Select committee: Public Accounts Committee

Conclusion 16

67th Report - NS&I’s transformation programme Published 13 Feb 2026 Addressed to HM Treasury
Conclusion (the committee's words)
There are still many risks for the Programme to manage, for example the replacement of the ‘core banking engine’ is extremely high risk, but the main work has yet to start.41 NS&I agreed that when it replaced its banking engine, data migration would be a “huge consideration”, and said it knew this would need to be managed “in minute detail”, but gave no details of how it would do this. NS&I’s contract with Atos to run the banking engine expires in 2028, and it will need a new contract after then to ensure continuity.42

From: Public Accounts Committee, 67th Report - NS&I’s transformation programme (HC 1237), 13 February 2026

Government response

The government responded to the whole report on 7 April 2026 (deadline 13 April 2026).

Summary written by Accountability Index from the government's response. It is not the government's own words.

The government states that it "agrees with the Committee's recommendation" on each of the recommendations in the report, and sets target implementation dates between June and Autumn 2026.

  • On the integrated plan, the government agrees that NS&I should prepare a realistic plan. NS&I is developing costed options, which will form the basis of a revised Full Business Case in the second quarter of 2026-27, "subject to Treasury and Ministerial process timings".
  • NS&I will write to the Committee "within six months" setting out the integrated plan, including timelines and a revised estimated cost, and will provide a written update on its risk management framework "by June 2026".
  • On culture, a business-wide programme of cultural change activity will be developed, with an initial plan to go to the Board and the Treasury in early Summer 2026 for "rolling implementation over the coming 12-18 months".
  • The Treasury says it will evaluate NS&I's agreed plan through a full Treasury Approval Panel process and will write to the Committee in the Autumn on lessons learned from its oversight.

Read the government's response ↗ Report an error