Lessons from major projects and programmes
Closed
What the inquiry looked at
“The Government Major Projects Portfolio currently comprises 125 major programmes at a combined cost of £448 billion - and in addition, government has committed to spending £640 billion for new infrastructure projects between now and 2025. The ability of government to successfully navigate the unique and novel challenges of delivering major programmes is crucial to securing the best value from public money. They often have bespoke features and require new technology, and are complex because of their huge scale. Major programmes frequently encounter difficulties, failing to deliver to their planned cost and schedule, with significant consequences for national capabilities and the public purse. The inquiry will consider the NAO’s work on major programmes and assess the common issues that arise , often repeatedly. It will examine issues and problems encountered in delivery of major projects, why they occur, and consider recommendations for government to help improve programme delivery. The Committee will question the CEO of the government’s Infrastructure and Projects Authority. If you have evidence on the issues raised in this inquiry please submit it here by 6.00pm Friday 27 November 2020.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
This Committee has examined numerous major projects and programmes delivered by government including, for example, High Speed Two, the Emergency Services Network, and Universal Credit. We see many of the same difficulties time and time again—such as programmes not keeping to cost or schedule, a lack of transparency in their progress, and weaknesses in leadership and governance. Through the 2020 Spending Review and the National Infrastructure Strategy, the Government has committed to a large programme of infrastructure investment, with £600 billion of gross public investment planned for the next five years. This is accompanied by efforts to accelerate the delivery of major programmes, and better target investment to support the levelling up agenda and achieving net zero.
We want to see lasting improvements made to the way in which government delivers major projects, and do not want to see past problems repeated. The Infrastructure and Projects Authority (IPA) is government’s centre of expertise for major project delivery.
We are supportive of the IPA’s plans and welcome its work to strengthen assurance and capability within government. However, we remain concerned as to whether the IPA will be able to make use of its authority and influence to drive the change required throughout government.
This report makes recommendations to the IPA and Government more widely, setting out the areas we think Government should address to improve project delivery. In particular, we want to see a better focus on managing cost and schedule appropriately, improvements in the leadership and transparency of major programmes. The IPA must ensure its oversight of the Government Major projects Portfolio is sufficiently robust to improve the delivery of government programmes in practice.
What the government said
The government responded on 26 March 2021.
The government agrees with the Committee's recommendations on investment capacity, transparency, assurance, cost estimating and project leadership, but disagrees with the recommendation on IPA scrutiny of the Restoration and Renewal project.
- On transparency, the government agrees and notes that from April 2021 GMPP projects "will begin publishing summary business cases following final approval", with the annual report data cutting the lag from nine months to four.
- On assurance, the government agrees; from 2021 the RAG rating is to be simplified to three categories and "Projects ranked red will not be permitted to proceed until issues are managed to an acceptable level of risk". The IPA will write to the Committee within six months.
- On cost and schedule estimates, the government agrees; new requirements, on a "comply or explain basis", will include a requirement to use ranges that are gradually narrowed as certainty emerges, set out in guidance to be published in March 2021.
- On Restoration and Renewal, the government disagrees, stating that any formal IPA scrutiny or assurance "must be based on an invitation from Parliament and amendment to the existing agreements", although informal advice can continue where requested.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 5 November 2020 to 16 November 2021.
- Oral evidence 30 Nov 2020
- Report 29 Jan 2021
- Government response 26 Mar 2021
- Correspondence 2 letters
What it recommended 6 recommendations · 23 conclusions
2We are concerned about the continued lack of transparency to Parliament about the progress of...
3We welcome the IPA’s plans to strengthen how it assures government’s major projects and the...
4There is scope for a more mature approach to setting and monitoring cost and schedule...
5The calibre and number of people in leadership positions in major projects is still not...
6It is vital that Parliament’s own major project, the Restoration and Renewal programme, is an...
1On the basis of a report by the Comptroller and Auditor General, we took evidence...
7We asked about the capacity of both government and the private sector to deliver large...
8The NIC stated that new economic infrastructure must take a cross-sectoral, evidence- based and long-term...
9Within the National Infrastructure Strategy, the government also announced the initiatives that had come out...
10Government has also made changes to its Green Book guidance on evaluating investment proposals, such...
11In discussing the historic performance on managing major programmes and the challenges they have faced,...
12The NIC agreed, stating that when building infrastructure, government needs to spend sufficient time at...
13The IPA stated that it is working with government to improve the quality of cost...
14The IPA and NIC stated that programmes should provide a reasonable range of outcomes for...
15Skills and leadership remain a persistent problem in delivering major projects.
16However, the IPA stated that many SROs manage more than one programme, and typically have...
17The IPA told us that, to remedy this issue, in addition to making attendance at...
18This Committee has examined many government programmes where problems had arisen and were known by...
19The IPA agreed that creating a culture of transparency and openness are the foundations of...
20Projects need good data to appropriately track programme performance, but the underlying data which communicates...
21The IPA stated that releasing all data at the detailed level would cause issues within...
22The IPA provides a range of assurance and support services to major programmes, with one...
23The IPA considers that while its gateway review process is good, government has not always...
24The IPA pointed to the Lower Thames Crossing as a recent example of where it...
25We noted that the number of projects rated as red has increased from four to...
26The IPA told us that it is looking to introduce metrics to help it understand...
27Since the IPA’s remit covers the government major programmes portfolio, it does not extend to...
28Whilst the IPA has provided support and advice in an advisory capacity to the programme,...
29When asked, the IPA stated that it could not see a reason why it could...
Evidence
Oral evidence sessions 1
- 30 Nov 2020Lessons from major projects and programmes2 witnesses, listed belowparliament.uk ↗
Who gave evidence 2 witnesses
- Matthew VickerstaffDeputy Chief Executive, NISTA
- Nick SmallwoodCEO, Infrastructure and Projects Authority
Correspondence 2 letters
- 16 Nov 2021Correspondence from Alex Chisholm, Civil Service Chief Operating Officer and Cabinet Office Permanent Secretary, and Catherine Little, Director General Public Spending, HM Treasury, re TM39 Report of Session 2019-21 – Lessons from major projects and programmes, dated 29 October 2021
- 14 Sep 2021Written evidence submitted by Amit Bhagwat