Select Committee · Public Accounts Committee

High Speed 2: Progress at Summer 2021

Status: Closed Opened: 7 Jun 2021 Closed: 14 Dec 2021 11 recommendations 19 conclusions 1 report

One year ago the Public Accounts Committee reported that the High-Speed 2 rail project was “badly off course” with project managers “blindsided by contact with reality” , as it raised serious concerns about the official account that had been provided to the Committee, over time, of the project’s health. The Committee is now recalling senior … Show more

Clear

Reports

1 report
Title HC No. Published Items Response
Seventeenth Report- HS2 Summer 2021 HC 329 22 Sep 2021 30 Responded

Recommendations & Conclusions

5 items
1 Conclusion Seventeenth Report- HS2 Summer 2021 Acknowledged

On the basis of a report by the Comptroller and Auditor General, we took evidence...

On the basis of a report by the Comptroller and Auditor General, we took evidence from the Department for Transport (the Department) and High Speed Two Limited (HS2 Ltd) on the High Speed 2 programme.1 We also took evidence from the West Midlands Combined Authority, the National Infrastructure Commission and … Read more

Government response AI summary
The government acknowledged the committee's summary of the evidence-gathering process, restating who gave evidence and noting that the report was published and this is the government's response.
Read full response →
HM Treasury
7 Conclusion Seventeenth Report- HS2 Summer 2021 Acknowledged

Following our evidence session, HS2 Ltd wrote to us and set out the high-level schedule...

Following our evidence session, HS2 Ltd wrote to us and set out the high-level schedule and associated budgets (including contingency) for Phase 1 activities discussed at the session. These are set out in the table below: Phase 1 activity Budget (including Estimated duration of contingency) (£ billion) activity Civil engineering … Read more

Government response AI summary
The government acknowledged the Committee's conclusion regarding the Phase 1 schedule and budgets, stating that the third HS2 6-monthly report confirms cost pressures and contingency use. It committed to maintaining this reporting format for future 6-monthly reports.
Read full response →
HM Treasury
9 Conclusion Seventeenth Report- HS2 Summer 2021 Acknowledged

The construction of the main civil engineering components of the programme (such as tunnels and...

The construction of the main civil engineering components of the programme (such as tunnels and viaducts) is a major undertaking and was a major cause of delays and cost increases at the time of our last report.16 In a letter following our evidence session, HS2 Ltd informed us that it … Read more

Government response AI summary
The government acknowledged the Committee's conclusion regarding the programme's costs and contracts, stating that the third HS2 6-monthly report details cost pressures and contingency use. It committed to maintaining this reporting format for future reports.
Read full response →
HM Treasury
14 Conclusion Seventeenth Report- HS2 Summer 2021 Acknowledged

The Department acknowledged that Euston is a “very urgent and immediate challenge”.

The Department acknowledged that Euston is a “very urgent and immediate challenge”. HS2 Ltd similarly noted that decisions on the final options are time-bound, and that it was concerned that the programme will “literally run out of time”.33 HS2 Ltd explained that it was setting up Old Oak Common as … Read more

Government response AI summary
The government acknowledged the Committee's concerns regarding Euston, reporting a decision to move to a smaller, simpler 10-platform design for the station. The updated design is under development, and the department is exploring greater integration with Network Rail, with further details to follow.
Read full response →
HM Treasury
15 Conclusion Seventeenth Report- HS2 Summer 2021 Acknowledged

We asked the Department what assurances it could give that whatever happened at Euston, it...

We asked the Department what assurances it could give that whatever happened at Euston, it would not affect the delivery of the programme overall.36 The Department provided us with details of the assurance process it follows more broadly on the High Speed 2 programme, including lines of assurance within HS2 … Read more

Government response AI summary
The government acknowledged the conclusion by providing an update on the decision to move to a smaller, 10-platform design for Euston Station, confirming it is in development and will be assured, and that the Euston Partnership continues to explore integration opportunities.
Read full response →
HM Treasury

Oral evidence sessions

2 sessions
Date Witnesses
24 Jun 2021 Bernadette Kelly · Department for Transport, Clive Maxwell · Department for Energy Security and Net Zero, Mark Thurston · HS2 Ltd View ↗
21 Jun 2021 Craig Wakeman · West Midlands Combined Authority, Sir John Armitt · National Infrastructure Commission, Sir Mark Worthington · HS2 Ltd View ↗

Who gave evidence

6 witnesses
WitnessOrganisationSessions
Bernadette Kelly · Permanent Secretary Department for Transport 1
Clive Maxwell · Second Permanent Secretary Department for Energy Security and Net Zero 1
Craig Wakeman · Head of Transport Implementation and Lead HS2 Man… West Midlands Combined Authority 1
Mark Thurston · Chief Executive HS2 Ltd 1
Sir John Armitt · Chair National Infrastructure Commission 1
Sir Mark Worthington · Independent Construction Commissioner HS2 Ltd 1

Correspondence

5 letters
DateDirectionTitle
25 Oct 2021 Correspondence from Mark Wild, CEO, Crossrail Ltd, re Crossrail progress update…
20 Jul 2021 Correspondence from Bernadette Kelly, Permanent Secretary, Department for Trans…
20 Jul 2021 Correspondence Mark Thurston, Chief Executive Officer, High Speed Two (HS2) Ltd…
21 Jun 2021 Correspondence from Bernadette Kelly, Permanent Secretary, Department for Trans…
10 Jun 2021 Correspondence Mark Thurston, Chief Executive Officer, High Speed Two (HS2) Ltd…