Source · Select Committees · Public Accounts Committee
Recommendation 4
4
There is scope for a more mature approach to setting and monitoring cost and schedule...
Conclusion
There is scope for a more mature approach to setting and monitoring cost and schedule estimates by using ranges which narrow over time. The UK government has some of the most novel and complex programmes in the world. The issues that major programmes face are not unique to the public sector, with research indicating that around 75% of major programmes exceed their intended cost and schedule, including those in the private sector. Nonetheless, there are practices in the private sector that the public sector could learn from, such as there being more front-end development of a programme to define its scope, and on getting cost and schedule estimates right before committing to them. The IPA and the National Infrastructure Commission say that they are working to improve the quality of cost estimates across government, and the understanding of what a good estimate looks like. Programmes should make greater use of cost and schedule ranges to reflect the high degree of uncertainty at early stages, with the expectation that these ranges would narrow as the programme is developed further. Lessons from major projects and programmes 7 Recommendation: The IPA should encourage and support departments to use ranges for cost and schedules estimates, rather than single point numbers, and write to us setting out how it is scrutinising and improving cost and schedule estimates on major programmes.
Government Response
Acknowledged
HM Government
Acknowledged
4.1 The government agrees with the Committee’s recommendation. Target implementation date: April 2021 4.2 In January 2021, the IPA Chief Executive Officer (CEO) addressed permanent secretaries, requesting that they insist their teams are more realistic and evidence-driven in their approach to estimations of major project cost and schedule. The IPA will formally set out new requirements of departments, on a comply or explain basis, in Best Practices for Cost Estimating which will be published in March 2021. This will include a requirement to use ranges that are gradually narrowed as certainty emerges. The IPA will offer additional training to SROs on cost estimation later in 2021. 4.3 The IPA is working to develop a centralised data platform to aggregate and leverage past government project data to underpin, challenge and assure future project estimations of cost and schedule. This platform will be piloted across a number of asset classes from March 2021.