NS&I attempted an overly complex, risky programme with too many parallel transitions.
We asked NS&I why it had been trying to do such a complex Programme, splitting operations undertaken by a single supplier into a multi-supplier model, in such a risky way. The NAO report shows that NS&I original planned expected four transition stages to happen largely at the same time, and …
Government response. The government's response completely fails to address the committee's conclusion about NS&I's complex programme transition and the need for re-evaluation, instead discussing unrelated matters concerning Carer's Allowance overpayments and reassessments.