Fifth report: Obsolescent and outgunned: the British Army’s armoured vehicle capability
Defence Committee
HC 659
Published 14 March 2021
Recommendations
10
Para 47
We note the significant delay and expenditure on the continuation of the Warrior CSP and...
Recommendation
We note the significant delay and expenditure on the continuation of the Warrior CSP and that, after nine years and over £400 million in sunk costs, the Department has still to decide on the placement of a production contract. We …
Read more
Ministry of Defence
View Details →
14
Para 57
We recognise that the Army must prioritise its equipment spending to specific areas of capability,...
Recommendation
We recognise that the Army must prioritise its equipment spending to specific areas of capability, but consider it unacceptable that the replacement of the FV430 series may not be in service until the 2030s, meaning that this vehicle will have …
Read more
Ministry of Defence
View Details →
22
We share Brigadier Barry’s concern about the message that any reductions in the Army’s ability...
Recommendation
We share Brigadier Barry’s concern about the message that any reductions in the Army’s ability to conduct high-intensity warfighting in defence of NATO may send to both our allies and adversaries. Whatever the specific conclusions that emerge from the Integrated …
Read more
Ministry of Defence
View Details →
Conclusions (27)
1
Conclusion
Para 18
Even in the sorry recent history of the Army’s attempts to procure Armoured Fighting Vehicles, MRAV—now Boxer—stands out as a stark example of how shifting priorities and indecision about requirements lead to increased costs and failure to deliver new capabilities.
2
Conclusion
Para 23
The Ministry of Defence and the Army embarked on a series of overly-ambitious procurement programmes which were too reliant on the development of nascent technologies in order to deliver viable capabilities; within these programmes; and, there was a reluctance to trade off capability requirements (such as vehicle weight) leading to …
3
Conclusion
Para 24
Procurement practices and skills were frequently found wanting; in 2011 the NAO concluded that the failure to introduce any new vehicles since 1997 indicated that, “the Department’s standard acquisition processes for armoured vehicles was not working”. Subsequently the Committee of Public Accounts concluded that “there [was] poor accountability for long-term …
4
Conclusion
We are concerned that the Ministry of Defence, and in particular Defence Equipment and Support may not have sufficient technically qualified staff and capacity to manage effectively the multiple armoured vehicle procurement and upgrade programmes that are currently underway. Given both the large amounts of taxpayer’s money at stake and …
5
Conclusion
Para 27
We are astonished that between 1997 and late 2020 (with the exception of a small number of armoured engineering and Viking protected mobility vehicles) the Department had not delivered a single new armoured vehicle from the core procurement programme into operational service with the Army. It is clear that the …
6
Conclusion
Para 38
We note that the Department’s recent experience of upgrading older vehicles with new weapons and turrets has been difficult, resulting in additional costs and delays 54 Obsolescent and outgunned: the British Army’s armoured vehicle capability in delivering the required capability. The Challenger 2 LEP calls for the integration of a …
7
Conclusion
Para 39
We do not want to see the Army forced to ensure a lengthy capability gap as a consequence of emergent technical and integration issues. The Department should confirm to us that the UK’s main battle tank capability is currently fit for purpose and will remain so until Challenger 2 LEP …
8
Conclusion
Para 42
Despite having spent around 50% of the allocated budget (£800 million), the programme has yet to place a manufacturing contract. The programme has a current in-service date of 2024 (originally planned for 2017) and is some £227 million over budget. After a decade of effort, this abject failure to deliver …
9
Conclusion
Para 44
The Ministry, which mandated this weapons system, should therefore now be fully transparent about the cost of this new, highly specialised ammunition and its implications for the full life-cycle costs of the vehicle (and indeed for Ajax, which utilises the same weapon system).
11
Conclusion
Para 50
The first vehicles were originally due to be delivered to the British Army in April 2017, however this was delayed. In May 2020 it emerged that the delivery of the first batch of Ajax vehicles was to be delayed further as they were found not to be ready to be …
12
Conclusion
Para 51
The Ajax programme, which is now also seriously delayed, is yet another example of chronic mismanagement by the Ministry of Defence and its shaky procurement apparatus. This is particularly worrying, as Ajax is fundamental to the establishment and deployment of the Army’s new Strike Brigades, which are intended to be …
13
Conclusion
Para 54
We note that difficulties with the Ajax programme have again arisen in part as a consequence of the Army’s desire to develop a bespoke vehicle capability (albeit one based on an existing but modified ASCOD 2 hull), with a plethora of complex requirements, and the need to integrate a novel …
15
Conclusion
Para 60
We welcome the decision to procure the Boxer armoured vehicle for the British Army, albeit more than ten years later than would have been the case had the UK stayed in the original multi-national consortium. As part of the Integrated Review and associated funding decisions, the Department should seek to …
16
Conclusion
Para 61
We believe that commonality of platforms and modularity of capability such as sensors and weapon systems will be an essential element in maintaining an effective and capable Army. The Department should ensure that future decisions around procuring new vehicles give greater weight to the undoubted benefits offered by both commonality …
17
Conclusion
Para 65
We are alarmed by the revelation to this inquiry that a core aspect of the plans set out in the 2015 SDSR will not be met. In its response to this Report the Ministry of Defence should provide a detailed explanation of the specific shortfalls (equipment, logistic support, personnel et …
18
Conclusion
Para 72
While we welcome the ongoing efforts to modernise the fleet, new vehicles will only trickle into service over the next four years, and it seems unlikely that they will do so in sufficient numbers to make a material difference by 2025. For example, the Ministry of Defence does not expect …
19
Conclusion
Para 76
An “artillery duel” between a modern British and Russian division would now only be likely to end one way—and not necessarily to the British Army’s advantage.
20
Conclusion
Para 77
We share our witnesses’ concern that, considering recent experience in Ukraine and elsewhere, UK armoured forces may find themselves at a serious disadvantage in terms of artillery capability and air defence when facing a peer adversary. The Ministry of Defence must urgently pursue options to address shortfalls in artillery, air …
21
Conclusion
It is alarming that for at least the next several years UK armoured forces may find themselves overmatched by their most challenging peer adversary. During the Cold War, the British Army and its NATO counterparts sought to offset the numerical advantage held by the Warsaw Pact through the superior quality …
23
Conclusion
Para 90
The lack of a credible short-range air defence system for our land forces, especially in light of the rapidly increasing threat from unmanned aerial vehicles, is of particular concern. We have already noted in Chapter 3 that the Army is also overmatched in terms the artillery firepower available to our …
24
Conclusion
Para 96
We share the concerns of our witnesses and our predecessors. It appears that, as part of the Integrated Review, there is a risk that the Army’s current armoured capabilities (albeit in need of modernisation) are at risk of being denuded on the basis of promises of technically advanced ‘jam tomorrow’. …
25
Conclusion
Para 98
The Department must ensure that Project Morpheus is adequately resourced with technically qualified staff to facilitate coordination and integration with its current and planned armoured vehicle programmes. Based on the Department’s track record in the Land sector we are concerned that the programmes necessary to deliver the capability described above …
26
Conclusion
Para 103
We support the Ministry of Defence’s initiative to develop a Land Industrial Strategy. The LIS should place the land sector on an equal footing with the Air and Maritime sectors, providing industry with certainty for the coming decades and ensuring the Army has access to the technical and manufacturing base …
27
Conclusion
We agree that it is important the Ministry of Defence maximises the collaborative opportunities offered by the recent investments in the UK’s armoured vehicles sector. The Department should ensure that it leverages these advantages by making a clear decision about its participation in the Main Ground Combat System. A repeat …
28
Conclusion
We trust the creation of and adherence to the proposed Land Industrial Strategy will improve the UK’s competitiveness in this sector. The Ministry of Defence, the British Army and their Industry counterparts must work together to map out the coming decades for the armoured vehicle sector. (Paragraph 107) Conclusion
29
Conclusion
Para 108
This report reveals a woeful story of bureaucratic procrastination, military indecision, financial mismanagement and general ineptitude, which have continually bedevilled attempts to properly re-equip the British Army over the last two decades. Even on the MoD’s own current plans (but subject to the Integrated Review), we are still some four …
30
Conclusion
Were the British Army to have to fight a peer adversary—a euphemism for Russia— in Eastern Europe in the next few years, whilst our soldiers would undoubtedly remain amongst the finest in the world, they would, disgracefully, be forced to go into battle in a combination of obsolescent or even …