The design of our motorways and strategic roads necessarily entails balancing competing priorities. However, successive Administrations, together with the Department and National Highways’ predecessor, Highways England, underestimated the scale of safety measures needed effectively and reliably to mitigate the risks associated with the permanent removal of the hard shoulder on …
Read more
The design of our motorways and strategic roads necessarily entails balancing competing priorities. However, successive Administrations, together with the Department and National Highways’ predecessor, Highways England, underestimated the scale of safety measures needed effectively and reliably to mitigate the risks associated with the permanent removal of the hard shoulder on all-lane running motorways. The Department and Highways England failed to deliver safety improvements to all-lane running motorways in a timely fashion, despite having promised previous Transport Committees that such improvements would be prioritised. Moreover, the communication of this radical change in the design of our motorways has been woeful. Six years after their introduction, many people do not understand what all-lane running motorways are and what to do if they breakdown in a live lane.
Show less
Government response AI summary
The government committed to further investigating the benefits of a health and safety assessment by the ORR and establishing an expert panel to review regulatory responsibilities and assess costs, benefits, and risks of additional ORR assessment, with recommendations later in the year.
Read full response →
Department for Transport
5
Conclusion
Third Report - Rollout and safety of sm…
Deferred
We welcome the steps that the Department is taking through the action plan to rebuild trust in smart motorways and to make them safer. However, we are concerned a) that emergency refuge areas will remain too far part on existing all-lane running schemes at up to 2.5 km; b) whether …
Read more
We welcome the steps that the Department is taking through the action plan to rebuild trust in smart motorways and to make them safer. However, we are concerned a) that emergency refuge areas will remain too far part on existing all-lane running schemes at up to 2.5 km; b) whether stopped vehicle detection technology is effective and reliable; and c) that emergency services and traffic patrol officers will still struggle to access incidents, especially when traffic is congested. (Paragraph 28) Rollout and safety of smart motorways 25
Show less
Government response AI summary
The government agreed in principle with the Committee's concerns but deferred action, stating that National Highways is researching the feasibility of emergency corridor rules. Initial research is due in early 2022, followed by further assessments and consultation by late 2022.
Read full response →
Department for Transport
9
Recommendation
Third Report - Rollout and safety of sm…
Deferred
Dynamic hard shoulder motorways apparently confuse drivers, because the hard shoulder is used unpredictably to tackle congestion. A more consistent approach, where the hard shoulder is used at known times, could clarify the situation for drivers without physically removing the hard shoulder. The Department for Transport and National Highways should …
Read more
Dynamic hard shoulder motorways apparently confuse drivers, because the hard shoulder is used unpredictably to tackle congestion. A more consistent approach, where the hard shoulder is used at known times, could clarify the situation for drivers without physically removing the hard shoulder. The Department for Transport and National Highways should pause plans to convert dynamic hard shoulder motorways until the next Road Investment Strategy and use the intervening period to trial alternative ways in which to operate the dynamic hard shoulder to make the rules less confusing for drivers.
Show less
Government response AI summary
The government agrees with the recommendation and commits to revisiting the case for controlled motorways compared to all-lane running motorways. An initial report comparing business cases will be published later this year, with updates as further data becomes available.