Public Inquiry

Edinburgh Tram Inquiry

Completed · Chair: Lord Hardie · Established July 2014 · Commissioned by Scottish Government

Public inquiry into why the Edinburgh Trams project was delivered late, over budget, and with a reduced scope.

More about this inquiry

Public inquiry into why the Edinburgh Trams project was delivered late, over budget, and with a reduced scope. The project cost £776m against an original estimate of £375m and took 5 years longer than planned.

Where it stands

Public hearings were held on 59 days between September 2017 and May 2018.

Edinburgh Tram Inquiry Report was published on 19 September 2023.

The most recent government response on the record is Response to the Edinburgh Tram Inquiry (item 7.1), dated 14 December 2023.

Government response (24 recommendations)

Delivery (the addressees’ latest statements)

  • No statement from Scottish Government found in the sources searched 17
  • No statement from City of Edinburgh Council found in the sources searched 7

Record checked against the sources 31 January 2026. Latest activity 14 December 2023.

Latest on the recommendations

All 24 recommendations

Reports

Reports and timeline

Recent milestones

  • Inquiry Closed1 September 2026
  • Government Response31 January 2024
  • Final Report Published19 September 2023
Full timeline

Costs

£13,200,000

Reported cost Costs in detail

Parliament

2

mentions in Parliament Parliamentary activity

Recommendations

10 shown (filtered)
Clear filters

ETI-5: Business Case Timing

Noted · No statement from Scottish Government found

Recommended

Where the Business Case for any future light rail project is based upon an assumption that, prior to the award of the contract for the construction of the infrastructure, certain matters will have been completed (e.g. design, the obtaining of all necessary approvals and consents or the diversion of utilities), the contract negotiations should be delayed until completion of these matters has been achieved, failing which before any infrastructure contract is signed a new Business Case should be prepared on the basis of the altered assumptions that prevail and should be approved by the promoter and owner of the project.

Since then (summary written by this site)

In November 2023, Màiri McAllan, Cabinet Secretary for Transport, Net Zero and Just Transition, stated to the Scottish Parliament that the Scottish Government and its public bodies "already operate in line with these recommendations and best practice" (Màiri McAllan response, Nov 2023). The Minister noted that while the recommendations were directed at project leads and local authority officials, they linked to work being carried out across the administration and its agencies (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).

Addressed to Scottish Government · Full record

ETI-6: Optimism Bias in Business Cases

Noted · No statement from Scottish Government found

Recommended

All versions of the Business Case, including any Business Case required as a result of altered assumptions, should include an assessment of risk that takes account of optimism bias in accordance with the current published government guidance.

Since then (summary written by this site)

In November 2023, Màiri McAllan, Cabinet Secretary for Transport, Net Zero and Just Transition, stated to the Scottish Parliament that while the recommendation was directed at project leads and local authority officials, the administration and its public bodies "already operate in line with these recommendations and best practice" (Màiri McAllan response, Nov 2023). The Minister stated that this was evidenced by an established record of delivering major infrastructure projects, including the Queensferry Crossing and Borders Railway (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).

Addressed to Scottish Government · Full record

ETI-7: External Peer Review

Noted · No statement from Scottish Government found

Recommended

The assessment of risk at each stage mentioned in Recommendation 6 should be the subject of a peer review by external consultants with experience of similar large-scale infrastructure projects in the transportation sector who should submit a report of each review to the promoter and owner of the project as well as to the procurement and project manager sufficiently far in advance of the signature of the infrastructure contract to enable the promoter and owner to consider whether to authorise its signature and, as appropriate, to consider any other available options requiring a strategic decision.

Since then (summary written by this site)

In November 2023, Màiri McAllan, Cabinet Secretary for Transport, Net Zero and Just Transition, stated to the Scottish Parliament that her administration and its public bodies "already operate in line with these recommendations and best practice" across major infrastructure projects (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).

Addressed to Scottish Government · Full record

ETI-8: Update Optimism Bias Guidance

Noted · No statement from Scottish Government found

Recommended

The existing Guidance on optimism bias was based on empirical data available almost two decades ago and should be revised to take into account the additional data that is now available. In particular, the reference classes should be updated to include a specific reference to light rail projects and the recommended uplifts for the different reference classes should be adjusted to reflect the additional empirical data that is now available. Thereafter the Guidance should be reviewed and revised to take account of additional data on a regular basis at intervals of not more than five years.

Since then (summary written by this site)

In November 2023, Màiri McAllan, Cabinet Secretary for Transport, Net Zero and Just Transition, stated to the Scottish Parliament that the administration follows detailed guidance on procurement, risk, and optimism bias enshrined in the Treasury's Green Book, the Scottish Public Finance Manual, and the Client Guide to Construction Projects (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).

Addressed to Scottish Government · Full record

ETI-9: Risk Management Standards

Noted · No statement from Scottish Government found

Recommended

The identification and management of risk should be an integral part of the governance of all major public-sector contracts in future. In identifying and managing risk the following principles should be adopted: • Probabilistic forecasts rather than single-point forecasts should be used to take account of the risk appetite of funders and project sponsors. • Funders, sponsors and project managers should be cautious when adjusting uplifts and there should be critical review of claims that mitigation measures have reduced project risk. • Effective governance needs to provide constant challenge and control of the project, including recording of where the project is compared with its baseline, and reacting quickly to get the project back on track, whenever there are signs that it is veering off course. This necessitates providing senior decision-makers with data-driven reports on project performance and forecasts combined with reports by the management team and independent audits. • In reporting to governance bodies there should be special emphasis on detecting early warning signs that the cost, schedule and benefit risks may be materialising so that damage to the project can be prevented. If early warning signs do emerge, the project should revisit assumptions and reassess risk and optimism bias forecasts. • The quality of evidence rather than process is the key to providing effective oversight and validation.

Since then (summary written by this site)

In November 2023, Màiri McAllan, Cabinet Secretary for Transport, Net Zero and Just Transition, stated that the Scottish Government and its public bodies "already operate in line with these recommendations and best practice" as demonstrated by their delivery of major infrastructure projects (Màiri McAllan response, Nov 2023). In February 2024, the City of Edinburgh Council Transport and Environment Committee agreed that a report would be brought back setting out what funding had been allocated and what measures would be taken regarding recommendation 9 on risk and optimism bias (City of Edinburgh Council, Feb 2024).

Addressed to Scottish Government · Full record

ETI-11: Public Fund Protection

Noted · No statement from Scottish Government found

Recommended

The Scottish Ministers and local authorities responsible for funding light rail projects should be mindful at all times of their obligation to protect public funds and to obtain value for public expenditure. In that regard: • the Scottish Ministers should impose conditions on the payments of grants, similar to the “hold points” imposed on the offer of grant made on 19 March 2007 that enable them to review at each “hold point” whether the scheme is continuing to meet its objectives and to determine whether to continue to support the funding and implementation of the scheme; • continued financial support from the Scottish Ministers should require their critical review of all versions of the draft Business Case and their approval of the FBC as well as their review, and approval before their signature, of the draft contracts for the delivery of the project; • the Scottish Ministers should be involved in the delivery of the project as they were before the withdrawal of the support of officials from Transport Scotland in 2007 and following the resumption of infrastructure works after the mediation settlement at Mar Hall; and • as a condition of the grant the local authority should be obliged to comply with the project monitoring and control procedures of Transport Scotland and should ensure that robust, transparent, externally verifiable project controls for the project are in place.

Since then (summary written by this site)

In November 2023, Cabinet Secretary for Transport, Net Zero and Just Transition Màiri McAllan told the Scottish Parliament that effective collaboration was central to shared priorities under the Verity House Agreement (Màiri McAllan response, Nov 2023). The Minister stated that while delivery responsibility must remain with councils as project leads, she had "absolutely no hesitation in championing close working with our local authority partners" (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).

Addressed to Scottish Government · Full record

ETI-12: Record Keeping Requirements

Noted · No statement from Scottish Government found

Recommended

For reasons of transparency and accountability for public expenditure, the Scottish Ministers should keep minutes of: • the nature and content of any discussions and the reasons for any decisions taken at all meetings, discussions or telephone conversations, and in email or other correspondence between a Minister and civil servants relating to the nature and extent of any involvement by civil servants in the procurement and delivery of a project funded or to be funded in whole or in part from public funds (including a grant from the Scottish Ministers); • all discussions between a Minister and representatives of a local authority, the company responsible for the procurement and delivery of a publicly funded project or the company responsible for its construction to record what was discussed and what, if any, decisions were reached and the reasons for any such decision; • all discussions between a Minister and civil servants including telephone discussions concerning any negotiations, including, but not restricted to, negotiations at mediation, for settling disputes involving contracts funded or to be funded in whole or in part from public funds (including a grant from the Scottish Ministers) to record what was discussed and what, if any, decisions were reached and the reasons for any such decision.

Since then (summary written by this site)

In November 2023, Cabinet Secretary for Transport, Net Zero and Just Transition Màiri McAllan stated that robust procedures regarding minute-taking and documentation management had long been embedded across the civil service (Màiri McAllan response, Nov 2023). The Minister added that the Permanent Secretary had recently reiterated to a parliamentary committee the commitment to maintaining systems to record and manage this information (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).

Addressed to Scottish Government · Full record

ETI-13: Utility Diversion Planning

Noted · No statement from Scottish Government found

Recommended

The procurement strategy for any future light rail project should make adequate provision for the uncertainties concerning the location of utilities and redundant equipment belonging to present and past utility companies, particularly in urban centres. In particular, although it is not possible to be prescriptive about the appropriate timescale: • the procurement strategy should include a requirement that the route of the track should be exposed and cleared of utilities well in advance of the infrastructure contractors commencing their work; • the procurement strategy should specify the period that should elapse between the exposure and clearance of the route and the commencement of construction, to ensure that the contractors have unrestricted access to the construction site and may proceed with the infrastructure works unencumbered by the presence of utilities; and • in fixing the period mentioned above, the procurement strategy should take into account the length of the route to be constructed, past experience of the time taken for the diversion of utilities in light rail projects in other parts of the UK and any additional constraints peculiar to the project such as an embargo on work to divert utilities during particular periods such as the festive season or special events (e.g. the Edinburgh Festival).

Since then (summary written by this site)

In November 2023, Cabinet Secretary for Transport, Net Zero and Just Transition Màiri McAllan stated to the Scottish Parliament that the Scottish Government and its public bodies already operated in line with the recommendation and best practice (Màiri McAllan response, Nov 2023). In April 2024, Paul Lawrence, Executive Director of Place at the City of Edinburgh Council, reported that the Council did not accept the recommendation, noting that clearing utilities immediately prior to construction had been effective on the Trams to Newhaven project and should remain an option for future schemes (Paul Lawrence, Apr 2024).

Addressed to Scottish Government · Full record

ETI-14: Utility Diversion Risk Management

Noted · No statement from Scottish Government found

Recommended

Although some participants in the Inquiry criticised the use of MUDFA to divert utilities in advance of the infrastructure works and advocated the “bow wave” approach to the diversion of utilities that followed the mediation settlement at Mar Hall, I do not think it appropriate to be prescriptive about how the risks associated with the diversion of utilities are managed. It is sufficient for promoters of light rail schemes to be aware of such risks and to demonstrate that they have adequate proposals for managing them.

Since then (summary written by this site)

In November 2023, Màiri McAllan, Cabinet Secretary for Transport, Net Zero and Just Transition, stated to the Scottish Parliament that the Scottish Government and its public bodies "already operate in line with these recommendations and best practice" through their delivery of major infrastructure projects (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).

Addressed to Scottish Government · Full record

ETI-18: Interviews of Key Personnel in Readiness Reviews

Noted · No statement from City of Edinburgh Council found

Recommended

As part of their investigations, representatives of OGC undertaking an independent “readiness review” of a publicly funded project and representatives of any person, including representatives of any public body such as Audit Scotland, undertaking a review of the progress of and/or expenditure on a project funded in whole or in part by public funds should interview key personnel involved in the project to ensure that each of them understands his or her role and is performing it effectively. In preparing any list of key personnel to be interviewed, the individuals undertaking the investigations shall include the person designated as SRO.

Since then (summary written by this site)

In December 2023, Andrew Kerr, Chief Executive of the City of Edinburgh Council, stated that while the recommendation was for third parties undertaking future reviews or audits, he recommended that the council agree to support any such review or audit to ensure "a clear understanding of roles and responsibilities" (Andrew Kerr response, Dec 2023). The record holds no update since the council's response of December 2023 (Andrew Kerr response, Dec 2023).

Addressed to City of Edinburgh Council · Full record

Reports and timeline

Timeline

Inquiry Announced

Scottish Ministers established an inquiry into the Edinburgh Tram Project.

Source

Chair and Terms of Reference announced

Source

Chair appointed by letter

Source

First preliminary hearing

Source

Oral evidence hearings begin

Source

Oral evidence ends

Source

Oral closing submissions concluded

Source

Final Report Published

Report published with 24 recommendations.

Source

Show all 10 milestones

Government Response

Scottish Government response to recommendations.

Inquiry Closed

Lord Hardie notified the First Minister that the inquiry had ended and published an explanatory note.

Source

Parliamentary activity

2 mentions since Mar 2003

European Tram Driver Championship

Early Day Motion House of Commons Christine Jardine · Liberal Democrat

Said: That this House congratulates Edinburgh Trams Drivers Emma White and Jason Moffat on their selection to represent Edinburgh Tram Driver Championship in Warsaw; recognises the skill, expertise and dedication required to compete in the championship which brings together tram drivers from across Europe and beyond; …

EDINBURGH TRAM NETWORK

Early Day Motion House of Commons Mark Lazarowicz · Labour

Said: That this House welcomes the announcement by the Scottish Executive of funding of ú375 million for the proposed Edinburgh tram network; and urges elected representatives at all levels of government in Scotland to put their backing behind these proposals which will benefit the wider Scottish …

View all 2 mentions →

Evidence & impact

AI-generated · 26 Mar 2026
The Edinburgh Tram Inquiry, chaired by Lord Hardie, examined the planning and construction of Edinburgh's tram system, which experienced significant cost overruns and delays. The inquiry published 24 recommendations in August 2023 focusing on project governance, management practices, and legal reforms.

The Scottish Government accepted 14 recommendations (58%), accepted 7 in principle (29%), and placed 3 under consideration (12%). In its November 2023 response, the Government stated that enhanced procedures for documentation management had been embedded within government and that guidance for establishing inquiries was already in development. The Government noted its commitment to collaborative working through the Verity House agreement, whilst maintaining that responsibility for project delivery remains with councils.

City of Edinburgh Council's Chief Executive reported to the Transport and Environment Committee in November 2023, recommending acceptance of several recommendations. Council Leader Cammy Day acknowledged that "serious mistakes were made in the construction of the original tram line" and noted that processes implemented since the original project had helped deliver the successful Trams to Newhaven extension.

The Council reported that scrutiny of ALEOs had "significantly improved" following reviews in 2012 and 2016, resulting in formalised observer roles and increased committee scrutiny. Training on the Member/Officer Protocol was being delivered to senior officers to clarify the distinction between officer and councillor roles.

Three recommendations regarding civil damages provisions and criminal offences for misleading evidence to inquiries remain under consideration by the Scottish Government, which noted that existing remedies may already exist under delictual liability and fraud law.

Whilst both the Scottish Government and City of Edinburgh Council provided initial responses accepting most recommendations, published evidence of specific implementation actions remains limited for many recommendations, particularly those relating to project management expertise requirements, governance structures, and stakeholder co-location practices.
Reforms attributed to this inquiry · AI-generated- Enhanced procedures for minute-taking and documentation management embedded within Scottish Government and Civil Service (Scottish Government statement, November 2023)
- Improved scrutiny arrangements for Arms Length External Organisations (ALEOs) by City of Edinburgh Council, including formalised observer roles and regular committee reporting following 2012 and 2016 reviews
- Member/Officer Protocol training delivered to senior officers at City of Edinburgh Council to clarify distinction between officer and councillor roles
- Guidance for efficient establishment of inquiries developed and shared with recent inquiries (Scottish Government statement, November 2023)
Unfinished business · AI-generated- Recommendations on civil damages provisions and criminal statutory offences for misleading evidence to inquiries remain under consideration by Scottish Government
- No published evidence of action on recommendations regarding project management expertise requirements for light rail projects
- No published evidence of progress on recommendations for governance structure guidance and role clarity in major projects
- No published evidence regarding recommendations on co-location of project stakeholders
- No published evidence of updates to guidance on best practices for light rail delivery, despite Scottish Government stating it already operates in line with best practices

Key facts

Duration: 12 years, 1 month Total reported cost: £13.2m Witnesses: 85 Hearing days: 59 Core participants: 14 Documents disclosed: 6,000,000 Report pages: 961