High Speed 2: Progress at Summer 2021
Closed
What the inquiry looked at
“One year ago the Public Accounts Committee reported that the High-Speed 2 rail project was “badly off course” with project managers “blindsided by contact with reality” , as it raised serious concerns about the official account that had been provided to the Committee, over time, of the project’s health. The Committee is now recalling senior officials at the Department for Transport and executives at HS2 Ltd, as well as representatives of construction and local authority stakeholder groups. If you have new evidence that has not previously been submitted on: How the HS2 programme is progressing HS2 Ltd and the Department’s readiness to move into construction of Phase One How HS2 Ltd and the Department are managing other parts of the programme - please submit it here by 6pm on Thursday 17 June 2021.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The High Speed 2 programme is one of the single most expensive taxpayer funded projects in the UK. This committee and our predecessor committees have been watching the costs for some years and been critical about the lack of transparency over costs and some of the decisions taken by management. The increase in costs have dented public confidence, but the project does appear to be in a better place following the reset last year. Significant concerns remain however, around key parts of the programme that if unaddressed will lead to further costs and disruption. With construction of Phase one underway and plans for Phase 2a approved by Parliament, the current estimated cost of completing High Speed 2 is between £72–98 billion (2019), an increase from the original budget of £55.7 billion (2015 prices) in 2015. While HS2 Ltd consider these estimates to be realistic, uncertainty remains, particularly when a substantial amount of the Phase One programme is still to be procured and HS2 Ltd is already reporting cost pressures of £0.8 billion from activities such as delayed enabling works and Euston station. HS2 Ltd is also unable to quantify the final cost of the impacts from the COVID-19 pandemic but estimates the cost to be between £300 million and £400 million at the end of 2020.
If these costs are validated, they will need to be covered by the government-retained contingency of £4.3 billion.
Having warned in May 2020 that the Department and HS2 Ltd’s lack of transparency about the scale of the issues facing the programme risked undermining public confidence, we are encouraged that HS2 Ltd is now able to provide us with a clearer account than we have heard previously of what it has spent so far and what it expects to spend during the rest of Phase One. However, we are increasingly alarmed by the lack of progress in developing Euston station. Despite Euston being a key part of Phase One, the Department is yet to make key decisions on the design and approach to construction.
Government also still needs to decide how Phase 2b – the northern sections of the route – will integrate with other parts of the railway and transport system. Both Euston and Phase 2b are complex and risky parts of the programme, but they are critical to the delivery of the promised benefits from High Speed 2. Urgent action is needed if the whole programme is to be delivered on time.
HS2 Ltd and the Department also need to do more to address the concerns of people, communities and businesses near the route, and to make sure that the benefits they have been promised are delivered. The volume of complaints about disruption and environmental damage from construction is rising and is expected to increase as the programme progresses. HS2 Ltd has an opportunity to get on the front foot and engage with communities earlier and more successfully than it has done so far. Government has promised a range of benefits in addition to building the new railway, including providing local jobs. Yet the Department and HS2 Ltd are unable to tell us how they will ensure these are delivered. We expect the Department and HS2 Ltd to have established a strategy to monitor and evaluate the benefits of the programme when we next revisit High Speed 2.
What the government said
The government responded on 14 December 2021. The deadline was 22 November 2021.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 7 June 2021 to its close on 14 December 2021. The dashed mark is the deadline Parliament records for the government's response.
- Oral evidence 2 sessions
- Report 22 Sep 2021
- Government response 14 Dec 2021
- Correspondence 5 letters
What it recommended 11 recommendations · 19 conclusions
2The Department has made little progress on the design and delivery at Euston since we...
3HS2 Ltd has started planning how it will integrate its systems for Phase One to...
4We are increasingly concerned that the Department and HS2 Ltd do not yet know how...
5The Department and HS2 Ltd are not adequately engaging with the Department for Education to...
6We are already concerned about the volume of complaints on disruption from the programme which...
1On the basis of a report by the Comptroller and Auditor General, we took evidence...
7Following our evidence session, HS2 Ltd wrote to us and set out the high-level schedule...
8The Government’s latest range of estimated costs for Phase 1 is £35–45 billion (2019 prices).12...
9The construction of the main civil engineering components of the programme (such as tunnels and...
10In our 2020 report we recommended that the Department publish regular reports on progress to...
11Euston station is a key element of HS2 and will be an important transport hub...
12In our May 2020 report, we raised our concerns over the huge uncertainty remaining for...
13The Department detailed some of the work it has been undertaking since early 2020 to...
14The Department acknowledged that Euston is a “very urgent and immediate challenge”.
15We asked the Department what assurances it could give that whatever happened at Euston, it...
16The High Speed 2 programme has many interdependent elements, including stations, infrastructure and railway systems.
17The Department recognised two primary risks in relation to railway systems: the physical practicalities of...
18HS2 Ltd recognised that the integration of railway systems would be crucial and explained that...
19The Department and HS2 Ltd have repeatedly promised that High Speed 2 will bring about...
20Both the Department and the West Midlands Combined Authority provided examples of how cities and...
21The creation of thousands of jobs is central to the Department and HS2 Ltd programme’s...
22The Department and HS2 Ltd asserted that many of the jobs from the programme will...
23We asked the Department about the private sector investment that would be needed as part...
24HS2 Ltd described the work it was doing to protect the environment as the “untold...
25Ensuring that enough people with the right skills and capability are available to the High...
26The Department and HS2 Ltd told our previous Committee in 2016 that the National College...
27The Department explained that it was not, and had never been, directly responsible for the...
28HS2 Ltd told us that the nature of the High Speed 2 programme means that...
29In May 2021, the Parliamentary and Health Service Ombudsman published a report that found that...
30HS2 Ltd told us that there had already been significant activity from environmental protests at...
Evidence
Oral evidence sessions 2
- 24 Jun 2021HS2 recall3 witnesses: Bernadette Kelly, Clive Maxwell, Mark Thurstonparliament.uk ↗
- 21 Jun 2021HS2 recall3 witnesses: Craig Wakeman, Sir John Armitt, Sir Mark Worthingtonparliament.uk ↗
Who gave evidence 6 witnesses
- Bernadette KellyPermanent Secretary, Department for Transport
- Clive MaxwellSecond Permanent Secretary, Department for Energy Security and Net Zero
- Craig WakemanHead of Transport Implementation and Lead HS2 Manager, West Midlands Combined Authority
- Mark ThurstonChief Executive, HS2 Ltd
- Sir John ArmittChair, National Infrastructure Commission
- Sir Mark WorthingtonIndependent Construction Commissioner, HS2 Ltd
Correspondence 5 letters
- 25 Oct 2021Correspondence from Mark Wild, CEO, Crossrail Ltd, re Crossrail progress update: Summer 2021, dated 1 October 2021
- 20 Jul 2021Correspondence Mark Thurston, Chief Executive Officer, High Speed Two (HS2) Ltd, re High Speed 2: Progress at Summer 2021, dated 13 July 2021
- 20 Jul 2021Correspondence from Bernadette Kelly, Permanent Secretary, Department for Transport, re High Speed 2: Progress at Summer 2021 – further information, dated 13 July 2021
- 21 Jun 2021Correspondence from Bernadette Kelly, Permanent Secretary, Department for Transport, re Accounting Officer Assessment summary for HS2 Phase 2a, dated 16 June 2021
- 10 Jun 2021Correspondence Mark Thurston, Chief Executive Officer, High Speed Two (HS2) Ltd, re Parliamentary and Health Service Ombudsman Report, May 2021, dated 28 May 2021