Source · Select Committees · Public Accounts Committee

10th Report - HS2: Update following the Northern leg cancellation

Public Accounts Committee HC 357 Published 28 February 2025
Government response
Treasury minutes: Government response to the Committee of Public Accounts on the Tenth report from Session 2024-25 · published 16 May 2025
Read the government response ↗ Response on the Index

Recommendations & Conclusions

51 items
2 Conclusion

Publish agreed HS2 cost estimate methodology and update programme costs regularly

Conclusion
The Department and HS2 Ltd’s failure to work together effectively is starkly illustrated by them not being able to agree how much HS2 will cost. The Department and HS2 Ltd have still not agreed on how much it will cost to complete Phase 1. They are yet to reach agreement on the methodology and assumptions that underpin their cost estimates. This has been exacerbated by HS2 Ltd failing to ensure it receives reliable data from its supply chain. The existing budget, set in 2019, is no longer viable. With the estimates for completing Phase 1 now as high as £66bn in 2019 4 prices and inflation adjustments potentially representing an additional £10bn, the total programme costs could be close to £80bn. Only when the Department and HS2 Ltd are able to agree on cost estimates will they be able to agree a budget with HM Treasury. In the interim, the Department is agreeing annual budget settlements for HS2 Ltd, a short–term funding approach that provides poor value for money for the delivery of any long– term infrastructure project. recommendation Alongside its Treasury Minute response, the Department should write to the committee, setting out details of the agreed cost estimate methodology. The Department should also include in its next six–monthly update to Parliament when it will update programme costs into current prices and how frequently it will do this in the future.

Link to this item

HM Treasury
View Details →
3 Conclusion

Report progress on HS2 contract renegotiations and plans for achieving cost savings

Conclusion
HS2 Ltd’s construction contracts are unacceptable to the public purse and it is imperative that HS2 Ltd deliver on its assurances to us that it can renegotiate these and deliver significant cost savings. The terms and operation of these contracts provide extremely poor value for money. HS2 Ltd did not heed the warnings that the previous Public Accounts Committee made in 2020 that, in bearing more of the risk of cost increases, it would need to ensure the contracts were managed carefully and accepts that it has not done so effectively. HS2 Ltd is now seeking to renegotiate these contracts on more favourable terms. However, we are unconvinced that there are incentives for the contractors to make significant changes and deliver significant cost savings. There is also a risk that the main contractors pass any financial consequences down the supply chain to small and medium–sized enterprises who may find it more difficult to absorb such changes. recommendation a. The Department’s six–monthly progress updates to Parliament should include progress on contract renegotiations and the level of savings made. b. HS2 Ltd should write to the committee before the 2025 summer recess, setting out what steps it will take if the contracts cannot be negotiated on more favourable terms.

Link to this item

HM Treasury
View Details →
4 Recommendation

Assess new nature restoration fund's impact using HS2 bat tunnel case study

Recommendation
HS2 Ltd’s efforts to reduce the environmental impact of HS2 are not delivering value for money, with the c.£100 million cost of a protective ‘bat tunnel’ more than doubling the cost of that section of railway alone. The Committee does not consider that the right balance has been struck between protecting the landscape and wildlife and the burden this places 5 on taxpayers in relation to large public infrastructure projects such as this. The most striking example of this is the 1 kilometre long ‘bat tunnel’ that HS2 Ltd is building at a cost of c.£100 million (in 2019 prices) to reduce the impact of the railway in that area on a protected species of bat. This is in addition to the £73 million cost of building the underlying stretch of railway and the time and effort taken by DfT, HS2 Ltd and other bodies involved to agree the design and planning permission for the structure. The fact that the Department and HS2 Ltd chose this solution leaves us concerned that the cost to the public purse was not properly front and centre to their decision making. The Department acknowledged that the laws in this area for national infrastructure should be reviewed and while we welcome the recent announcements from government to reduce such burdens on infrastructure projects, through a Nature Restoration Fund, it is not clear to what extent this would reduce costs and delays for major projects such as HS2. recommendation In its letter to us before the 2025 summer recess, the Department should set out how it will work with the Department for Environment, Food and Rural Affairs to assess what impact the new nature restoration fund would have had on the section of the line where the bat tunnel is, and use that case study to help refine the operation of the fund.

Link to this item

HM Treasury
View Details →
5 Conclusion

Address HS2 leadership and capability gaps to ensure successful programme delivery

Conclusion
The Department and HS2 Ltd do not have the skills and capabilities needed to successfully deliver the programme. The Public Accounts Committee has repeatedly raised concerns over the Department and HS2 Ltd having the skills and capability they need. Following the cancellation of Phase 2, HS2 Ltd now needs to reinforce its capability, such as in commercial management, and focus its culture on the singular purpose of delivering Phase 1 for the lowest feasible cost. The company now has new leadership in Mark Wild, who brings experience of delivering Crossrail and is tasked with delivering the programme’s reset. There are also likely to be changes in advance of the reset to how the Department engages with HS2 Ltd as well as how it organises itself internally following the conclusion of the Major Transport Project Governance and Assurance Review. However, we are not convinced that the Department has sufficiently considered how it could bring fresh thinking to its own leadership of HS2, or whether it has the right skills and capabilities in place to lead the programme effectively and credibly. 6 recommendation The Department should, alongside the reset of the programme, set out how gaps in skills and capabilities, such as in leadership and other key areas, will be addressed to secure the successful delivery of HS2. This should include the performance measures or indicators that leaders will be reviewed against.

Link to this item

HM Treasury
View Details →
6 Conclusion

Update Parliament on HS2 Euston progress, funding, risk management, and costs

Conclusion
The Department’s plans for Euston carry huge risks given the uncertainties about its scope, cost, funding, schedule and delivery model. In the 2024 Autumn budget, the government confirmed that HS2 would terminate at London Euston rather than Old Oak Common in West London, but the scope of the work needed at Euston is unclear. The task at Euston is significant as there is not only the construction of the HS2 station and potential allowance for future expansion, but also redevelopment of the existing Network Rail station, the underground station and the surrounding area, all within an extremely tight space. The Department has not yet decided on the final delivery model for work at Euston and how this connects with possible commercial development. Its current ambition is also for the approximately £6 billion cost at Euston to be funded through significant contributions from the private sector. However, there is not yet a clear plan for this and we are sceptical that the private sector will provide this level of contribution. In the meantime, local businesses, residents and passengers will continue to face significant disruption at Euston for many years to come. recommendation The Department should include in the six–monthly update to Parliament an update on its progress on Euston, including progress in establishing a delivery model and private financing for the works; how it is managing risks; and latest figures for both the spend to date and total cost estimate.

Link to this item

HM Treasury
View Details →
7 Conclusion

Slow progress on HS2 land and property disposal decisions post-Phase 2 cancellation

Conclusion
Things are moving too slowly on making decisions on the disposal of land and property purchased as part of the programme. The Department has yet to determine what land and property can be disposed of following the cancellation of Phase 2, and what land it will retain ownership of for the purpose of potential future work. In February 2024, the previous Public Accounts Committee stressed the need for the Department and HS2 Ltd to develop a strategy for the disposal of land and property, and to balance this with the needs of those who have been affected. Very little progress has been made and people who previously owned property that is no longer needed, and who may welcome the opportunity to buy it back, are still waiting for clear timeframes and answers. This includes properties that were already no longer required from changes to the HS2 route in 7

Link to this item

HM Treasury
View Details →
8 Conclusion

Require the Department to report on lessons learned and their practical implementation to the Committee.

Conclusion
Over the last decade the Department and HS2 Ltd have repeatedly said they are learning lessons but there is little evidence that lessons have been applied effectively and mistakes avoided. Since 2013, the Department and HS2 Ltd have told the Committee that they have been learning lessons. This has included areas such as around management of costs and schedule. The Department and HS2 Ltd say that they are still drawing on work already completed on HS2 to learn lessons for future delivery and have worked with HM Treasury and the Infrastructure and Projects Authority to consider all the lessons to date. However, escalating costs, programme delays and rescoping demonstrate that the Department and HS2 Ltd have not implemented these lessons effectively. recommendation Alongside its Treasury Minute response, the Department should write to the committee setting out the key lessons they have drawn and then, in its six–monthly update, explain how those lessons have been put into practice. 8 1 Resetting the HS2 programme Introduction

Link to this item

HM Treasury
View Details →
1 Conclusion

Committee examines current state of HS2 programme with Department and HS2 Ltd.

Conclusion
On the basis of a report by the Comptroller and Auditor General, we took evidence from the Department for Transport (the Department) and High Speed Two Limited (HS2 Ltd) on the current state of the High Speed Two (HS2) programme.1 The Department is the programme’s sponsor, responsible for funding and overseeing delivery. HS2 Ltd, an arm’s–length body of the department, is responsible for delivering an operational railway.2

Link to this item

HM Treasury
View Details →
9 Conclusion

HS2 programme reset to take until mid-2026 for assured contractual baseline.

Conclusion
We were told by HS2 Ltd that it would take time to implement the changes needed as part of the programme’s fundamental reset, with all of 2025 needed to ensure the organisation’s activities are all orientated towards delivering Phase 1. HS2 Ltd estimated that the reset would not be complete, with an “assured contractualised baseline” that can be properly measured against, until mid–2026. The Department also explained that the reset will include a re–evaluation and refreshing of the business case and a revised benefit–cost ratio.15 Revising cost estimates

Link to this item

HM Treasury
View Details →
10 Conclusion

Department and HS2 Ltd disagree on total programme cost estimates and methodology.

Conclusion
The Department and HS2 Ltd still disagree on the estimated total costs for completing the programme. Despite using the same data, the Department and HS2 Ltd told us that estimates differ because they disagree over a range of technical factors relating to the methodology used for the estimates and assumptions used, for example over the value of remaining risks on the programme and productivity savings.16 HS2 Ltd also had limited cost information from the supply chain, which reduced its ability to assess which cost increases were necessary.17

Link to this item

HM Treasury
View Details →
11 Conclusion

Department and HS2 Ltd are working to agree cost estimation methodology with Treasury.

Conclusion
Both the Department and HS2 Ltd told us that they were working together to reach an agreed methodology including drawing on third–party technical advice on cost estimation and, to ensure that the underpinning assumptions of future estimates are agreed, establishing an oversight group with HM Treasury representation.18 The Department expressed confidence that there would be agreement on the methodology in the coming two to three months.19

Link to this item

HM Treasury
View Details →
12 Conclusion

HS2 Ltd's latest Phase 1 cost estimate significantly exceeds prior figures and funding envelope.

Conclusion
Prior to the October 2023 announcement, HS2 Ltd estimated that the total costs of Phase 1 would be £49 billion to £57 billion. The Department’s estimate was lower, at £45 billion to £54 billion but still above the funding envelope of £44.6 billion set in 2019. These estimates were all calculated 14 Qq 72–73 15 Qq 5, 37, 39 16 Qq 1, 6–7, 12 17 C&AG’s Report, Figure 8 18 Qq 6, 9, 13 19 Q 12 12 using 2019 prices.20 HS2 Ltd has continued to assess the cost of the programme and provided an even higher estimate to its Board in June 2024 of £54 billion to £66 billion, again still in 2019 prices. HS2 Ltd told us that this was based on new information and data from the supply chain. The Department reported that this estimate had been included in its six– monthly report to Parliament for the purposes of transparency. However, it was highly uncertain and subject to further assurance, and had not been approved by the HS2 Ltd Board or by the Department. Also, the estimate did not take into account work as part of resetting the programme and any private financing.21

Link to this item

HM Treasury
View Details →
13 Conclusion

HS2 cost estimates in 2019 prices are unsatisfactory, projected to reach £80 billion.

Conclusion
We expressed to the Department how unsatisfactory we found it that the cost estimates for completing the programme are still in 2019 prices. The Department agreed, telling us that it expects that any funding agreed at the spending review will be in current prices. It also explained that this will produce an increase in the estimated total programme cost in cash terms given that the adjustment will cover a period of time that has seen very high inflation, particularly in the construction sector.22 HS2 Ltd, in January 2024 evidence to the Transport Committee, estimated that bringing its estimate in 2019 prices up to 2023–24 prices would add a further £8 billion to £10 billion to the cost of Phase 1.23 With HS2 Ltd’s latest estimate for completing Phase 1 now £54 billion to £66 billion even in 2019 prices, the total programme costs might therefore be close to £80 billion in current prices.24

Link to this item

HM Treasury
View Details →
14 Conclusion

HM Treasury to challenge HS2 revised costs before final programme budget agreement.

Conclusion
The Department confirmed that as well as agreeing a revised cost for the programme with HS2 Ltd, there will also be challenge from HM Treasury before a revised budget for the programme can be set. It told us that HM Treasury is already closely engaged and an important step in determining the eventual cost of the programme will be the upcoming spending review. As part of that, the Department will need to agree with the Treasury what the funding profile for the programme will be for the remainder of this Parliament.25

Link to this item

HM Treasury
View Details →
15 Conclusion

Department manages HS2 via annual funding despite need for long-term profile.

Conclusion
The Department emphasised the need for a long–term spending profile for the completion of HS2, acknowledging to us that agreeing annual budget settlements was really poor for long–term infrastructure delivery.26 20 C&AG’s Report, para 4.6 and 4.7; Department for Transport, HS2 6 monthly report to Parliament: October 2020, 13 October 2020 21 Q 7; Department for Transport, HS2 6-monthly report to Parliament: December 2024, 17 December 2024 22 Qq 23–25 23 Transport Committee, Oral evidence: HS2: progress update, HC 85, Q 408 24 Department for Transport, HS2 6-monthly report to Parliament: December 2024, 17 December 2024 25 Qq 14, 19 26 Q 21 13 However, ahead of the programme’s reset and spending review and the longer–term certainty they should provide, the Department reported that it is having to manage HS2 Ltd’s delivery through annual funding and delivery targets for this year and the next. HS2 Ltd told us that it recognised this as a necessary short–term intervention.27 Renegotiating contracts

Link to this item

HM Treasury
View Details →
16 Conclusion

HS2 Ltd revised Phase 1 construction contracts in 2020, increasing its liability for cost overruns.

Conclusion
In July 2017, HS2 Ltd let contracts with four joint venture companies for the main civil construction work on Phase 1. However, in 2020, once the cost of building the railway became clearer, it revised the terms of the contracts in an attempt to ensure an affordable programme at that time. Contractors would no longer be liable for cost increases above a fixed target price. Instead HS2 Ltd would be responsible for funding increases above the estimated cost although contractors would lose a proportion of their fee for building the railway if they did not meet performance indicators on cost and schedule.28

Link to this item

HM Treasury
View Details →
17 Recommendation

Previous Public Accounts Committee warned HS2 Ltd about managing revised contracts and cost risks.

Recommendation
However, the previous Public Accounts Committee was clear on the risk of these changes and that HS2 Ltd needed to closely manage these contracts. In its May 2020 report it warned that: “Now that it is bearing more of the risk of cost increases, HS2 Ltd also needs to ensure that it has the right commercial skills to manage its revised contractual arrangements with its main construction contractors.” 29

Link to this item

HM Treasury
View Details →
18 Conclusion

HS2 Ltd acknowledges suboptimal contract risk management contributed to a £6 billion cost increase.

Conclusion
HS2 Ltd acknowledged that it has not managed these contract risks in an optimal or coherent way.30 In September 2023, HS2 Ltd estimated that the forecast cost of main civil construction work alone had increased by £6 billion (2019 prices) since 2020.31 27 Q 35; Department for Transport, HS2 6-monthly report to Parliament: December 2024, 17 December 2024 28 C&AG’s Report, High Speed Two: A progress update, Session 2019–20, HC 40, 24 January 2020 29 Committee of Public Accounts, High Speed 2: Spring 2020 update, Third Report of Session 2019–21, HC 84, 17 May 2020 30 Q 5 31 C&AG’s Report, para 4.6 14

Link to this item

HM Treasury
View Details →
19 Conclusion

HS2 Ltd is seeking to renegotiate unproductive civil construction contracts for better risk allocation.

Conclusion
HS2 Ltd told us that it is now seeking to renegotiate these contracts.32 It considers that the current contracts are unproductive and that reset provides the opportunity for a fair allocation of risk and an opportunity to find different ways of commercially incentivising the outcomes that it wants, rather than the ones that it is getting at the moment.33

Link to this item

HM Treasury
View Details →
20 Conclusion

Major HS2 contractors willing to renegotiate terms for future infrastructure programme opportunities.

Conclusion
We challenged HS2 Ltd on the feasibility of renegotiating existing contacts to deliver significant cost savings given the lack of incentives for the contractors to change terms. It told us that all major contractors have expressed willingness to discuss and work through a renegotiation as there was recognition from the private sector that better alignment of incentives between the taxpayer and the delivery of the works was necessary to reduce long–term risk. HS2 Ltd also emphasised that the major contractors would want to work on future rail and wider government infrastructure programmes and so would want to help successfully deliver HS2.34

Link to this item

HM Treasury
View Details →
21 Conclusion

Committee concerned about contract renegotiation impact on HS2's small and medium enterprises.

Conclusion
We expressed our concern to HS2 Ltd for the potential for the large main contractors to pass any financial consequences of contract renegotiations down the supply chain to the small and medium–sized enterprises, of which HS2 Ltd told us there were around 2,400, who may find it more difficult to absorb such changes. HS2 Ltd acknowledged this issue, telling us that it will take this into account as part of its renegotiations and commercial management.35 Environmental obligations

Link to this item

HM Treasury
View Details →
22 Recommendation

Ensure environmental legislation requirements do not disproportionately increase major public infrastructure project costs.

Recommendation
We challenged the Department on the balance in legislation that needs to be taken between meeting environmental obligations and costs, raising the example of the £100 million cost of a protective ‘bat tunnel’.36 In order to mitigate HS2’s impact on nearby bat habitats, the Sheephouse Wood Bat Protection Structure is being constructed near Calvert in Buckinghamshire. The structure will be a combination of concrete arches and mesh inserts and around 1km in length and up to 10m high.37 The Department explained that under the Wildlife and Countryside Act 1981, the Habitats and Species Regulations 2017 and the International Convention on the Conservation of European Wildlife and Natural Habitats, HS2 Ltd was legally required to mitigate the damage or harm to protected species, such as the bats that lived in the area of that section of railway. Both the Department and HS2 Ltd told us that they understood the public concern over the cost of the 32 Q 30 33 Qq 40–41 34 Qq 40–41 35 Q 43 36 Qq 15–16, 18 37 HS2 Ltd, Sheephouse Wood Bat Protection Structure Information Boards, October 2022 15 structure but emphasised that it was a considerable engineering structure, built to last 120 years.38 We note that the enabling legislation for both Phase 1 and 2a passed ahead of the Environment Act 2021 which required developers to achieve a 10% biodiversity net gain. Government will need to ensure that these legislative requirements do not lead to decisions which disproportionately add to the cost of major public infrastructure projects resulting in poor value for money.

Link to this item

HM Treasury
View Details →
23 Conclusion

HS2 Ltd concluded £95m bat tunnel was most efficient option after considering 15 alternatives.

Conclusion
HS2 Ltd confirmed that it was its decision to build the structure and not one required by Natural England. However, the Department and HS2 Ltd told us that, despite its cost, that they had concluded the ‘tunnel’ structure was the most efficient and appropriate way to protect the bats out of the 15 options considered.39 Other options were rejected because of either “excessive cost, technical infeasibility or ecological ineffectiveness”. Their assessment included “robust challenge” from HM Treasury, a review by Arup on whether the solution could be delivered more efficiently and work with the Department for Environment, Food and Rural Affairs and Natural England to test whether the structure would provide the legal compliance and whether there were any better solutions that also reduced costs.40

Link to this item

HM Treasury
View Details →
24 Conclusion

Department and HS2 Ltd recognise need for improved balance between environmental compliance and cost.

Conclusion
The Department strongly agreed, however, about how the balance between compliance and cost should be considered when delivering national infrastructure in the future.41 HS2 Ltd also recognised that it was a complex issue and a sensitive area, telling us that the structure needed local planning permission from Buckinghamshire Council which led to at least a four–year delay which was eventually resolved by the planning inspector.42

Link to this item

HM Treasury
View Details →
25 Conclusion

Bat protection structure increased specific railway section costs from £73 million to £168 million.

Conclusion
In follow–up evidence, the Department confirmed that the total cost of building the structure will be £95 million (in 2019 prices). The Department also reported that the cost of building that section of the railway, irrespective of any mitigation works, would have been £73 million, meaning that the bat structure more than doubled the costs of that section of railway to £168 million.43

Link to this item

HM Treasury
View Details →
26 Conclusion

HS2 Ltd fails to monitor total spending on environmental mitigation schemes.

Conclusion
HS2 Ltd does not monitor how much in total it spends on environmental mitigation. For example, we asked HS2 Ltd how much it was spending on wildlife migration schemes such as for the great crested newt at Halse Copse. In its follow–up letter, HS2 Ltd told us that it was not able 38 Qq 15–16, 18; Letter from DfT on cost breakdown of the HS2 bat mitigation structure at Sheephouse Wood, dated 31 January 2025 39 Qq 15–16, 18 40 Q 18; Letter from DfT on cost breakdown of the HS2 bat mitigation structure at Sheephouse Wood, dated 31 January 2025 41 Qq 15–16, 18 42 Q 16 43 Letter from DfT on cost breakdown of the HS2 bat mitigation structure at Sheephouse Wood, dated 31 January 2025 16 to provide that information as the provision and maintenance of habitat migration forms part of ‘integrated work packages’ and HS2 Ltd had set no requirement in these contracts to segregate the cost of mitigation schemes.44

Link to this item

HM Treasury
View Details →
27 Conclusion

Government plans new Nature Restoration Fund for simplified infrastructure environmental obligations.

Conclusion
In January 2025, the government announced that it will look to change how infrastructure projects meet their environmental obligations as part of its forthcoming Planning and Infrastructure Bill. It set out that this would include a Nature Restoration Fund which will pool contributions from developers to fund larger strategic interventions by, for example, Natural England. In many cases this should enable infrastructure builders to make a single payment to enable development to proceed. The government considers that this approach should be quicker and less burdensome than the current requirement of needing to secure mitigation or compensation for environmental harm before planning permission can be granted on an individual site or project basis.45 Ensuring the right skills and capability

Link to this item

HM Treasury
View Details →
28 Recommendation

Ensure Department and HS2 Ltd secure necessary skills for successful programme delivery.

Recommendation
The Public Accounts Committee has repeatedly raised concerns over whether the Department and HS2 Ltd have had the necessary skills and capability to deliver HS2 successfully. In 2020 the previous Committee cautioned that it was not yet convinced that the Department and HS2 Ltd had the skills and capability they needed either then, now or in the future.46 “In 2013 and 2016, previous Public Accounts Committees identified the challenges the Department has faced in securing the skills it needs for High Speed Two as well as its wider programme portfolio. A lack of capability continues to be an issue [ … ], it still has gaps in key areas such as risk management and assurance, project management and project controls.[ … ]Both organisations will need to ensure that they secure the right skills, at the right time, as the programme progresses.”

Link to this item

HM Treasury
View Details →
29 Conclusion

HS2 Ltd shifts focus to railway systems and operational capability.

Conclusion
HS2 Ltd also acknowledged in evidence to the previous Committee in November 2023 that it that it needed to think about its capacity and capability throughout the company to deliver the task ahead.47 While HS2 Ltd’s focus in recent years has been on civil engineering, it has been 44 Q17; Letter from HS2 Ltd dated 10 January 2025 45 Ministry of Housing, Communities and Local Government and Department for Environment, Food & Rural Affairs, Planning proposals to unblock vital infrastructure and drive nature’s recovery, 22 January 2025 46 Committee of Public Accounts, High Speed 2: Spring 2020 update, Third Report of Session 2019–21, HC 84, 17 May 2020 47 Committee of Public Accounts, HS2 and Euston, Tenth Report of Session 2023–24, HC 67, 7 February 2024 17 shifting its focus to the delivery of railway systems, bringing the railway into operation and managing how it will integrate with the wider railway network. HS2 Ltd began making changes to its organisation in January 2024, including establishing a new role of Chief Railway Officer, with responsibility for integration and focusing programme decisions on how to best deliver the railway, rather than individual component projects.48

Link to this item

HM Treasury
View Details →
30 Conclusion

New HS2 Ltd CEO to reinforce capability, reduce costs, and focus on Phase 1 delivery.

Conclusion
HS2 Ltd now has new leadership, with Mark Wild appointed as the new Chief Executive Officer and taking up the role in December 2024. He brings his experience of delivering Crossrail into operation and is tasked with delivering the programme’s reset.49 He told us that the three things that he needs to do with HS2 Ltd are: reinforce its capability, particularly commercial management in the teams that are managing the contractors, bear down on costs and drive productivity; create an organisation that will operate the railway in the future; and focus HS2 Ltd’s culture on the singular purpose of delivering Phase 1 at the lowest feasible cost.50 The Department also told us that it would expect changes to how it would sponsor and oversee HS2 Ltd following the conclusion of the Major Transport Project Governance and Assurance Review early in 2025.51 48 C&AG’s Report, para 4.4 49 Qq 1–3, 5 50 Qq 42, 71 51 Qq 72–73 18 2 Delivering Euston station

Link to this item

HM Treasury
View Details →
31 Conclusion

Expanded Euston programme scope includes commercial development, housing, and station redevelopments.

Conclusion
In the October 2023 announcement, the government at the time set out that the HS2 station itself would be planned to be smaller, reflecting the lower number of train services expected to operate following the cancellation of Phase 2. However, the scope of the Euston programme would now be larger, incorporating more commercial development and new housing beyond the boundary of the station site.52 The Department set out for us the four key elements that now need to be brought together as a result of the increased scope of works at Euston, both at the station site and surrounding area, all of which are situated in a tight urban environment. • The construction of a new station for HS2 which, although now smaller, is being planned to be future–proofed for potential further expansion. • The redevelopment of the existing Network Rail station at Euston, which is ageing and showing operational problems. • The redevelopment of the underground station to ensure sufficient capacity and improve performance. • The development of commercial property and housing above and around the two stations and in the wider Euston quarter.53 The October 2023 announcement also set out that a new delivery company, separate from HS2 Ltd, would be appointed to deliver the station and a new development corporation would be created to support the wider development of the area.54

Link to this item

HM Treasury
View Details →
32 Conclusion

Department pursues holistic Euston approach, progressing new delivery company and corporation models.

Conclusion
The Department told us that the new approach to Euston is now a holistic one, seeking to build consensus between stakeholders and as a unified delivery rather than the ineffective attempts of the past to try to solve each part separately and hope that they fit together.55 The Department expects to progress with the delivery model and set up of the delivery company over the next year.56 It also told us that, on the development corporation, 52 C&AG’s Report, para 3.3 and 3.5 53 Qq 45, 47, 49; Committee of Public Accounts, High Speed 2: Spring 2020 update, Third Report of Session 2019–21, HC 84, 17 May 2020 54 C&AG’s Report, para 3.3 55 Q 45 56 Qq 46–48 19 there are two models being considered–one mayoral–led and one led by the London Borough of Camden. The Department is talking to both the Greater London Authority and Camden Council about which would be preferred.57

Link to this item

HM Treasury
View Details →
33 Conclusion

Department defends new Euston delivery body necessity due to project complexity and private investment.

Conclusion
We challenged the Department over the necessity and added risk of establishing an additional delivery body to oversee the works at Euston and its surroundings. The Department recognised that setting up new organisations is far more complex and difficult than is often thought, and that its experience with HS2 Ltd demonstrates that it is difficult to set up high–functioning new organisations delivering extremely complex infrastructure. However, the Department told us that the task at Euston is quite different to HS2 Ltd’s core mission of building a railway. The Department explained that the challenge at Euston is more complex, with more moving parts and different opportunities within it, such as attracting private investment, which is a different skill set and poses a different set of technical challenges.58

Link to this item

HM Treasury
View Details →
34 Conclusion

Department stresses need for correct financial incentives in new Euston delivery company.

Conclusion
The Department also pointed to the need to get the financial incentives right in the new delivery company, including what the shareholding and financial participation would be between the different bodies, so that people consider the collective interest, not just their own interests. The Department reasoned that having that in one delivery body, rather than dispersed across four entities, provides a better chance of producing coherent solutions and effective and efficient delivery.59

Link to this item

HM Treasury
View Details →
35 Conclusion

Department anticipates mixed funding for Euston station, including significant private investment.

Conclusion
We also challenged the Department on the likelihood of obtaining the more than £6 billion that the station at Euston is estimated to cost from the private sector. The Department suggested that the funding for Euston would likely be a mix of four components: private financing of the HS2 station; development receipts from commercial development; tax increment finance or contributions from local government; and some residual public funding. The Department told us that it had carried out some early market–testing of the potential for private financing and as a result believes it is a viable option. The Department said that once decisions are taken on the delivery model and spatial allocation, and the detailed design of the station has begun, there will be a better understanding of the potential commercial return and likely level of private investment.60

Link to this item

HM Treasury
View Details →
36 Conclusion

Euston tunneling confirmed, but completion date for HS2 services remains unknown.

Conclusion
In the 2024 Autumn Budget, the government confirmed that HS2 would terminate at Euston, announcing that it would fund the work to tunnel from Old Oak Common in west London to Euston.61 The previous Public Accounts 57 Qq 78–80 58 Q 47 59 Ibid 60 Qq 45–46 61 HM Treasury, Autumn Budget 2024, 30 October 2024. 20 Committee recommended that a decision on tunnelling was needed urgently to avoid incurring much greater costs from stopping and restarting work.62 The Department was unable to tell us, however, when the station will be completed and in operation.63 In the interim however, when it expects HS2 services to begin operating sometime between 2029 and 2033, trains will terminate at Old Oak Common.64

Link to this item

HM Treasury
View Details →
37 Conclusion

Euston works will cause over a decade of disruption to local communities

Conclusion
The Department acknowledged that establishing a clearer plan for the works at Euston and implementing it will take over a decade and that there will be continued disruption to local businesses and communities at Euston. The Department committed to provide transparency and engagement with local residents on its plan.65 62 Committee of Public Accounts, HS2 and Euston, Tenth Report of Session 2023–24, HC 67, 7 February 2024 63 Qq 81–86 64 Department for Transport, HS2 6-monthly report to Parliament: December 2024, 17 December 2024 65 Q 51 21 3 Addressing implications of Phase 2 cancellation Disposal of land and property

Link to this item

HM Treasury
View Details →
38 Conclusion

HS2 Ltd spent £592 million on land for cancelled Phase 2 route

Conclusion
Up to the end of March 2024, HS2 Ltd had spent £3.7 billion on buying land and property along the HS2 route, of which £592 million relates to the cancelled Phase 2.66 The types of land and property include agricultural, commercial and residential, with HS2 Ltd purchasing around a thousand properties and 17 square kilometres of land on the Phase 2 route. HS2 Ltd acts as an agent in purchases and disposals for the Department, with the land and property held as assets of the Department.

Link to this item

HM Treasury
View Details →
39 Recommendation

Department developing programme for disposing of HS2 surplus land and property

Recommendation
In February 2024, the previous Public Accounts Committee stressed the need for the Department and HS2 Ltd to develop a strategy for the disposal of land and property, and to balance the need for value for money for the taxpayer with the needs of those who have been affected. The Committee commented that the Department and HS2 Ltd did not yet know when they would dispose of land and property no longer needed.67 The Department reported in December 2024 that it was developing a programme to dispose of land that is surplus to requirements and has completed a small number of pilot sales.68

Link to this item

HM Treasury
View Details →
40 Conclusion

Full disposal of HS2 surplus land dependent on future rail strategy decisions

Conclusion
However, the Department told us that overall decisions need to be made on future rail investment first. It explained that the government’s long– term strategy being developed for strategic rail investment, including on improvements to rail connectivity in the north of England, may affect what land is bought or sold or safeguarded. It expects the timetable for decisions to be made on the strategy “as a matter of months, not a matter of years”. There was some land that it was very confident would not be required under any plausible scheme, and so it would look to release those in a “sensible and sensitive way, so that communities don’t suffer that 66 C&AG’s Report, para 2.12 and Fig 4 67 Committee of Public Accounts, HS2 and Euston, Tenth Report of Session 2023–24, HC 67, 7 February 2024 68 Department for Transport, HS2 6-monthly report to Parliament: December 2024, 17 December 2024 22 detriment, and so the Exchequer gets the revenue back” 69 The Department expects that fully disposing of land and property no longer needed will take several years to complete.70

Link to this item

HM Treasury
View Details →
41 Recommendation

Committee urges sympathetic handling of property offers back to former HS2 owners

Recommendation
We pressed the Department to ensure that wherever possible, properties should be offered back to the persons from whom they were purchased, and that requests from people who would like to move back into their former homes be handled sympathetically, given that it can take years for cases to be considered through the Crichel Down rules. We raised the case of properties where decisions were still waiting to be made from earlier changes to the HS2 route, such as around Sheffield which was cancelled in 2021 as part of the Department’s Integrated Rail Plan for the North and Midlands.71

Link to this item

HM Treasury
View Details →
42 Conclusion

Department must balance Crichel Down rules with human impact in property disposal

Conclusion
The Department told us that it is obliged to secure value for money for the taxpayer and to follow the Crichel Down rules, which require government departments to offer surplus land back to the previous owner at the current market value. However, the Department acknowledged that the rules need to be applied in a way that remembers that there are human beings at the end of the process.72 Capacity on West Coast Main Line

Link to this item

HM Treasury
View Details →
43 Conclusion

Phase 2 cancellation limits HS2 capacity benefits to London-Birmingham route

Conclusion
The HS2 programme was originally intended to improve capacity on the West Coast Main Line. However, with the cancellation of Phase 2, the revised programme will only address capacity between London and Birmingham. The Department is exploring options to run longer HS2 trains north of Birmingham, but this would require additional works at existing stations.73 Further options for addressing capacity issues include managing demand for rail services or investing in infrastructure such as additional tracks and longer platforms.74

Link to this item

HM Treasury
View Details →
44 Conclusion

West Coast Main Line capacity challenge expected by late 2030s due to HS2 changes

Conclusion
The Department acknowledged the capacity challenge on the West Coast Main Line as a consequence of not building Phase 2, estimating that it will reach capacity by the late 2030s. These capacity concerns were also raised with us in evidence from Manchester City Council, Transport for Greater Manchester and the High Speed Rail Group.75 The Department 69 Qq 56–57; Prime Minister’s Office, The King’s Speech 2024, pages 42–43 70 C&AG’s Report, para 2.16 71 Qq 54–57; C&AG’s Report, Fig 2 72 Ibid 73 C&AG’s Report, para 4.20 74 C&AG’s Report, para 4.21 75 HS2U0007, Written evidence submitted by Manchester City Council; HS2U0009, Written evidence submitted by Transport for Greater Manchester; HS2U0005, Written evidence submitted by the High Speed Rail Group 23 told us that the government is considering what options exist for dealing with capacity north of Birmingham in future years. While there would not be a reinstatement of the northern sections of HS2, the Department said these options could include smaller–scale investments in infrastructure or optimising services using both existing and HS2 trains, although the latter would only delay the problem rather than resolve it.76

Link to this item

HM Treasury
View Details →
45 Conclusion

East-west rail connectivity in the North now considered as series of programmes

Conclusion
The Department told us it is also carrying out development work on how to improve the east–west rail connectivity in the north of England. It said that this may well now be considered as a series of programmes and choices “rather than a big totemic thing” as originally envisaged by Northern Powerhouse Rail.77 76 Qq 66–68 77 Q 70 24 4 Learning lessons

Link to this item

HM Treasury
View Details →
46 Conclusion

Department and HS2 Ltd claim continuous learning from major project experiences

Conclusion
Since 2013, the Department and HS2 Ltd have told the Public Accounts Committee that they have been learning lessons from other major programmes to apply to how they are managing the HS2 programme. For example, in 2019, the Department and the Infrastructure and Projects Authority published a ‘Lessons for the sponsorship of major projects’ report that drew from the Department’s experiences, and the Department told the previous committee that it was embedding the 24 lessons across its portfolio. It pointed to lessons such as using realistic ranges for costing and schedules rather than fixed points, taking action to reset the programme rather than continuing and hoping it is brought back under control, and using benchmarking to test and assure cost estimates.78 More recently, in November 2023, HS2 Ltd also told the previous committee that it was strengthening its governance, with a particular focus on controlling costs.79

Link to this item

HM Treasury
View Details →
47 Recommendation

Department and HS2 Ltd repeatedly fail to embed crucial lessons from major projects

Recommendation
However, the Committee has needed to recommend repeatedly that the Department and HS2 Ltd improve the degree they reflect on past or current experiences and implement any lessons. In 2020, the previous Committee made clear its dissatisfaction: 80 “Given the repeated emergence of issues across the Department’s major programmes, we are not satisfied that the Department is yet embedding the lessons it has learned to date.”

Link to this item

HM Treasury
View Details →
48 Recommendation

HS2 Euston exemplifies department's failure to learn from past major rail projects

Recommendation
The previous Public Accounts Committee also concluded in its 2023 report on HS2 Euston that it was another example of the Department making the same mistakes and failing to learn lessons from its management of other major rail programmes, highlighting the need for more work on cost estimation, the treatment of contingency and managing the integration of complex projects.81 78 Committee of Public Accounts, High Speed 2: Spring 2020 update, Third Report of Session 2019–21, HC 84, 17 May 2020 79 Committee of Public Accounts, HS2 and Euston, Tenth Report of Session 2023–24, HC 67, 7 February 2024 80 Committee of Public Accounts, High Speed 2: Spring 2020 update, Third Report of Session 2019–21, HC 84, 17 May 2020; 81 Committee of Public Accounts, HS2 Euston, Sixty–third Report of Session 2022–23, HC 1004, 7 July 2023 25

Link to this item

HM Treasury
View Details →
49 Conclusion

Department continues to 'mine' lessons from HS2 programme with other bodies

Conclusion
The Department told us that, together with HS2 Ltd, it has worked with HM Treasury and the Infrastructure and Projects Authority to consider all the lessons to date from the HS2 programme but is continuing to ‘mine’ the lessons learned from HS2. The Department also expects the Major Transport Project Governance and Assurance Review to identify lessons from the programme.82

Link to this item

HM Treasury
View Details →
50 Conclusion

Clear project scope definition essential to prevent cost escalation in infrastructure plans

Conclusion
The Department reflected that a key lesson from the experience of HS2, and which needs to inform all the Department’s future infrastructure plans, is that the Department needs to be very clear when it sets out on a large project what it is there to achieve. Changing the scope significantly when a project is already underway has a financial cost to it and the Department told us that the escalation of costs seen with HS2 reflects an obvious lesson of “to have a plan and stick to it.”83

Link to this item

HM Treasury
View Details →
51 Conclusion

Incremental delivery of infrastructure projects offers better control and earlier benefits

Conclusion
The Department also suggested to us that the delivery of infrastructure has been too focused on “grand projects or big schemes that are binary—you do them or you don’t do them” as opposed to setting a long–term intent and delivering it in smaller incremental stages. The Department explained that in such circumstances it can be easier to commit to each stage, is more controllable as a project, you can learn the lessons from each stage and reapply them to subsequent stages and it is likely to bring passenger benefits and economic benefits sooner, as they are not relying on the whole thing.84 82 Q 63 83 Qq 27, 63 84 Q 64 26

Link to this item

HM Treasury
View Details →
Report Status
Response document linked

Missing links do not establish that no response was published. A linked document does not verify responses to individual findings.

Conclusions & Recommendations
51 items (8 recs)

No response data available yet.