Select committee: Defence Committee

Conclusion 11

Fifth report: Obsolescent and outgunned: the British Army’s armoured vehicle capability Published 14 Mar 2021 Paragraph 50 Addressed to Ministry of Defence
Conclusion (the committee's words)
The first vehicles were originally due to be delivered to the British Army in April 2017, however this was delayed. In May 2020 it emerged that the delivery of the first batch of Ajax vehicles was to be delayed further as they were found not to be ready to be accepted into service. It is not exactly clear what caused this delay but, in its evidence to the inquiry GDLSUK stated that delays had occurred in agreeing requirements and challenges with the integration of the 40mm weapon system mandated by the Ministry of Defence - similar to the issue on the Warrior programme.

From: Defence Committee, Fifth report: Obsolescent and outgunned: the British Army’s armoured vehicle capability (HC 659), paragraph 50, 14 March 2021

Government response

The government responded to the whole report on 21 May 2021 (deadline 14 May 2021).

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government largely sets out reforms and programme plans in response, noting criticisms of past acquisition, while disagreeing with some points, including that the 40mm weapon system contributed to Ajax delays.

  • On past procurement failings, the Department "notes the Committee's comments and acknowledges that defence acquisition has faced challenges in the past", and points to reforms including a three step approvals process.
  • On Boxer, it "agrees with the Committee on the desirability of acceleration" and is "intending to accelerate and enhance the programme", to deliver full operational capability by 2030.
  • On Challenger 2, it says the Life Extension Project offers better value for money than off-the-shelf alternatives, and that an auto-loader was "considered and dismissed early" on capability and technical feasibility grounds.
  • On the Warrior upgrade, it states that a decision "has now been taken as part of the Integrated Review to no longer upgrade Warrior".

Read the government's response ↗ Report an error