Summer; however, following the change in Government, there has as of 3 December 2024 been no announcement of a new accommodation offer for service families. (Conclusion, Paragraph 137) 44

Link to this item · Read this item

30: Mandate MOD and Treasury to make substantial, ongoing funding commitments for the Defence estate

Conclusion · 1st Report – Service Accommodation · Addressed to Ministry of Defence

Concluded (the committee's words)
The MOD has acknowledged that current levels of funding are insufficient to bring all service accommodation up to decent, modern standards and that “it is investment that ultimately will lead to the change.” In the current economic climate, and with so many competing pressures on public funds, we are not confident that the sustained investment required will be forthcoming in future Defence budgets. Both the MOD and the Treasury must make substantial and ongoing funding commitments to improve the Defence estate before it deteriorates beyond repair—and before greater numbers of personnel decide to leave the military because of poor accommodation. (Conclusion, Paragraph 142) 45

Link to this item · Read this item

Reports

1 report

Oral evidence sessions

2 sessions

On smaller screens, scroll horizontally to read every column. Keyboard users can focus the table region and use the arrow keys.

Date Session and witnesses Source
27 Feb 2024
Panel 1
James Cartlidge MP · Ministry of Defence, Major General Richard Clements · Ministry of Defence, Mike Green · Defence Infrastructure Organisation, Vice Admiral Philip Hally · Ministry of Defence
View ↗
27 Nov 2023
Panel 1
Claire Kober OBE · Pinnacle Group, Craig McGilvray · Amey, Jerry Moloney · VIVO Defence Services
View ↗

Who gave evidence

7 witnesses

On smaller screens, scroll horizontally to read every column. Keyboard users can focus the table region and use the arrow keys.

WitnessOrganisationSessions
Claire Kober OBE · Managing Director of Homes Pinnacle Group 1
Craig McGilvray · Managing Director for Complex Facilities Amey 1
James Cartlidge MP · Minister for Defence Procurement Ministry of Defence 1
Jerry Moloney · Managing Director VIVO Defence Services 1
Major General Richard Clements · Director Army Basing and Infrastructure Ministry of Defence 1
Mike Green · Chief Executive Defence Infrastructure Organisation 1
Vice Admiral Philip Hally · Chief of Defence People Ministry of Defence 1