National Law Enforcement Data Programme
Closed
What the inquiry looked at
“The Home Office’s National Law Enforcement Data Programme was created to replace the Police National Computer, the national record of data on arrests and missing or wanted persons, and the Police National Database, which facilitates sharing of intelligence between forces. These systems are vital to police operations and are used by all 45 police forces and many other law enforcement agencies. Early in 2021 it was reported that the Police National Computer had suffered a data loss with the accidental deletion of thousands of records. The Committee has warned, in previous inquiries, on the Home Office’s “miserable record of exorbitantly expensive digital programmes that fail to deliver ”. It will question senior officials at the Home Office on whether National Law Enforcement Data programme is likely to meet user requirements and deliver technology that is likely to work , progress against time and budget, and the remaining risks to successful delivery. If you have evidence on these questions please submit it here by 6.00pm on Thursday 9th September 2021”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The Home Office (the Department) has overseen some challenging technology and digital projects in recent years. The Emergency Services Network and Digital Services at the Border programmes are examples of critical projects which have suffered from severe delays and cost overruns, this latest project does not give the committee any comfort that the Department is learning from past mistakes.
Over the last five years, the Department has wasted both vital time and scarce funding without making any meaningful progress in replacing the Police National Computer (PNC) and the Police National Database (PND). Under the Department’s current plans, a replacement for the PNC is not expected to be available until at least 2025–26, more than five years later than the original delivery date of 2020, while total costs to the Department have increased by a staggering 68% to £1.1 billion. The Department now plans to upgrade or replace PND by a separate programme, but it is unclear when this will happen and at what cost.
The PNC is vital to all aspects of police work and their efforts to prevent crime and protect the public from harm. The PNC is reaching the end of its life and requires urgent replacement. While newer, the PND also needs to be replaced. In 2016 the Department began a programme to replace the PNC and the PND, aiming to create a single cloud-based system combining the data and functions of both - the National Law Enforcement Data Service (NLEDS) programme. While the challenges of delivering national programmes for the 45 police forces across the United Kingdom have long been recognised, the Department and the police did not develop the effective working relationship needed to enable the development of NLEDS, with the former Senior Responsible Owner of the programme conceding that the police had in the past lost confidence in the Department’s ability to deliver the programme. The Department has now recognised that more effective working with the police is fundamental to the successful delivery of NLEDS and other technology programmes in its portfolio and has changed tact via the announcement of a new ‘partnership’ approach, with policing now involved in all decision-making at every level.
Despite the failure of NLEDS to deliver meaningful benefits to the police, and several negative evaluations of its progress, the Department did not take decisive action to recover the programme until late 2020. This reset required the programme to take a different, iterative approach to its delivery and has led to changes in its senior leadership.
It is not yet clear that these changes will put the programme back on track to deliver. It remains to be seen whether the Department’s new approach to working with police and its more iterative approach to developing the technology will mean that NLEDS will be ready to replace the PNC within the revised timetable. We will revisit the Department’s progress next year.
What the government said
The government responded on 1 March 2022. The deadline was 8 February 2022.
The government states that it "agrees with the Committee's recommendation" on each of the six recommendations, with acceptance of the first made "on the basis of" its own planning approach.
- On the delivery roadmap, the department plans to share key programme milestones with forces alongside a more detailed annual plan, updated each quarter on a rolling basis, and to provide a further update in April 2022.
- On oversight, the programme board has been strengthened with senior Home Office officials since September 2021, and engagements with the Permanent Secretary "will take place every six weeks".
- On the PNC, the department says a re-platforming option exists, and it will "formulate an action plan" on or before 30 June 2022 to determine "whether and when" to trigger it. Should it be initiated, NLEDP would be paused and "postponed for a further 2 to 3-year period".
- On the PND, its business case is due before the Finance Investment Committee on 10 March 2022, with an update to the Committee in April 2022 once approved. A further £6.5 million has been allocated for 2022-23.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 1 September 2021 to its close on 1 March 2022. The dashed mark is the deadline Parliament records for the government's response.
- Oral evidence 16 Sep 2021
- Report 8 Dec 2021
- Government response 1 Mar 2022
- Correspondence 25 Oct 2021
What it recommended 6 recommendations · 27 conclusions
2The Department made poor decisions at the outset of the NLEDS programme and, despite signs...
3Working effectively with the police is critical to the delivery of NLEDS and other technology...
4The police must continue to rely on the PNC for another five years, despite the...
5The Department does not yet have a plan for maintaining the PND and combining its...
6There is a risk that the Department still lacks the capacity to prioritise and deliver...
1On the basis of a report by the Comptroller and Auditor General, we took evidence...
7The Department told us about its new engagement model, with more iterative delivery intended to...
8The Department told us that it has also retained what it called a ‘no-go option’...
9One of the critical success factors for the programme is having the right people in...
10There were numerous reasons for the Department’s failure to deliver the NLEDS programme to the...
11By early 2018, the Department had recognised that the programme would not deliver as originally...
12The former SRO for the NLEDS programme acknowledged that the Department should have come earlier...
40The lack of documentation for the PNC meant that the Department repeatedly came across such...
13The operational independence of UK police forces is a key challenge for the Department’s implementation...
14Despite the Department’s attempt to reset the programme in 2019, the police continued to have...
15The former SRO acknowledged that the Department had not achieved the sense of partnership with...
16The Department told us that the approach it is now taking is “to have the...
17We asked about the inherent difficulty of reconciling the need to maintain the autonomy of...
18On funding, the Department confirmed that it might give forces funds to ‘come on board’...
19The Department’s failure to deliver NLEDS to date means that the increasingly fragile PNC system...
20The PNC has consistently met its service availability targets in recent years; from January 2020...
21Concerning the January 2021 incident, the Department told us that all deleted data had now...
22The Department also confirmed that there had been an outage earlier this year, which was...
23As the NAO reported, the PNC’s current technology will no longer be fully supported beyond...
24The PND enables police forces to share intelligence that they have gathered locally.
25The Department intended that the NLEDS programme would combine the PNC with the PND, which...
26Police and other users will therefore be unable to access PNC and PND data from...
27The Department’s former CDDTO commented that the Department had added complexity to the NLEDS programme...
28The Department told us that there would be a separate five-year programme for the PND,...
29The Department is delivering several other national ICT programmes for police use, in addition to...
30The NLEDS programme team is also changing the way it delivers technology to be more...
31The Department told us that its new way of working with the police for the...
32The Department also said it was now trying to really think about its portfolio of...
Evidence
Oral evidence sessions 1
- 16 Sep 2021National Law Enforcement Data Programme4 witnesses, listed belowparliament.uk ↗
Who gave evidence 4 witnesses
- Joanna Davinsoninterim Government Chief Digital Officer, Cabinet Office
- Matthew Rycroft CBEPermanent Secretary, Home Office
- Mike HillDirector Police and Public Protection Technology and SRO of NLEDP, Home Office
- Stephen WebbFormer Senior Responsible Owner, Home Office