Summary

Mr C made a complaint against his housing association as he had ongoing problems with damp and water penetration in his property. He first raised a repair request on this matter over two years prior to bringing the case to us. He was of the view that the property needed re-roughcast and re-rendered to resolve the issues. He was not satisfied with the action taken by the association and the length of time it had taken to resolve this issue.

The association apologised for the delay, although they stated that they had completed repairs as requested, in good faith. Part of their investigation uncovered that a redundant chimney stack was the main cause of water ingress in the property. After some further repairs and inspections the association arranged for the chimney stack to be removed. They also apologised to Mr C for the delay and offered compensation, which was declined.

We investigated the case and obtained information from the association. We assessed their response to Mr C's repair requests against their repairs policy and noted that on several occasions repairs were not completed within the set timescales. We also noted that there did not seem to be any measure in place to ensure that repair targets had been met. Mr C was looking for his property to be re-roughcast and the association had said that his house was identified as a property that was due for this type of work but that it was assessed as not being high priority. Given the missed timescales for individual repairs and the overall length of time taken to resolve the problem, we upheld Mr C's complaint.

Recommendations

We recommended that the association: ensure that they adhere to the deadlines for repairs as laid out in their repairs and maintenance policy; ensure staff check that repairs have been completed within an appropriate timescale; and conduct a further survey of Mr C's property to assess the current condition of the roughcast and rendering and to determine what priority rating is currently appropriate.

Related reading

View Decision Report 201607176 as a PDF (13.31 KB) Updated: March 13, 2018

View original on SPSO (Scottish Publ… website

Other decisions involving Argyll Community Housing Association

Reference Date Summary Outcome
202002983 01 Dec 2022 C complained about the length of time taken by their housing association to carry out repairs on their property and … Not Upheld
201700908 01 Apr 2018 Mr C complained that the housing association did not investigate his complaints of damp in line with their obligations. He … Not Upheld
201602008 01 Apr 2017 Mr C complained on behalf of his mother (Mrs A) that the housing association failed to take reasonable action to … Not Upheld
201600473 01 Apr 2017 Mr C contacted the housing association regarding the behaviour of his neighbour, who was their tenant. He said that a … Not Upheld
201407697 01 May 2016 Ms C complained about dampness issues on behalf of her client (Ms A). Ms A had downsized from a larger … Upheld
View all decisions for this organisation