Select Committee · Public Accounts Committee

Crossrail: A progress update

Status: Closed Opened: 9 Jun 2021 Closed: 16 Nov 2021 6 recommendations 18 conclusions 1 report

Crossrail is a large, complex programme to run a new direct rail line across London, known as the Elizabeth line and part of Transport for London’s rail and underground network. The Elizabeth line is now in its final stages. It became clear in 2018 that the original schedule and cost estimate would not be met … Show more

Clear

Reports

1 report
Title HC No. Published Items Response
Twenty-Fourth - Crossrail: A progress update HC 184 29 Oct 2021 24 Responded

Recommendations & Conclusions

3 items
5 Recommendation Twenty-Fourth - Crossrail: A progress u… Accepted

The Department has still not demonstrated that it is embedding lessons learned into its major...

The Department has still not demonstrated that it is embedding lessons learned into its major programmes. This Committee has examined many major transport programmes, such as HS2, Great Western route modernisation and Thameslink, many of which have had significant problems in their delivery. We have told the Department many times … Read more

Government response AI summary
The government states that it wrote to the Committee on 30 November 2021, as requested, providing an update on progress and specifically outlining the changes in its approach to delivering major programmes with its arms-length bodies.
Read full response →
HM Treasury
15 Recommendation Twenty-Fourth - Crossrail: A progress u… Accepted

Once the central section opens, commuters must still change to other Elizabeth line services to...

Once the central section opens, commuters must still change to other Elizabeth line services to continue their journeys on the eastern and western ends. The opening of full east-west services must align with national rail timetable changes which take place in May and December each year. TfL told us it … Read more

Government response AI summary
The government confirms the phased opening of Elizabeth line services, with full end-to-end services opening by May 2023, specifically stating this will align with National Rail timetable changes.
Read full response →
HM Treasury
24 Conclusion Twenty-Fourth - Crossrail: A progress u… Accepted

The Department also referred to the lessons it and HS2 Ltd have learnt from the...

The Department also referred to the lessons it and HS2 Ltd have learnt from the difficulties Crossrail had in integrating the 36 main works contracts and ensuring that they work together. Informed by the Crossrail experience, at our June 2021 session on HS2, HS2 Ltd and the Department told us … Read more

Government response AI summary
The government states it is at the forefront of developing a lessons management approach for major projects and has already provided a letter to the Committee on 30 November 2021 outlining changes in its approach and the real-world impact of these changes.
Read full response →
HM Treasury

Oral evidence sessions

1 session
Date Witnesses
19 Jul 2021 Andy Byford · Transport for London, Bernadette Kelly CB · Department for Transport, Mark Wild · HS2 Ltd, Matt Lodge · Department for Transport View ↗

Who gave evidence

4 witnesses
WitnessOrganisationSessions
Andy Byford · Commissioner Transport for London 1
Bernadette Kelly CB · Permanent Secretary Department for Transport 1
Mark Wild · Chief Executive Officer HS2 Ltd 1
Matt Lodge · Director Rail Infrastructure South Department for Transport 1

Correspondence

3 letters
DateDirectionTitle
10 Sep 2021 Correspondence from Bernadette Kelly CB, Permanent Secretary, Transport for Lon…
20 Jul 2021 Correspondence from Bernadette Kelly CB, Permanent Secretary and Andy Byford …
29 Jun 2021 Correspondence from Mark Wild, CEO, Crossrail Ltd, re Crossrail progress update…