Source · Select Committees · Public Accounts Committee
Third Report - The future of the Advanced Gas-cooled Reactors
Public Accounts Committee
HC 118
Published 20 May 2022
Recommendations
4
EDFE’s timetable for the closure of the stations will result in a significant reduction in...
Recommendation
EDFE’s timetable for the closure of the stations will result in a significant reduction in the UK’s generating capacity until new capacity comes online. In 2020, nuclear power accounted for 16% of UK electricity generation. The closure of seven nuclear …
Read more
HM Treasury
View Details →
7
Not Addressed
Given the scale and complexity of decommissioning the AGR stations, we are concerned that the...
Recommendation
Given the scale and complexity of decommissioning the AGR stations, we are concerned that the Department’s oversight of a complex set of governance arrangements is itself not subject to sufficient scrutiny and challenge. The Department is performing a variety of …
Read more
Government Response Summary
The Clerk of the House and Clerk of Parliament will oversee the programme and manage short-term risks to value for money to avoid nugatory expenditure.
HM Treasury
View Details →
Conclusions (28)
3
Conclusion
The terms of the 2009 sale of the nuclear stations agreed by the Department with EDFE placed a disproportionate amount of risk for meeting future decommissioning costs on the taxpayer. The negotiations surrounding the sale of the stations to EDFE in 2009 were focused on maintaining operations, with less attention …
5
Conclusion
We are not convinced the Department has struck the right balance in incentivising the NDA and EDFE to deliver safe and efficient defueling of the AGR stations on time while reducing costs. The Department has introduced financial incentives to encourage cost-efficient defueling and station transfer with EDFE potentially earning or …
6
Conclusion
Arrangements for transferring nuclear stations to NDA are worryingly under- developed, and there is a risk that transfer negotiations between EDFE and NDA could drag on and increase the costs to the taxpayer. The first of the stations could transfer to the NDA as early as 2026. The NDA and …
1
Conclusion
On the basis of a report by the Comptroller and Auditor General, we took evidence from the Department for Business, Energy & Industrial Strategy (the Department), the Nuclear Decommissioning Authority (NDA) and EDF Energy (EDFE) on the decommissioning of the UK’s fleet of Advanced Gas-cooled Reactor (AGR) nuclear power stations.1
8
Conclusion
The Committee has previously identified significant uncertainty regarding the estimation of decommissioning costs. We examined, for example, the NDA’s management arrangements for decommissioning the Magnox nuclear power stations in 2020 and identified significant difficulties estimating decommissioning costs. We concluded that the NDA did not have a full understanding of the …
9
Conclusion
The estimated cost of decommissioning the AGR stations, plus the PWR at Sizewell B, increased from £12.6 billion in 2004–05 to £23.5 billion in 2020–21 in real terms. We asked the Department why the estimated cost of decommissioning the AGRs had increased to such an extent. The Department asserted that …
10
Conclusion
There remain significant uncertainties which if managed poorly could increase decommissioning costs further. The estimated cost of defueling the seven stations, for example, ranges between £3.1 billion and £8 billion depending upon how quickly they can be defueled and how soon defueling starts once a station closes after stopping electricity …
11
Conclusion
EDFE has recently brought forward the closure date for five out of the seven AGR stations. EDFE told us it expects the stations to stop operating at their current closure dates but acknowledged that early closure was always a risk. Dungeness B was due to close in 2028 but due …
12
Conclusion
In 2015, the then Shareholder Executive, on behalf of the Department undertook a review of the arrangements with EDFE for decommissioning the AGR stations. It concluded that the existing agreements did not incentivise EDFE to look at more innovative or cost- effective ways to minimise decommissioning costs. Between late 2017 …
13
Conclusion
A review commissioned by the Department during the negotiations suggested that the £100 million potential fee might not be enough incentive for EDFE to place greater focus on the AGR stations given the potential value of its other UK interests.20 We therefore queried whether the £100 million financial incentive was …
14
Conclusion
The Department told us it did have other rights to direct EDFE, for example it has the power to change decommissioning plans. If the Department, for example, identified material cost saving opportunities of more than £5 million it told us it could instruct EDFE to do things in a different …
15
Conclusion
The assets of the Fund have been created from the contributions made by the station operators, income from investments, capital injections from government and the proceeds from the sale of the Fund’s shares in British Energy. Despite EDFE extending the operating lives of all the AGR stations, its financial contributions …
16
Conclusion
We asked why, given the amount of uncertainty surrounding the costs, and concerns about the adequacy of the Fund to cover this, the risks of decommissioning were being entirely borne by the taxpayer. The Department said that the £100 million agreed with EDFE was a meaningful financial incentive to manage, …
17
Conclusion
The Department emphasised that it was applying significant learning from the experience of decommissioning the Magnox and AGR stations. For new nuclear stations a funded decommissioning plan has to be in place before construction begins. The Department told us that it was “building from the start with decommissioning in mind” …
18
Conclusion
Nuclear power contributed around 16% of the UK’s electricity in 2020. As at January 2022, five of the seven AGR stations and the Pressurised Water Reactor at Sizewell B are the only nuclear power stations in the UK currently generating electricity; two of the AGRs, Dungeness B and Hunterston B, …
19
Conclusion
The Department acknowledged there will be a production gap between existing nuclear stations closing and new ones coming online. However, it told us that it was not concerned about a lack of generating capacity during that period. It told us that the capacity market allowed electricity capacity to be bought …
20
Conclusion
We asked whether there could be value in reusing the AGR sites, given the existing support in those communities for nuclear power. In particular, we asked the Department what work it was doing to give more clarity to the providers of small modular reactors about potential plans for these sites. …
21
Conclusion
After the AGR stations are defueled EDFE will transfer the stations to NDA who will be responsible for completing the rest of the decommissioning process. The first 30 Qq 3, 7; C&AG’s Report para 1.2–1.3 31 Qq 3–5 32 Q 7 33 Qq 78–79, 82–83 The future of the Advanced …
22
Conclusion
There are still some important aspects of transfer that are yet to be agreed. The NDA and EDFE recognise there are issues around transfer that will need to be agreed but believe they have sufficient time to sort out the remaining points.35 They established nine working groups in 2021 to …
23
Conclusion
The Department’s business case estimates that the transfer of the stations will cost £300 million, but given the uncertainties the cost and liabilities could be as large as £1.8 billion. The uncertainties include a potential need to update IT systems, the condition and nature of assets, and the cost of …
24
Conclusion
We were concerned by the number of issues still to be resolved in the time available. We enquired about progress regarding Hunterston B, the first station expected to transfer, especially as discussions around pension contributions can take time to sort out. The witnesses told us they were in discussion as …
25
Conclusion
We wrote to the Department and HM Treasury number of times (see Annex 1) after our evidence session and asked it to clarify what it had agreed with EDFE in terms of the land and buildings that will be transferred to the NDA, and how it planned to resolve any …
26
Conclusion
The long-term benefits of transferring the AGR stations into public ownership will depend on the ability of Magnox Ltd to deliver efficiencies from combining the stations with its existing portfolio of nuclear stations. The NDA told us it expected to deliver savings once the stations begin to transfer. The addition …
27
Conclusion
Delivering the benefits intended from the new arrangements will require a clear long- term delivery strategy. The current EDFE approach for these stations involves putting reactor buildings into a state of care and maintenance lasting some decades to allow radioactivity levels to decay before starting deconstruction of the reactor. The …
28
Conclusion
The AGR decommissioning programme is complex, and key organisations already have substantial portfolios of work. The NDA, for instance, already has a very heavy workload decommissioning the Magnox fleet and parts of the Sellafield site to which the AGRs will now be added. The NDA’s subsidiary, Magnox Ltd, is currently …
29
Conclusion
The Department told us that following its experience of the Magnox contract, it had undertaken a full review to establish whether it had the right governance and it was now confident that this was the case. It also told us that the NDA has similarly taken “really important steps in …
30
Conclusion
Decommissioning the AGR stations is an unusual programme compared with others in government as no single organisation has complete responsibility and authority for performance overall. The success of the programme will depend significantly on the ability of the Department, NDA and EDFE to work together effectively and resolve any problems …
31
Conclusion
Given the centrality of its role we asked the Department whether its own role was subject to sufficient scrutiny and whether AGR decommissioning should be included in the Government Major Projects Portfolio. The Department told us that similar concerns had been raised by HM Treasury and Cabinet Office. However, the …