Recommendations & Conclusions
43 items
3
Conclusion
Eleventh Report - Decarbonisation of th…
Deferred
An overarching delivery plan for the decarbonisation of power, with clear milestones and contingencies, will help the Government bring a complex set of interrelated tasks together. At the moment, decisions are taken on specific technologies or issues in silos without a roadmap for the whole system. This has led to …
Read more
An overarching delivery plan for the decarbonisation of power, with clear milestones and contingencies, will help the Government bring a complex set of interrelated tasks together. At the moment, decisions are taken on specific technologies or issues in silos without a roadmap for the whole system. This has led to sequencing problems and a failure to take ownership of whole system costs. This was illustrated by National Grid ESO confirming significant constraint payments, largely stemming from a failure to upgrade the transmission grid between Scotland and England. A comprehensive plan will give investors more confidence to deploy new, low-carbon infrastructure in the UK because they will have a clearer understanding of how their projects, and the reforms these depend on, will fit into a decarbonised energy system.
Show less
Government response AI summary
The government, through HM Treasury, focuses on monitoring the impact of international subsidies and leveraging capital allowances to support green industries, committing to engage with industry on tax incentives. It does not commit to developing an overarching delivery plan with clear milestones and contingencies for …
Read full response →
Department for Business and Trade
4
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
We reiterate the calls of both the Climate Change Committee and National Audit Office for the Government to publish a comprehensive, long-term delivery plan for a decarbonised power system by 2035. The creation of a new Department for Energy Security and Net Zero should provide the impetus and Ministerial capacity …
Read more
We reiterate the calls of both the Climate Change Committee and National Audit Office for the Government to publish a comprehensive, long-term delivery plan for a decarbonised power system by 2035. The creation of a new Department for Energy Security and Net Zero should provide the impetus and Ministerial capacity to do this. This plan should recognise the time needed to decarbonise the different aspects of the electricity system as well as the sequencing involved. We recommend that this delivery plan sets out clear roadmaps and milestones as well as contingency plans for key risks and uncertainties. It should also focus on whole system costs. We ask the Government to publish this delivery plan no later than by the end of 2023.
Show less
Government response AI summary
The government's response discusses ongoing work related to Contracts for Difference (CfD) auction parameters, budgets, and engagement with industry, but does not commit to publishing a comprehensive long-term delivery plan for a decarbonised power system by the end of 2023.
Read full response →
Department for Business and Trade
5
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
The Government has set a target to decarbonise the power system by 2035, subject to security of supply. The Government has not defined ‘security of supply’. After 2035, there may be rare occasions when the UK needs to use unabated gas-fired stations to meet shortfalls in supply. A clear definition …
Read more
The Government has set a target to decarbonise the power system by 2035, subject to security of supply. The Government has not defined ‘security of supply’. After 2035, there may be rare occasions when the UK needs to use unabated gas-fired stations to meet shortfalls in supply. A clear definition of ‘security of supply’ is needed to ensure that the Government can be properly held to account for its performance against the 100 Decarbonisation of the power sector 2035 target. The Government should define the ‘subject to security of supply’ condition in its 2035 target and clarify the amount of residual emissions from unabated gas plants that it is willing to accept from 2035 onwards.
Show less
Government response AI summary
The government is undertaking further work and assessing options as part of the wider Review of Electricity Market Arrangements (REMA) but does not provide a definition of 'security of supply' or clarify residual emissions from unabated gas plants.
Read full response →
Department for Business and Trade
6
Conclusion
Eleventh Report - Decarbonisation of th…
Deferred
Announcements by major oil and gas companies to prioritise share buybacks and dividends over investment in renewables, and to scale back on targets to reduce the impact of their operations on the climate in favour of extracting more fossil fuels, suggest that the industry has some way to go before …
Read more
Announcements by major oil and gas companies to prioritise share buybacks and dividends over investment in renewables, and to scale back on targets to reduce the impact of their operations on the climate in favour of extracting more fossil fuels, suggest that the industry has some way to go before it finds a good balance between prioritising profit and its responsibility to cut emissions. The investment relief included in the Energy Profits Levy means that taxpayers will effectively pay oil and gas companies to clean up their own operations. Taxpayer support for oil and gas companies should be contingent on these companies being transparent about their future investments in renewables and low-carbon technologies, and on evidence showing how their plans for decarbonisation are compliant with the country’s statutory carbon budgets and net zero target. (Paragraph 40) Retaining investment in low-carbon energy
Show less
Government response AI summary
The government's response discusses a consultation on community benefits for network infrastructure, coordination with The Crown Estate on transmission links, and tracking offshore wind capacity, but does not address making taxpayer support for oil and gas companies contingent on their transparency or decarbonisation plans.
Read full response →
Department for Business and Trade
8
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
There is a risk that the Government has not accurately reflected rising costs for renewables developers in the budget for this year’s Contracts for Difference auction, putting the viability of future projects into question. We recommend that the Government reviews the parameters set for its Contracts for Difference Allocation Round …
Read more
There is a risk that the Government has not accurately reflected rising costs for renewables developers in the budget for this year’s Contracts for Difference auction, putting the viability of future projects into question. We recommend that the Government reviews the parameters set for its Contracts for Difference Allocation Round 5 to ensure that they accurately reflect the cost pressures facing the sector.
Show less
Government response AI summary
The government's response discusses the important role of onshore wind in achieving net zero targets and the reasons against setting a UK-wide target for its deployment. This completely deflects from the recommendation to review Contracts for Difference Allocation Round 5 parameters to accurately reflect rising …
Read full response →
Department for Business and Trade
9
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
Providing that oil and gas companies utilise their investment allowances included in the Energy Profits Levy, oil and gas extraction will continue to benefit from a lower effective rate of marginal tax than low-carbon developers. This risks offering perverse incentives to investors. We recommend that when investing in low-carbon electricity …
Read more
Providing that oil and gas companies utilise their investment allowances included in the Energy Profits Levy, oil and gas extraction will continue to benefit from a lower effective rate of marginal tax than low-carbon developers. This risks offering perverse incentives to investors. We recommend that when investing in low-carbon electricity technologies, developers should receive an investment allowance rate equivalent to that received by the oil and gas sector. We further recommend that the Government revisits the case for Voluntary Contracts for Difference for low-carbon electricity generators currently subject to the Electricity Generators Levy.
Show less
Government response AI summary
The government's response discusses local decision-making for onshore wind sites and a consultation on changes to the National Planning Policy Framework, failing to address the recommendations regarding investment allowance rates for low-carbon developers or Voluntary Contracts for Difference.
Read full response →
Department for Business and Trade
11
Conclusion
Eleventh Report - Decarbonisation of th…
Deferred
The UK’s offshore wind sector is a success story. The Government has ambitious plans to scale up offshore wind deployment, maximising the potential of the UK’s natural resources. However, unless rapidly addressed, current bottlenecks in the process will stand in the way of the Government achieving its ambition for 50 …
Read more
The UK’s offshore wind sector is a success story. The Government has ambitious plans to scale up offshore wind deployment, maximising the potential of the UK’s natural resources. However, unless rapidly addressed, current bottlenecks in the process will stand in the way of the Government achieving its ambition for 50 GW of offshore wind to be deployed by 2030. While we commend the Government for the work being done to speed up the deployment of offshore wind, and to ensure local communities that host critical transmission infrastructure benefit from doing so, it is unfortunate that the Government is only now consulting in these areas.
Show less
Government response AI summary
The government states it continues to assess the merits of a long-term target for tidal stream deployment and recognizes the need for tailored subsidy mechanisms for tidal range, subject to value for money and evidence from proposed schemes, rather than addressing offshore wind bottlenecks.
Read full response →
Department for Business and Trade
12
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
In response to this report, the Government should set out how it is monitoring progress against its ambition to deploy 50 GW of offshore wind by 2030. The Government should also set out how it will be responding to the recommendations of the UK Offshore Wind Champion. Furthermore, local communities …
Read more
In response to this report, the Government should set out how it is monitoring progress against its ambition to deploy 50 GW of offshore wind by 2030. The Government should also set out how it will be responding to the recommendations of the UK Offshore Wind Champion. Furthermore, local communities which host critical national infrastructure must see tangible benefits from doing so, and connections between offshore wind farms and transmission networks need to be better co-ordinated to minimise disruption for local communities. We ask the Government to set out how it will ensure appropriate oversight of Crown Estate decision-making in respect of social value and impact for local communities.
Show less
Government response AI summary
The government's response discusses the strategic case for nuclear power, the establishment of GBN, and cost management for projects like Hinkley Point C and Sizewell C. This completely deflects from the recommendation concerning monitoring offshore wind targets, responding to the UK Offshore Wind Champion, and …
Read full response →
Department for Business and Trade
13
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
Floating offshore wind offers the potential to expand and diversify the UK’s portfolio of wind projects, including to the Celtic Sea. Significant new investment in UK ports will be needed to enable floating offshore wind to be deployed at scale and to harness local supply chains and manufacturing. The Government’s …
Read more
Floating offshore wind offers the potential to expand and diversify the UK’s portfolio of wind projects, including to the Celtic Sea. Significant new investment in UK ports will be needed to enable floating offshore wind to be deployed at scale and to harness local supply chains and manufacturing. The Government’s Floating Offshore Wind Manufacturing Investment Scheme, though welcome, may not address the key concern of port operators — long term market revenue certainty. To provide ports with the confidence to make long-term investments in the necessary infrastructure for floating offshore wind, the Government should provide policy certainty that de-risks the required investment in ports.
Show less
Government response AI summary
The government's response addresses plans to publish a nuclear roadmap and consult on a nuclear siting strategy later this year. This completely deflects from the recommendation to provide policy certainty to de-risk port investments for floating offshore wind infrastructure.
Read full response →
Department for Business and Trade
14
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
The British Energy Security Strategy did not include a target for onshore wind, even though it is one of the cheapest and quickest sources of renewable electricity to deploy. We recommend that the UK Government works with the Scottish and Welsh Governments to agree a UK-wide target for the deployment …
Read more
The British Energy Security Strategy did not include a target for onshore wind, even though it is one of the cheapest and quickest sources of renewable electricity to deploy. We recommend that the UK Government works with the Scottish and Welsh Governments to agree a UK-wide target for the deployment of onshore wind by 2035, which should inform a specific target to increase the deployment of onshore wind in England.
Show less
Government response AI summary
The government's response details investments through the Nuclear Fuel Fund to support the domestic nuclear fuel supply chain and a strategic civil nuclear partnership with the US. This completely deflects from the recommendation to agree a UK-wide target for onshore wind deployment.
Read full response →
Department for Business and Trade
15
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
We welcome the Government’s decision to review the National Planning Policy Framework but are concerned that the proposed changes do not go far enough to encourage the new onshore wind capacity the country needs. The planning system needs to give more weight to critical infrastructure, such as onshore wind, that …
Read more
We welcome the Government’s decision to review the National Planning Policy Framework but are concerned that the proposed changes do not go far enough to encourage the new onshore wind capacity the country needs. The planning system needs to give more weight to critical infrastructure, such as onshore wind, that is in the national interest. If the Government’s proposed reforms to the National Planning Policy Framework do not result in a substantial increase in the amount of onshore wind development in England, we recommend that the Government brings onshore wind projects back under the regime for National Significant Infrastructure Projects, as we suggested in our report on the Revised (Draft) National Policy Statement for Energy. (Paragraph 78) 102 Decarbonisation of the power sector
Show less
Government response AI summary
The government's response details its £20bn investment in Carbon Capture, Utilisation, and Storage (CCUS), including selected projects and cluster sequencing, but does not address the recommendation regarding onshore wind planning or its classification as critical infrastructure.
Read full response →
Department for Business and Trade
16
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
We are pleased that the Government is looking at how best to support repowered assets. Replacing old onshore wind turbines with new technologies will help reduce the need for new capacity elsewhere. The Government should introduce a framework which supports the retention of existing onshore wind farms and other renewable …
Read more
We are pleased that the Government is looking at how best to support repowered assets. Replacing old onshore wind turbines with new technologies will help reduce the need for new capacity elsewhere. The Government should introduce a framework which supports the retention of existing onshore wind farms and other renewable assets, for example via the Contracts for Difference scheme, when they need to be repowered. The Government should ensure that the planning regime delivers a clear presumption in favour of repowering and life extensions of onshore wind farms.
Show less
Government response AI summary
The government's response describes Ofgem's investigation into Drax Power Limited and provides a general overview of the biomass industry and its sustainability criteria. This completely deflects from the recommendation to introduce a framework and planning presumption for repowering onshore wind farms.
Read full response →
Department for Business and Trade
17
Conclusion
Eleventh Report - Decarbonisation of th…
Deferred
The Government’s aim for 70 GW of solar capacity to be installed by 2035 is welcome. Achieving this goal will require the UK to ramp up the pace at which new solar capacity is deployed. We therefore welcome the Government’s announcement of a solar roadmap and the establishment of a …
Read more
The Government’s aim for 70 GW of solar capacity to be installed by 2035 is welcome. Achieving this goal will require the UK to ramp up the pace at which new solar capacity is deployed. We therefore welcome the Government’s announcement of a solar roadmap and the establishment of a dedicated government/industry taskforce. We strongly welcome the Government’s clarification that it is not planning to change the classification of agricultural land in ways which would constrain the expansion of the UK’s solar capacity.
Show less
Government response AI summary
The government's response discusses its commitment to developing a business model for power BECCS and its support for existing biomass generating stations, rather than addressing the committee's welcome for solar capacity targets or the solar roadmap.
Read full response →
Department for Business and Trade
18
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
We agree that the Government should seek to maximise the renewable opportunities afforded by the UK’s geography, including the potential benefits of tidal energy. Unlike offshore wind, tidal stream projects have not benefited from stable subsidies to bring their costs down. The Government’s recent decision to reduce the tidal steam …
Read more
We agree that the Government should seek to maximise the renewable opportunities afforded by the UK’s geography, including the potential benefits of tidal energy. Unlike offshore wind, tidal stream projects have not benefited from stable subsidies to bring their costs down. The Government’s recent decision to reduce the tidal steam ringfence from £20 million to £10 million in the upcoming round of Contracts for Difference scheme may damage the UK’s first-mover advantage in marine energy and increase project costs. However, we recognise that support must provide value for money for taxpayers.
Show less
Government response AI summary
The government's response discusses developing a business model for power BECCS and setting GHG thresholds, completely ignoring the recommendation about tidal energy funding.
Read full response →
Department for Business and Trade
19
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
The Government should justify the rationale for lowering the ringfenced amount of funding for tidal stream in the latest Contracts for Difference auction, and we invite the future Energy Security and Net Zero Committee to consider that rationale and to challenge it if it thinks necessary. We also ask the …
Read more
The Government should justify the rationale for lowering the ringfenced amount of funding for tidal stream in the latest Contracts for Difference auction, and we invite the future Energy Security and Net Zero Committee to consider that rationale and to challenge it if it thinks necessary. We also ask the Government to consider longer term CfDs for tidal energy, reflecting the longer lifecycle for tidal energy compared to, for example, offshore wind turbines. Industry has requested the setting of a target of tidal stream deployment in order to send further market signals. We ask the Government to consider setting a 1GW target for tidal stream by 2035.
Show less
Government response AI summary
The government's response states it plans to publish a Biomass Strategy and an updated bioenergy resource model, without addressing any aspect of the recommendation regarding tidal stream energy funding or targets.
Read full response →
Department for Business and Trade
20
Conclusion
Eleventh Report - Decarbonisation of th…
Deferred
The British Energy Security Strategy set an ambition for the UK to deploy 24 GW of civil nuclear power by 2050. This significantly raised the level of the Government’s ambition on nuclear power, above estimates suggested by the Climate Change Committee and others. But to be an effective part of …
Read more
The British Energy Security Strategy set an ambition for the UK to deploy 24 GW of civil nuclear power by 2050. This significantly raised the level of the Government’s ambition on nuclear power, above estimates suggested by the Climate Change Committee and others. But to be an effective part of a low-carbon, secure and affordable electricity mix, the cost of nuclear power must come down. Nuclear projects in the UK and elsewhere have been beset with delays and overspends.
Show less
Government response AI summary
The government's response highlights the importance of Greenhouse Gas Removals (GGRs) like BECCS for net zero and outlines deployment ambitions, ignoring the conclusion about nuclear power costs.
Read full response →
Department for Business and Trade
21
Conclusion
Eleventh Report - Decarbonisation of th…
Deferred
In response to this report, we request that the Government sets out: a) its current estimates of the total cost of delivering the Government’s 24 GW ambition; b) its latest official estimate of the total cost of Sizewell C and Hinkley Point C; Decarbonisation of the power sector 103 c) …
Read more
In response to this report, we request that the Government sets out: a) its current estimates of the total cost of delivering the Government’s 24 GW ambition; b) its latest official estimate of the total cost of Sizewell C and Hinkley Point C; Decarbonisation of the power sector 103 c) how it plans to finance its 24 GW ambition, including whether future projects will also adopt the Regulated Asset Base model; and d) the impact of the increasing costs of Hinkley Point C and Sizewell C on its plans for nuclear and how it is ensuring sufficient transparency over such costs.
Show less
Government response AI summary
The government's response details plans to publish standard terms for the low carbon hydrogen production business model and to design new transport and storage business models, completely ignoring the request for information on nuclear power costs and financing.
Read full response →
Department for Business and Trade
22
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
International examples suggest that the best way to bring the cost of nuclear energy generation down is to build a programme of new nuclear reactors, so that supply chains and skills can be developed and transferred from one project to the next. The Government has taken steps in this direction, …
Read more
International examples suggest that the best way to bring the cost of nuclear energy generation down is to build a programme of new nuclear reactors, so that supply chains and skills can be developed and transferred from one project to the next. The Government has taken steps in this direction, with plans to establish a programme of new nuclear projects, supported by Great British Nuclear, and to launch a competition to select the leading small modular reactors. The Government’s nuclear roadmap, due later this year, should set out the options for delivering the nuclear capacity the UK will need by 2050, including options for financing these new projects. Great British Nuclear should advise on how such a programme should be phased, including how to decide how much nuclear capacity is needed and the type of nuclear technologies the UK should deploy and when.
Show less
Government response AI summary
The government's response outlines guidance and standards for hydrogen production projects, committing to minimise leakage and monitor environmental impacts, without addressing the recommendation on the nuclear roadmap or Great British Nuclear.
Read full response →
Department for Business and Trade
23
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
Aside from the need to import uranium, the UK has the capability to undertake critical parts of the nuclear fuel cycle, such as uranium conversion, enrichment and fuel fabrication. The export potential of these strategic assets should be maximised, especially now that countries are looking to reduce their dependence on …
Read more
Aside from the need to import uranium, the UK has the capability to undertake critical parts of the nuclear fuel cycle, such as uranium conversion, enrichment and fuel fabrication. The export potential of these strategic assets should be maximised, especially now that countries are looking to reduce their dependence on Russia for these services. The Government should ensure that critical domestic assets in the nuclear supply chain are supported, while the UK’s current ageing fleet retires.
Show less
Government response AI summary
The government's response details its commitment to designing a hydrogen storage business model by 2025, progress on consultations, and legislative frameworks, along with existing funding programs for hydrogen projects. This completely deflects from the recommendation to support and maximise the export potential of the nuclear …
Read full response →
Department for Business and Trade
24
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
The Government’s recent confirmation of £20 billion investment over 20 years for the early development of Carbon Capture and Storage (CCS) is welcome, allowing the implementation of the initial clusters to commence. However, none of this £20 billion is reflected in the formal budget policy costings, so it is unclear …
Read more
The Government’s recent confirmation of £20 billion investment over 20 years for the early development of Carbon Capture and Storage (CCS) is welcome, allowing the implementation of the initial clusters to commence. However, none of this £20 billion is reflected in the formal budget policy costings, so it is unclear how it will be raised. The Government will need to come forward promptly with clarity for projects involved in the Track 1 expansion and Track 2 clusters. We recommend that the Government announces the cluster sequencing Track-1 expansion projects as quickly as possible and provides further detail on the forward timeline for selecting the next CCS clusters that need to be operational this decade. We urge the Government to provide clarity on how the £20 billion for the early development of CCS will be funded. The Government should develop a robust regulatory regime that tests the carbon capture rates of CCS facilities and penalises failure, which in turn should drive innovation.
Show less
Government response AI summary
The government's response outlines its commitment to developing policy by 2024 to enable investment in large-scale, long-duration electricity storage (LLES) technologies. This completely deflects from the recommendations regarding Carbon Capture and Storage (CCS) cluster announcements, funding clarity, and regulatory regime development.
Read full response →
Department for Business and Trade
25
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
The Committee has been concerned to hear reports about alleged misreporting by Drax to Ofgem in order to draw down public funds. We note that Ofgem has started a special audit process. We call on Ofgem to ensure a thorough investigation of the evidence that supported Drax submissions, specifically in …
Read more
The Committee has been concerned to hear reports about alleged misreporting by Drax to Ofgem in order to draw down public funds. We note that Ofgem has started a special audit process. We call on Ofgem to ensure a thorough investigation of the evidence that supported Drax submissions, specifically in respect of the sourcing of wood biomass, and for Ofgem to request access to any internal or independent external audits undertaken at Drax to investigate this issue. We ask Ofgem to report back to the Committee once this investigation has concluded. (Paragraph 127) 104 Decarbonisation of the power sector
Show less
Government response AI summary
The government's response details investments in energy efficiency, plans for local energy planning, new consumer advice services, and work on improving EPCs, completely ignoring the committee's call for Ofgem to investigate alleged misreporting by Drax.
Read full response →
Department for Business and Trade
26
Conclusion
Eleventh Report - Decarbonisation of th…
Deferred
The UK’s biomass industry is a diverse sector made up of large-scale power plants through to smaller-scale, more local, generators. The overall costs of large-scale bioenergy power plants, which converted from coal-fired plants, are very expensive and rely heavily on imported feedstocks, which may not be produced sustainably, and which …
Read more
The UK’s biomass industry is a diverse sector made up of large-scale power plants through to smaller-scale, more local, generators. The overall costs of large-scale bioenergy power plants, which converted from coal-fired plants, are very expensive and rely heavily on imported feedstocks, which may not be produced sustainably, and which may have significant lifecycle emissions. Existing support schemes for unabated bioenergy are due to end by 2027. We do not believe that the historic allocation of subsidies to large scale biomass, such as Drax, has represented either value for money or the best use of public funds.
Show less
Government response AI summary
The government's response outlines its Action Plan for reforming the planning system for Nationally Significant Infrastructure and plans to publish a consultation document. This completely deflects from the committee's conclusion regarding the costs, sustainability, and value for money of the UK's biomass industry.
Read full response →
Department for Business and Trade
27
Conclusion
Eleventh Report - Decarbonisation of th…
Deferred
We believe that there should be no extension beyond 2027 for taxpayer support for unabated bioenergy plants, and that the aim should be to phase out such plants in favour of more sustainable alternatives as soon as possible. This could include bioenergy with carbon capture and storage but only in …
Read more
We believe that there should be no extension beyond 2027 for taxpayer support for unabated bioenergy plants, and that the aim should be to phase out such plants in favour of more sustainable alternatives as soon as possible. This could include bioenergy with carbon capture and storage but only in a scenario where viable and functioning carbon capture and storage is in use. Further subsidy should not be given to unabated biomass. Any future subsidies should only be provided to companies which can evidence the use of local, waste biomass and not companies that rely on imported biomass.
Show less
Government response AI summary
The government states that its energy National Policy Statements (NPSs) are undergoing a second round of consultation, after which responses will be considered, finalised, and presented to Parliament by the end of the year, deflecting the specific recommendations on bioenergy subsidies to this broader process.
Read full response →
Department for Business and Trade
28
Conclusion
Eleventh Report - Decarbonisation of th…
Deferred
Bioenergy with carbon capture and storage has yet to be commercially deployed in the UK. We have concerns about whether biomass feedstocks can be scaled up sustainably to meet domestic and global demand and whether BECCS facilities will provide value for money. To ensure sufficient oversight of sustainability standards, the …
Read more
Bioenergy with carbon capture and storage has yet to be commercially deployed in the UK. We have concerns about whether biomass feedstocks can be scaled up sustainably to meet domestic and global demand and whether BECCS facilities will provide value for money. To ensure sufficient oversight of sustainability standards, the UK needs to develop domestic supplies of feedstocks. We do not oppose the use of BECCS for power in principle, but future taxpayer support for BECCS must be contingent on: a) robust, transparent evidence that the full lifecycle emissions from BECCS facilities in the UK are carbon neutral within a timeframe compatible with our climate targets; and, b) detailed assessment that BECCS facilities provide value for money.
Show less
Government response AI summary
The government's response outlines plans to introduce recommended funding for community benefits from electricity transmission infrastructure and discussions on supply chain development, without addressing the committee's conditions for future taxpayer support for BECCS.
Read full response →
Department for Business and Trade
29
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
The Government was due to publish a biomass strategy last year, setting out the role of biomass in helping to achieve the Government’s net zero target, including whether biomass would be best used to generate electricity or for other purposes The Government should publish its biomass strategy without delay and …
Read more
The Government was due to publish a biomass strategy last year, setting out the role of biomass in helping to achieve the Government’s net zero target, including whether biomass would be best used to generate electricity or for other purposes The Government should publish its biomass strategy without delay and set out: a) the Government’s assessment of future demand for biomass feedstocks in the UK and globally; b) the extent to which the UK can rely on domestic biomass feedstocks to meet future demand and mechanisms to support domestic biomass supply; and c) the timeframe for scaling up the supply of domestic biomass feedstocks.
Show less
Government response AI summary
The government's response focuses on accelerating new electricity network infrastructure and grid connections, including the work of the Network Commissioner and Ofgem's efforts, completely ignoring the recommendation to publish the biomass strategy.
Read full response →
Department for Business and Trade
30
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
We urge the Government to ensure that there is a robust contingency plan in place if BECCS proves unviable, either in terms of its sustainability or efficiency. We urge the Government not to rely upon unproven technologies at the expense of other simpler and cheaper approaches, which could be taken …
Read more
We urge the Government to ensure that there is a robust contingency plan in place if BECCS proves unviable, either in terms of its sustainability or efficiency. We urge the Government not to rely upon unproven technologies at the expense of other simpler and cheaper approaches, which could be taken now, such as deploying measures to Decarbonisation of the power sector 105 reduce energy demand.
Show less
Government response AI summary
The government's response details its commitment to accelerate new electricity network capacity, manage grid constraints, and implement strategic network planning, without addressing the recommendation for a BECCS contingency plan.
Read full response →
Department for Business and Trade
31
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
Hydrogen looks set to be an important part of a decarbonised power system, both as a source of low-carbon dispatchable power to replace gas and as a source of energy storage which can take advantage of excess supply of renewables. However, given supply constraints, the Government needs to determine the …
Read more
Hydrogen looks set to be an important part of a decarbonised power system, both as a source of low-carbon dispatchable power to replace gas and as a source of energy storage which can take advantage of excess supply of renewables. However, given supply constraints, the Government needs to determine the sectors of the economy in which use of hydrogen will be prioritised. We recommend that the Government takes forward the recommendations of the Climate Change Committee to develop a cross-sectoral infrastructure strategy that narrows the space for future hydrogen uses and finalise the business models for hydrogen this year.
Show less
Government response AI summary
The government's response details Ofgem’s streamlining of regulatory approval for Accelerating Strategic Transmission Investment projects and the appointment of an Electricity Networks Commissioner, without addressing the recommendation on hydrogen strategy or business models.
Read full response →
Department for Business and Trade
32
Conclusion
Eleventh Report - Decarbonisation of th…
Deferred
Blue hydrogen may have value as a transitional measure which builds a market for hydrogen and provides supply over the shorter term. However, excess reliance on blue hydrogen could leave the UK exposed to volatile international gas prices and risk increasing greenhouse gas emissions due to the threat of methane …
Read more
Blue hydrogen may have value as a transitional measure which builds a market for hydrogen and provides supply over the shorter term. However, excess reliance on blue hydrogen could leave the UK exposed to volatile international gas prices and risk increasing greenhouse gas emissions due to the threat of methane leakage. In response to this report, we ask that the Government sets out how its plans for blue hydrogen will address recent evidence that hydrogen emissions escaping from gas pipelines have a stronger warming effect in the atmosphere than previously thought. It should include in that response an account of how it will ensure that efforts to constrain and monitor methane leakage at point of extraction, transportation and storage are robust.
Show less
Government response AI summary
The government's response focuses entirely on improving electricity network connections and reducing connection timescales, including an upcoming Connections Action Plan, without addressing the committee's questions about blue hydrogen, hydrogen emissions, or methane leakage.
Read full response →
Department for Business and Trade
33
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
Whilst the Government’s commitment to delivering hydrogen storage business models by 2025 is welcome, it appears that this could be too late to allow the development of hydrogen storage projects so that they are in operation in time to meet the Government’s target for 10 GW of hydrogen by 2030, …
Read more
Whilst the Government’s commitment to delivering hydrogen storage business models by 2025 is welcome, it appears that this could be too late to allow the development of hydrogen storage projects so that they are in operation in time to meet the Government’s target for 10 GW of hydrogen by 2030, given possible lead times of seven to eight years. In response to this report, the Government should confirm whether it still believes that hydrogen storage projects can be delivered by 2030 and, if so, how that will be achieved.
Show less
Government response AI summary
The government's response details Ofgem's RIIO-ED2 price control, funding for electricity distribution network upgrades to support electric vehicles and heat pumps, and Ofgem's consultation on future network regulation, completely failing to address the recommendation regarding hydrogen storage delivery by 2030.
Read full response →
Department for Business and Trade
34
Conclusion
Eleventh Report - Decarbonisation of th…
Deferred
The deployment of long-duration energy storage is essential to ensuring that a zero- carbon power system can operate 24/7, 365 days a year. These projects are capital intensive and face barriers to deployment due to a lack of long-term market signals. The Government’s 2024 ambition to develop appropriate policy to …
Read more
The deployment of long-duration energy storage is essential to ensuring that a zero- carbon power system can operate 24/7, 365 days a year. These projects are capital intensive and face barriers to deployment due to a lack of long-term market signals. The Government’s 2024 ambition to develop appropriate policy to enable investment in these technologies is welcome, but we are concerned that this has not been made enough of a policy priority.
Show less
Government response AI summary
The government's response highlights Ofgem's RIIO-ED2 price control mechanisms, including flexible funding and enabling strategic investment for network needs. However, it does not directly address the committee's concern about the prioritisation of specific long-duration energy storage policy.
Read full response →
Department for Business and Trade
35
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
We recommend that the Government establishes an appropriate policy framework to support investment decisions in long-duration energy storage this year, to enable projects to be completed by the end of the decade. This includes setting out a target range for long-duration energy technologies and putting in place a revenue stabilisation …
Read more
We recommend that the Government establishes an appropriate policy framework to support investment decisions in long-duration energy storage this year, to enable projects to be completed by the end of the decade. This includes setting out a target range for long-duration energy technologies and putting in place a revenue stabilisation mechanism. We recommend that the Government ensures that there is a sufficient number of staff within the Department working on this crucial policy area. In response to this report, we ask that the Government sets out how many staff are working on developing this policy and how this compares to other teams such as those working on civil nuclear energy.
Show less
Government response AI summary
The government welcomes Ofgem's consultation on the future of local energy institutions and governance, stating it will engage with Ofgem to ensure appropriate arrangements are implemented, potentially legislating. However, it does not directly address the recommendation for a policy framework, targets, revenue stabilisation, or staffing …
Read full response →
Department for Business and Trade
36
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
Energy efficiency is the quickest and most cost-effective way to reduce gas demand and lower household energy bills. If significant strides are not made to reduce demand, it will become increasingly challenging and expensive to decarbonise 106 Decarbonisation of the power sector the electricity system. We call on the Government …
Read more
Energy efficiency is the quickest and most cost-effective way to reduce gas demand and lower household energy bills. If significant strides are not made to reduce demand, it will become increasingly challenging and expensive to decarbonise 106 Decarbonisation of the power sector the electricity system. We call on the Government to bring forward the £6 billion funding package for energy efficiency allocated for the period 2025 to 2028 to now. The Government should prioritise delivering a locally co-ordinated programme of energy efficiency and home retrofit. This should be paired with a communications campaign on the benefits of home improvements and fuel switching. We recommend that the Government uses new powers in the Energy Bill to urgently reform the flawed EPC rating system, so that it gives a more accurate reflection of overall energy use and emissions, as soon as the Bill is enacted. (Paragraph 166) Delivery risks to the Government’s 2035 target
Show less
Government response AI summary
The government's response details Ofgem's mandate and the efficiency targets and funding allocated within electricity network price controls RIIO-ED2 and RIIO-T2, focusing on network costs, but does not address recommendations for energy efficiency funding, home retrofits, communications, or EPC reform.
Read full response →
Department for Business and Trade
37
Conclusion
Eleventh Report - Decarbonisation of th…
Deferred
The planning system, nationally and locally within England and also in Scotland and Wales, is a major constraint on the timely delivery of low-carbon energy infrastructure. There are many reasons for this, some of which we do not cover in this report, and we acknowledge the need for effective controls …
Read more
The planning system, nationally and locally within England and also in Scotland and Wales, is a major constraint on the timely delivery of low-carbon energy infrastructure. There are many reasons for this, some of which we do not cover in this report, and we acknowledge the need for effective controls where justified. But we are in no doubt that steps will need to be taken to accelerate the planning process for low-carbon energy infrastructure.
Show less
Government response AI summary
Ofgem's response describes its stakeholder engagement and consultation processes for the RIIO-ED2 price control, aiming to ensure fair price controls and minimise information asymmetry. This addresses network investment regulation rather than the committee's observation about planning system constraints on low-carbon energy infrastructure.
Read full response →
Department for Business and Trade
38
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
The Government should ensure that bodies within the planning system (such as local authorities, the Planning Inspectorate, and the Marine Management Organisation) are adequately resourced to process and comment on applications faster. The Department for Energy Security and Net Zero should work with the Department for Levelling-Up, Housing and Communities, …
Read more
The Government should ensure that bodies within the planning system (such as local authorities, the Planning Inspectorate, and the Marine Management Organisation) are adequately resourced to process and comment on applications faster. The Department for Energy Security and Net Zero should work with the Department for Levelling-Up, Housing and Communities, as well as local government and the devolved administrations, to ensure that the planning system embeds and gives priority to the UK’s legally binding net zero target and the UK Government’s target to decarbonise power by 2035.
Show less
Government response AI summary
The Electricity System Operator's (ESO) response details its role in balancing the electricity network, integrating low-carbon technologies into the Balancing Mechanism, and monitoring carbon intensity, without addressing the committee's recommendations for resourcing planning bodies or embedding net zero targets in the planning system.
Read full response →
Department for Business and Trade
39
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
In December 2020, the Government confirmed that the National Policy Statements for Energy, which were published in 2011, would need to be updated to reflect our transition away from fossil fuels and towards cleaner, greener sources of energy. We are disappointed that now, in 2023, the Government has not yet …
Read more
In December 2020, the Government confirmed that the National Policy Statements for Energy, which were published in 2011, would need to be updated to reflect our transition away from fossil fuels and towards cleaner, greener sources of energy. We are disappointed that now, in 2023, the Government has not yet finalised these statements. The Government is consulting on material changes to the statements which reflect recent shifts in Government policy. These changes will also be subject to parliamentary scrutiny. Due to the delay in revising these statements, we urge the Government to make sure the remaining work is delivered at pace. In future, revisions to the NPS should take place in conjunction with changes to the Government’s forthcoming delivery plan, so that the two remain aligned.
Show less
Government response AI summary
The Electricity System Operator (ESO) and Ofgem's response describes the Demand Flexibility Service, its success during Winter 22/23, and ongoing evaluations for potential future rollout, entirely failing to address the committee's recommendation regarding the delayed finalisation and future alignment of National Policy Statements for Energy.
Read full response →
Department for Business and Trade
40
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
Local communities who host critical clean energy infrastructure should benefit from doing so. We call on Government to work with the Crown Estate to use the upcoming licencing round for offshore wind in the Celtic Sea as an opportunity for improving the assessment and delivery of social value to local …
Read more
Local communities who host critical clean energy infrastructure should benefit from doing so. We call on Government to work with the Crown Estate to use the upcoming licencing round for offshore wind in the Celtic Sea as an opportunity for improving the assessment and delivery of social value to local communities, such as in Cornwall.
Show less
Government response AI summary
Ofgem's response details its work on distributed flexibility markets, including consultations on local energy institutions, governance, and developing digital infrastructure for these markets, completely ignoring the recommendation to work with the Crown Estate on improving social value from offshore wind projects in the Celtic Sea.
Read full response →
Department for Business and Trade
43
Conclusion
Eleventh Report - Decarbonisation of th…
Deferred
There has been a clear lack of strategic planning and coordination of energy infrastructure and network upgrades. A failure to plan from a whole system perspective risks increasing the overall costs of the transition. We welcome the more strategic approach emerging following National Grid ESO’s Holistic Network Design and Ofgem’s …
Read more
There has been a clear lack of strategic planning and coordination of energy infrastructure and network upgrades. A failure to plan from a whole system perspective risks increasing the overall costs of the transition. We welcome the more strategic approach emerging following National Grid ESO’s Holistic Network Design and Ofgem’s Accelerated Strategic Transmission Investment (ASTI) framework. We also welcome measures included in the Energy Bill to enable competition in onshore electricity networks in Great Britain, which should be made a high priority by the Government and Ofgem once enacted.
Show less
Government response AI summary
The government will launch a Call for Evidence in summer 2023, followed by a consultation later in 2023, on how the energy retail market framework needs to evolve. This response focuses on retail market reforms rather than strategic planning of energy infrastructure or competition in …
Read full response →
Department for Business and Trade
44
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
We recommend that Ofgem sees the Accelerated Strategic Transmission Investment (ASTI) framework as a starting point to accelerate the delivery of the necessary grid upgrades required to meet the Government’s 2035 target. This work should continue beyond 2035 to ensure adequate overall capacity for delivering on the 2050 net zero …
Read more
We recommend that Ofgem sees the Accelerated Strategic Transmission Investment (ASTI) framework as a starting point to accelerate the delivery of the necessary grid upgrades required to meet the Government’s 2035 target. This work should continue beyond 2035 to ensure adequate overall capacity for delivering on the 2050 net zero target. We support the recommendation of the Climate Change Committee for the Government to establish a Minister-led infrastructure delivery group, advised by the Electricity Networks Commissioner, to ensure that network infrastructure build is taken forward at pace. This should bring together senior parties across relevant Government Departments, as well as Ofgem, the Scottish and Welsh Governments, National Grid ESO and asset owners, to monitor progress across the initiatives required to expedite progress.
Show less
Government response AI summary
The government references its ongoing Review of Electricity Market Arrangements (REMA), which involved a first consultation in 2022 and a second planned for Autumn 2023, exploring options for market reform and locational signals. The response outlines a process of consultation and exploration, but does not …
Read full response →
Department for Business and Trade
45
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
The UK’s “first come first served” approach to grid connections is failing to deliver the volume of connections required. Projects which may be speculative or slow-moving risk being prioritised over those that are more viable. While we welcome National Grid ESO’s five-point plan to tackle queue management issues at the …
Read more
The UK’s “first come first served” approach to grid connections is failing to deliver the volume of connections required. Projects which may be speculative or slow-moving risk being prioritised over those that are more viable. While we welcome National Grid ESO’s five-point plan to tackle queue management issues at the transmission level, we do not believe this has proved successful to date. We recommend that Ofgem allows National Grid ESO to require projects already in the queue to meet strengthened milestones. If projects are unable to meet these, network operators should be able to prioritise other more viable projects in the queue. In response to this report, we ask that National Grid ESO explains what steps it is taking to work with the Distribution Network Operators to stop projects that want to connect to the distribution network getting stuck in the transmission queue. We would welcome direct intervention from Government on these issues if required.
Show less
Government response AI summary
The government highlights its consultation on the Strategy and Policy Statement (SPS) for Energy Policy and the establishment of the Future System Operator (FSO), which will manage electricity and gas networks. The response outlines these ongoing policy and structural developments, but does not directly commit …
Read full response →
Department for Business and Trade
46
Conclusion
Eleventh Report - Decarbonisation of th…
Deferred
The RIIO-ED1 process, which set the amount network operators could charge energy bill-payers for making upgrades to the grid over the period 2015–2023, proved overly generous. Distribution Network Operators were able to either build 108 Decarbonisation of the power sector more infrastructure that is rewarded through the Regulated Asset Value, …
Read more
The RIIO-ED1 process, which set the amount network operators could charge energy bill-payers for making upgrades to the grid over the period 2015–2023, proved overly generous. Distribution Network Operators were able to either build 108 Decarbonisation of the power sector more infrastructure that is rewarded through the Regulated Asset Value, or not spend on that infrastructure and keep a proportion of underspends. Given that technology deployment curves are hard to forecast, we understand Ofgem’s use of uncertainty mechanisms for RIIO-ED2. We will be looking to the regulator to ensure that they better manage risk and that network companies bring forward the required investment. The uncertainty mechanisms will need to be used efficiently, before customers see problems, particularly if the economics of heat pumps or electric vehicles change quickly.
Show less
Government response AI summary
The government details the establishment of the Future System Operator (FSO), aiming for it to be operational in 2024 with a duty to promote net zero. It will also create a framework agreement outlining FSO's relationships. This response focuses on the FSO's role rather than …
Read full response →
Department for Business and Trade
48
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
We are concerned by the risks that customers face different outcomes in different regions due to a lack of national direction setting for distribution networks. We recommend that Ofgem revises its approach to the planning of distribution networks to one which is more outcome focused. Ofgem should set the minimum …
Read more
We are concerned by the risks that customers face different outcomes in different regions due to a lack of national direction setting for distribution networks. We recommend that Ofgem revises its approach to the planning of distribution networks to one which is more outcome focused. Ofgem should set the minimum expectations that network users should expect, as well as best practice. Distribution Network Operators should then find innovative ways to meet these standards.
Show less
Government response AI summary
The government recognises the need for a strategic approach to network planning and notes that Ofgem has launched a consultation on local energy institutions, including proposed Regional System Planners. The government will engage with this review, expects Ofgem to publish a decision later this year, …
Read full response →
Department for Business and Trade
53
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
To build on the success of the Demand Flexibility Service and ensure that demand- side response can become mainstream, the industry needs the opportunity to do more learning by doing. While necessary system reforms take place to create a more enabling environment for demand-side response, we recommend that National Grid …
Read more
To build on the success of the Demand Flexibility Service and ensure that demand- side response can become mainstream, the industry needs the opportunity to do more learning by doing. While necessary system reforms take place to create a more enabling environment for demand-side response, we recommend that National Grid ESO and Ofgem work with industry on developing a transitional demand-side response service that can support existing day-to-day balancing services.
Show less
Government response AI summary
ESO is currently evaluating the existing Demand Flexibility Service with industry participants and consumers, with outcomes to be published later in the summer to inform its future evolution. Ofgem will support this review for a potential further rollout for winter 2023/24.
Read full response →
Department for Business and Trade
57
Recommendation
Eleventh Report - Decarbonisation of th…
Deferred
The current regulatory and market structures of the retail sector will not deliver a consumer experience that can adequately support the transition to decarbonised power system. We recommend that the Government prioritises the reform of the retail market and that its updated Energy Retail Market Strategy: a) clearly sets out …
Read more
The current regulatory and market structures of the retail sector will not deliver a consumer experience that can adequately support the transition to decarbonised power system. We recommend that the Government prioritises the reform of the retail market and that its updated Energy Retail Market Strategy: a) clearly sets out the role that suppliers will be expected to play in the transition to a decarbonised power system as well as interim milestones to achieve this; b) enables suppliers to innovate and build sophisticated relationships with customers through the provision of a broader set of energy services; 110 Decarbonisation of the power sector c) allows suppliers to be fairly rewarded for providing services that entice customers to shift and reduce demand, in a way that reflects the additional risks that suppliers will be taking on; and d) removes barriers that prevent vulnerable customers from accessing the benefits that the transition will offer.
Show less
Government response AI summary
The government recognizes the retail market's importance and will pursue reforms by launching a Call for Evidence in summer 2023, followed by a consultation later in 2023, to determine how the framework should evolve.
Read full response →
Department for Business and Trade