Third Report - The future of the Advanced Gas-cooled Reactors

Public Accounts Committee HC 118 Published 20 May 2022
Report Status
Government responded
Conclusions & Recommendations
31 items (3 recs)
Government Response
AI assessment · 2 of 31 classified
Accepted 1
Not Addressed 1
Filter by: Clear

Recommendations

1 result
2 Accepted

The estimated cost of decommissioning has nearly doubled since 2004–05 and there remains a significant...

Recommendation
The estimated cost of decommissioning has nearly doubled since 2004–05 and there remains a significant risk that the costs will rise further. The estimated cost of decommissioning the AGR stations, plus the PWR at Sizewell B, has increased from £12.6 … Read more
Government Response Summary
The Department, working with the trustees of the Fund, should ensure the estimates make explicit allowance for the risk of optimism bias and report back to the Committee on the new estimates when they are available. They will reflect the revised costs for defueling/deconstruction and uncontracted liabilities.
HM Treasury