Select committee: Public Accounts Committee

Conclusion 15

67th Report - NS&I’s transformation programme Published 13 Feb 2026 Addressed to HM Treasury
Conclusion (the committee's words)
In taking forward the Programme, NS&I launched multiple procurements and planned to deliver four transitions in parallel, with no understanding of the risks that this was exposing the organisation and its customers to. NS&I said it had identified supply chain risk as a key area of focus.38 However, NS&I focused more on how it had handled past issues, telling the Committee how it had developed contingency plans when Atos had financial difficulties in 2023; it did not provide evidence that it had considered how to manage the current contracts.39 When asked if it was confident that it had resolved the issues with procurements, NS&I could only say that it had awarded contracts. NS&I acknowledged that these still contain the original milestone dates, which would need to be changed to take account of delays in NS&I’s Programme implementation.40

From: Public Accounts Committee, 67th Report - NS&I’s transformation programme (HC 1237), 13 February 2026

Government response

The government responded to the whole report on 7 April 2026 (deadline 13 April 2026).

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government states that it "agrees with the Committee's recommendation" on each of the recommendations in the report, and sets target implementation dates between June and Autumn 2026.

  • On the integrated plan, the government agrees that NS&I should prepare a realistic plan. NS&I is developing costed options, which will form the basis of a revised Full Business Case in the second quarter of 2026-27, "subject to Treasury and Ministerial process timings".
  • NS&I will write to the Committee "within six months" setting out the integrated plan, including timelines and a revised estimated cost, and will provide a written update on its risk management framework "by June 2026".
  • On culture, a business-wide programme of cultural change activity will be developed, with an initial plan to go to the Board and the Treasury in early Summer 2026 for "rolling implementation over the coming 12-18 months".
  • The Treasury says it will evaluate NS&I's agreed plan through a full Treasury Approval Panel process and will write to the Committee in the Autumn on lessons learned from its oversight.

Read the government's response ↗ Report an error