The contractual relationship between trusts and consultants should be redefined. The trust must provide the consultant with the time, space and the necessary tools to do the job. Consultants must accept that the time spent in the hospital and what they do in that time must be explicitly set out.

Bristol Heart Inquiry, Bristol Heart Inquiry — Final Report · 18 Jul 2001 Source PDF →

Government response

●No formal government response recorded

The Index has not yet recorded a verbatim government response to this recommendation.

Delivery

●DHSC and NHS England say completed · 27 Feb 2026

Schedule 3 of the 2003 consultant contract includes details of how the consultant’s job plan should be agreed with the clinical manager, including the use supporting resources to allow them to carry out their role. In addition, under the consultants ‘deal, agreed in April 2024, new arrangements have been introduced for the pay progression structure to ensure pay progression is achieved where clinical managers are satisfied certain criteria have been met, including participating satisfactorily in the job planning process.

From: The Thirlwall Inquiry: Review of Implementation of Recommendations from Previous Inquiries into Healthcare Issues (version dated April 2025)

Site note: DHSC and NHS England's own account of progress, supplied to the Thirlwall Inquiry in September 2024 and printed in the Inquiry legal team's Review of Implementation of Recommendations from Previous Inquiries into Healthcare Issues (version dated April 2025, published 27 February 2026). It is not a finding of the Inquiry. Their reviewed extent of implementation reads “Implemented – Closed”. Table row: section 6.2 No. 43, PDF page 92.

What other bodies have found

In their own words. These do not change the delivery statement above.

●Thirlwall Inquiry legal team · 15 May 2024

The Government agreed with this recommendation.

In its January 2002 response, the Department of Health referred to Government proposals for a new consultant contract, with all consultants’ job plans explicitly setting out how their working time should be organised and what support the trust should provide.

From: The Thirlwall Inquiry: Review of Implementation of Recommendations from Previous Inquiries into Healthcare Issues (version of 15 May 2024)

Site note: The Thirlwall Inquiry legal team's own notes on implementation, from its Review of Implementation of Recommendations from Previous Inquiries into Healthcare Issues (version of 15 May 2024). The review does not colour its Extent of Implementation cell for this recommendation green; it leaves the cell uncoloured where a recommendation was rejected, where evidence of implementation was insufficient, or where steps had been taken but implementation was not yet complete. Table row: section 6.2 No. 43, PDF page 87.

How this page is built

The recommendation and the government responses are verbatim from primary documents. Delivery statements and other bodies' findings are shown in their own words, each with its source. The summary is written by this site and labelled as such. The Index does not paraphrase sources or characterise intent; it records what has been published.