Select Committee · Public Accounts Committee

High Speed 2: Progress at Summer 2021

Status: Closed Opened: 7 Jun 2021 Closed: 14 Dec 2021 11 recommendations 19 conclusions 1 report

One year ago the Public Accounts Committee reported that the High-Speed 2 rail project was “badly off course” with project managers “blindsided by contact with reality” , as it raised serious concerns about the official account that had been provided to the Committee, over time, of the project’s health. The Committee is now recalling senior … Show more

Clear

Reports

1 report
Title HC No. Published Items Response
Seventeenth Report- HS2 Summer 2021 HC 329 22 Sep 2021 30 Responded

Recommendations & Conclusions

23 items
2 Recommendation Seventeenth Report- HS2 Summer 2021 Accepted

The Department has made little progress on the design and delivery at Euston since we...

The Department has made little progress on the design and delivery at Euston since we last reported, and we remain concerned that time is running out. Euston station is a key element of the programme both as the London terminus for High Speed 2 and a link to existing railway … Read more

Government response AI summary
The government agreed, stating it has moved to a smaller 10-platform design for Euston, as detailed in its third 6-monthly report, and confirmed funding for integration with Network Rail, with further details and assurance processes to be provided in the next report.
Read full response →
HM Treasury
3 Recommendation Seventeenth Report- HS2 Summer 2021 Accepted

HS2 Ltd has started planning how it will integrate its systems for Phase One to...

HS2 Ltd has started planning how it will integrate its systems for Phase One to ensure the railway works, but this is an inherently risky part of the programme. We previously raised concerns that, given the scale of the programme and its future impact on the rail network, if the … Read more

Government response AI summary
The government agreed to continue providing regular updates on systems integration in 6-monthly reports and committed to writing to the Committee by Summer 2022, after the rolling stock contract is awarded and design is underway, to explain how the train design supports system integration.
Read full response →
HM Treasury
4 Recommendation Seventeenth Report- HS2 Summer 2021 Accepted

We are increasingly concerned that the Department and HS2 Ltd do not yet know how...

We are increasingly concerned that the Department and HS2 Ltd do not yet know how they will turn the benefits promised from High Speed 2 into a reality, including what additional investments will be needed or how these will be funded. The Department claims that High Speed 2 is a … Read more

Government response AI summary
The government agreed with the recommendation and confirmed the department wrote to the Committee in November 2021 to outline its benefits approach. HS2 Ltd will also publish its first bi-annual Benefits Update and a joint Benefits Management and Evaluation Strategy next year.
Read full response →
HM Treasury
5 Recommendation Seventeenth Report- HS2 Summer 2021 Accepted

The Department and HS2 Ltd are not adequately engaging with the Department for Education to...

The Department and HS2 Ltd are not adequately engaging with the Department for Education to secure the skills required for the future of the programme and training the next generation of skilled workers. We have repeatedly raised concerns that the Department and HS2 Ltd did not have the skills or … Read more

Government response AI summary
The government agreed and reported that the recommendation had been implemented, stating the department wrote to the Committee in November 2021 detailing its proactive engagement with DfE and other education providers, and outlined HS2 Ltd's skills strategy and support for the NCATI merger.
Read full response →
HM Treasury
6 Recommendation Seventeenth Report- HS2 Summer 2021 Accepted

We are already concerned about the volume of complaints on disruption from the programme which...

We are already concerned about the volume of complaints on disruption from the programme which does not bode well for the future as more communities will be impacted as construction progresses. HS2 Ltd estimates it has handled 124,000 queries over the past three years and interacted with over 76,000 people … Read more

Government response AI summary
The government agreed with the recommendation and confirmed the department wrote to the Committee in November 2021 detailing efforts to resolve community engagement and environmental issues. It highlighted a decline in complaints, establishment of construction inspectors, and plans to publish an Environmental Sustainability Progress Report.
Read full response →
HM Treasury
8 Conclusion Seventeenth Report- HS2 Summer 2021 Accepted

The Government’s latest range of estimated costs for Phase 1 is £35–45 billion (2019 prices).12...

The Government’s latest range of estimated costs for Phase 1 is £35–45 billion (2019 prices).12 For Phase 2a the range is £5.2–7.2 billion (2019 prices). The latest updated 6 Committee of Public Accounts, High Speed 2: Spring 2020 update, Third Report of Session 2019–21, HC 84, 17 May 2020, conclusions … Read more

Government response AI summary
The government agreed with the committee's implied recommendation regarding cost reporting, stating that the third HS2 6-monthly report to Parliament already confirms cost pressures and contingency use in a tabular format. Future reports will continue to follow this consistent format.
Read full response →
HM Treasury
10 Recommendation Seventeenth Report- HS2 Summer 2021 Accepted

In our 2020 report we recommended that the Department publish regular reports on progress to...

In our 2020 report we recommended that the Department publish regular reports on progress to Parliament, including a realistic appraisal of the programme’s likelihood of delivering to budget and schedule.18 HS2 Ltd and the Department reported £0.8 billion in cost pressures in their most recent update to Parliament in March … Read more

Government response AI summary
The government accepted the recommendation, confirming that its third 6-monthly report to Parliament details cost pressures and contingency use in tabular form. It committed to maintaining this reporting format in all future 6-monthly reports.
Read full response →
HM Treasury
11 Conclusion Seventeenth Report- HS2 Summer 2021 Accepted

Euston station is a key element of HS2 and will be an important transport hub...

Euston station is a key element of HS2 and will be an important transport hub and business area, with potential opportunities for economic regeneration at the wider site. It is intended to be the London terminus of the High Speed 2 programme, providing links to the existing railway, London Underground … Read more

Government response AI summary
The government states it has agreed with and implemented the recommendation regarding Euston station, detailing decisions to move to a simpler 10-platform design and approved funding for greater integration between HS2 and Network Rail stations through The Euston Partnership.
Read full response →
HM Treasury
12 Recommendation Seventeenth Report- HS2 Summer 2021 Accepted

In our May 2020 report, we raised our concerns over the huge uncertainty remaining for...

In our May 2020 report, we raised our concerns over the huge uncertainty remaining for Euston station, specifically the lack of clarity around the station build. The Department and HS2 Ltd told us at the time that although the design of Euston was ready for planning consent, they were looking … Read more

Government response AI summary
The government accepted the recommendation, reporting a decision to move to a smaller, simpler 10-platform design for Euston station. It also noted that funding was approved to support greater integration with Network Rail, with further details expected in the next 6-monthly report.
Read full response →
HM Treasury
13 Conclusion Seventeenth Report- HS2 Summer 2021 Accepted

The Department detailed some of the work it has been undertaking since early 2020 to...

The Department detailed some of the work it has been undertaking since early 2020 to find cost savings at Euston. This included: a review of the proposed tracks and tunnelling at Euston, which confirmed the existing approach was justified; an assessment of the station design, which might lead to a … Read more

Government response AI summary
The government reported that it has moved to a smaller, simpler 10-platform Euston station design, which is in development. It is continuing to explore integration opportunities and optimise oversite development, with further details to be provided in the next 6-monthly report.
Read full response →
HM Treasury
16 Conclusion Seventeenth Report- HS2 Summer 2021 Accepted

The High Speed 2 programme has many interdependent elements, including stations, infrastructure and railway systems.

The High Speed 2 programme has many interdependent elements, including stations, infrastructure and railway systems. We raised concerns in our previous report that, given the scale of the programme and its future impact on the rail network, if the Department does not give enough attention to managing the interdependencies within … Read more

Government response AI summary
The government states it agrees with the committee's recommendation and considers it implemented, noting that procurements for remaining rail systems packages are underway and will continue over the next two years, with regular updates provided.
Read full response →
HM Treasury
17 Conclusion Seventeenth Report- HS2 Summer 2021 Accepted

The Department recognised two primary risks in relation to railway systems: the physical practicalities of...

The Department recognised two primary risks in relation to railway systems: the physical practicalities of different contractors working on the ground together; and, systems not integrating effectively.41 We asked HS2 Ltd how it planned to avoid the issues with railway systems experienced on the Crossrail programme. HS2 Ltd told us … Read more

Government response AI summary
The government agreed with the committee's implied recommendation, stating that procurements for rail systems packages are underway and will continue. The department committed to providing regular systems updates and will write to the Committee about train design and system integration once the rolling stock contract …
Read full response →
HM Treasury
18 Conclusion Seventeenth Report- HS2 Summer 2021 Accepted

HS2 Ltd recognised that the integration of railway systems would be crucial and explained that...

HS2 Ltd recognised that the integration of railway systems would be crucial and explained that it planned to establish a collaborative alliance amongst the main railway systems contractors to encourage them to work together to deliver the integrated systems. Although HS2 Ltd’s pre-contract market engagement found suppliers to be receptive … Read more

Government response AI summary
The government agreed with the committee's implied recommendation, stating that procurements for rail systems packages are underway and will continue. The department committed to providing regular systems updates and will write to the Committee about train design and system integration once the rolling stock contract …
Read full response →
HM Treasury
19 Conclusion Seventeenth Report- HS2 Summer 2021 Accepted

The Department and HS2 Ltd have repeatedly promised that High Speed 2 will bring about...

The Department and HS2 Ltd have repeatedly promised that High Speed 2 will bring about a wide range of benefits that go beyond the increase in capacity and reduction of journey times on routes between major cities. These promised benefits include jobs, economic growth, investment and regeneration. The Department told … Read more

Government response AI summary
The government states it has agreed with and implemented the recommendation regarding HS2 benefits, detailing actions such as a letter to the committee, HS2 Ltd publishing a bi-annual Benefits Update, and working towards a joint Benefits Management and Evaluation Strategy.
Read full response →
HM Treasury
20 Recommendation Seventeenth Report- HS2 Summer 2021 Accepted

Both the Department and the West Midlands Combined Authority provided examples of how cities and...

Both the Department and the West Midlands Combined Authority provided examples of how cities and regions that stand to benefit from High Speed 2 have ambitious plans for how to capitalise on the opportunity that High Speed 2 provides. For example, the development of public transport links in Birmingham and … Read more

Government response AI summary
The government agrees with the recommendation and states it is implemented. HS2 Ltd will publish a bi-annual Benefits Update and the department, with HS2 Ltd, is working towards a joint Benefits Management and Evaluation Strategy next year to maximise benefits and coordinate with other departments.
Read full response →
HM Treasury
21 Recommendation Seventeenth Report- HS2 Summer 2021 Accepted

The creation of thousands of jobs is central to the Department and HS2 Ltd programme’s...

The creation of thousands of jobs is central to the Department and HS2 Ltd programme’s case for building the railway. The Department told us that the growth strategies of Greater Manchester and the West Midlands envisaged that the programme would bring up to 180,000 and 100,000 job respectively, plus around … Read more

Government response AI summary
The government agrees with the recommendation, stating it is implemented, and outlines its benefits approach including future publication of a bi-annual Benefits Update and a joint Benefits Management and Evaluation Strategy next year, focusing on maximising jobs and skills.
Read full response →
HM Treasury
22 Recommendation Seventeenth Report- HS2 Summer 2021 Accepted

The Department and HS2 Ltd asserted that many of the jobs from the programme will...

The Department and HS2 Ltd asserted that many of the jobs from the programme will go to those who live locally to construction sites. However, the West Midlands Combined Authority told us that of a high number of the jobs promised to be created from work at Delta Junction, just … Read more

Government response AI summary
The government agrees with the recommendation and states it is implemented, outlining a benefits approach for HS2 to maximise positive outcomes for communities, including through a bi-annual Benefits Update and a joint Benefits Management and Evaluation Strategy next year.
Read full response →
HM Treasury
23 Conclusion Seventeenth Report- HS2 Summer 2021 Accepted

We asked the Department about the private sector investment that would be needed as part...

We asked the Department about the private sector investment that would be needed as part of delivering the benefits expected from the programme. The Department told us that it had started to take steps to encourage private sector investment to ensure these were delivered. For example, it was working with … Read more

Government response AI summary
The government accepted the implicit need to demonstrate benefits and encourage private investment, confirming it wrote to the Committee outlining its benefits approach. It committed to HS2 Ltd publishing a bi-annual Benefits Update and the department working towards a joint Benefits Management and Evaluation Strategy …
Read full response →
HM Treasury
24 Conclusion Seventeenth Report- HS2 Summer 2021 Accepted

HS2 Ltd described the work it was doing to protect the environment as the “untold...

HS2 Ltd described the work it was doing to protect the environment as the “untold story” of the programme. It stated that there would be no net loss to biodiversity from phases 1 and 2a, and that there could be a net gain to biodiversity from Phase 2b. HS2 Ltd … Read more

Government response AI summary
The government states that HS2 Ltd's first Environmental Sustainability Progress Report will be published to clarify the programme's environmental impacts, alongside a refreshed environmental sustainability vision.
Read full response →
HM Treasury
25 Conclusion Seventeenth Report- HS2 Summer 2021 Accepted

Ensuring that enough people with the right skills and capability are available to the High...

Ensuring that enough people with the right skills and capability are available to the High Speed 2 programme at the right time is critical to its success. In reports from 2013, 2016 and 2020, both this and our previous Committees have highlighted the importance of skills and capability, and concerns … Read more

Government response AI summary
The government agrees with the recommendation to proactively engage with education providers for HS2 skills, confirming actions taken include writing to the committee, HS2 Ltd's Skills, Employment and Education strategy, and ongoing engagement with DfE, ESFA, and FE colleges.
Read full response →
HM Treasury
26 Conclusion Seventeenth Report- HS2 Summer 2021 Accepted

The Department and HS2 Ltd told our previous Committee in 2016 that the National College...

The Department and HS2 Ltd told our previous Committee in 2016 that the National College for High Speed Rail would be crucial in training people in the skills required to successfully construct High Speed 2 and other infrastructure projects. For example, at the time of our evidence session in 2016, … Read more

Government response AI summary
The government agreed with the committee's implied recommendation for proactive engagement with education providers, confirming the department wrote to the Committee in November 2021. It detailed existing strategies, engagement with the ESFA, and ongoing work to support colleges along the HS2 route.
Read full response →
HM Treasury
27 Conclusion Seventeenth Report- HS2 Summer 2021 Accepted

The Department explained that it was not, and had never been, directly responsible for the...

The Department explained that it was not, and had never been, directly responsible for the college as this fell under the remit of the Department for Education. It explained that it’s detailed involvement in the college had been limited and that this had “been a bit of a challenge”. It … Read more

Government response AI summary
The government agreed with the committee's implied recommendation for proactive engagement with education providers, confirming the department wrote to the Committee in November 2021. It detailed existing strategies, engagement with the ESFA, and ongoing work to support colleges along the HS2 route.
Read full response →
HM Treasury
28 Recommendation Seventeenth Report- HS2 Summer 2021 Accepted

HS2 Ltd told us that the nature of the High Speed 2 programme means that...

HS2 Ltd told us that the nature of the High Speed 2 programme means that the work required for it will be disruptive. HS2 Ltd estimated it had handled 124,000 queries over the past three years and interacted with over 76,000 people along the route.63 The Independent Construction Commissioner HS2 … Read more

Government response AI summary
The government accepted the recommendation and confirmed it had already written to the Committee as requested, detailing efforts on community engagement and the environment. It highlighted a decline in complaints and committed to publishing an Environmental Sustainability Progress Report and a refreshed environmental sustainability vision.
Read full response →
HM Treasury

Oral evidence sessions

2 sessions
Date Witnesses
24 Jun 2021 Bernadette Kelly · Department for Transport, Clive Maxwell · Department for Energy Security and Net Zero, Mark Thurston · HS2 Ltd View ↗
21 Jun 2021 Craig Wakeman · West Midlands Combined Authority, Sir John Armitt · National Infrastructure Commission, Sir Mark Worthington · HS2 Ltd View ↗

Who gave evidence

6 witnesses
WitnessOrganisationSessions
Bernadette Kelly · Permanent Secretary Department for Transport 1
Clive Maxwell · Second Permanent Secretary Department for Energy Security and Net Zero 1
Craig Wakeman · Head of Transport Implementation and Lead HS2 Man… West Midlands Combined Authority 1
Mark Thurston · Chief Executive HS2 Ltd 1
Sir John Armitt · Chair National Infrastructure Commission 1
Sir Mark Worthington · Independent Construction Commissioner HS2 Ltd 1

Correspondence

5 letters
DateDirectionTitle
25 Oct 2021 Correspondence from Mark Wild, CEO, Crossrail Ltd, re Crossrail progress update…
20 Jul 2021 Correspondence from Bernadette Kelly, Permanent Secretary, Department for Trans…
20 Jul 2021 Correspondence Mark Thurston, Chief Executive Officer, High Speed Two (HS2) Ltd…
21 Jun 2021 Correspondence from Bernadette Kelly, Permanent Secretary, Department for Trans…
10 Jun 2021 Correspondence Mark Thurston, Chief Executive Officer, High Speed Two (HS2) Ltd…