Source · Select Committees · Public Accounts Committee

Recommendation 1

1

On the basis of a report by the Comptroller and Auditor General, we took evidence...

Conclusion
On the basis of a report by the Comptroller and Auditor General, we took evidence from the Department for Business, Energy & Industrial Strategy (the Department), the Nuclear Decommissioning Authority (NDA) and EDF Energy (EDFE) on the decommissioning of the UK’s fleet of Advanced Gas-cooled Reactor (AGR) nuclear power stations.1
Government Response Not Addressed
HM Government Not Addressed
Introduction from the Committee The UK has eight second generation nuclear power stations accounting for around 16% of total UK electricity generation in 2020. These stations are owned by EDF Energy (EDFE) following its purchase of British Energy in 2009. The stations comprise seven Advanced Gas- cooled Reactor (AGR) stations, all of which are planned to stop generating electricity by 2028, plus the Pressurised Water Reactor (PWR) at Sizewell B. In 1996, government established the Nuclear Liabilities Fund (the Fund) to meet the cost of decommissioning these eight stations. The aim of the Fund is to generate returns from investments that will meet the costs of decommissioning. As at March 2021, the Fund’s assets were valued at £14.8 billion and the estimated decommissioning costs of these eight stations was £23.5 billion. The government has provided a guarantee to underwrite the Fund in the event that its assets are insufficient to meet the total costs of decommissioning. The arrangements for decommissioning the stations have been governed by a series of agreements between the Fund, the Department for Business, Energy & Industrial Strategy (the Department) and the station owners. In late 2017, the Department entered into negotiations with EDFE to revise the agreements for the seven AGR stations. The agreement was finalised in June 2021. Under the revised agreements EDFE will defuel each of the stations after they have closed, as previously planned. The Department has, however, agreed financial incentives to encourage EDFE to accelerate defueling and transfer of the stations. This includes EDFE earning up to £100 million for good performance but paying out up to £100 million for poor performance. Ownership of the stations will then be transferred to the Nuclear Decommissioning Authority (NDA) to complete the decommissioning process. The Department estimates the new agreements could save the taxpayer up to £1 billion compared with the previous agreements. Following the evidence session, we engaged in a series of follow-up correspondence with the Department and HM Treasury. A chronological list of this can be found in Annex 1 at the back of the report. Based on a report by the National Audit Office, the Committee took evidence on Monday 7 February 2022 from the Department for Business, Energy & Industrial Strategy. The Committee published its report on 20 May 2022.This is the government’s response to the Committee’s report. Relevant reports • NAO report: The decommissioning of the AGR nuclear power stations -Session 2021-22 (HC 1017) • PAC report: The future of the Advanced Gas-cooled Reactors - Session 2022–23 (HC 118)