Source · Select Committees · Public Accounts Committee

10th Report - HS2: Update following the Northern leg cancellation

Public Accounts Committee HC 357 Published 28 February 2025
Report Status
Government responded
Conclusions & Recommendations
51 items (8 recs)
Government Response
AI assessment · 51 of 51 classified
Accepted 22
Acknowledged 4
Deferred 23
Not Addressed 1
Rejected 1
Filter by: Clear

Conclusions (1)

Observations and findings
45 Conclusion Not Addressed
The Department told us it is also carrying out development work on how to improve the east–west rail connectivity in the north of England. It said that this may well now be considered as a series of programmes and choices “rather than a big totemic thing” as originally envisaged by …
Government Response Summary
The government provides a boilerplate response focused on land disposal for Phase 2, which does not address the committee's observation regarding east-west rail connectivity in the north of England.
View Details →