ETI-13 Accepted

Utility Diversion Planning

Edinburgh Tram Inquiry · Edinburgh Tram Inquiry Report · Issued 1 August 2023 · Addressed to: Scottish Government

Source — verbatim from the inquiry

Inquiry recommendation, Chapter 25 Recommendation 13 (paragraph 25.225)

The procurement strategy for any future light rail project should make adequate provision for the uncertainties concerning the location of utilities and redundant equipment belonging to present and past utility companies, particularly in urban centres. In particular, although it is not possible to be prescriptive about the appropriate timescale:
• the procurement strategy should include a requirement that the route of the track should be exposed and cleared of utilities well in advance of the infrastructure contractors commencing their work;
• the procurement strategy should specify the period that should elapse between the exposure and clearance of the route and the commencement of construction, to ensure that the contractors have unrestricted access to the construction site and may proceed with the infrastructure works unencumbered by the presence of utilities; and
• in fixing the period mentioned above, the procurement strategy should take into account the length of the route to be constructed, past experience of the time taken for the diversion of utilities in light rail projects in other parts of the UK and any additional constraints peculiar to the project such as an embargo on work to divert utilities during particular periods such as the festive season or special events (e.g. the Edinburgh Festival).

Edinburgh Tram Inquiry, Edinburgh Tram Inquiry Report · 1 Aug 2023 Source PDF →

Published evidence summary

Publicly available evidence relating to this recommendation:

- In November 2023, the Scottish Government stated it already operates in line with best practices for governance and light rail delivery (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published updated procurement guidance specifically addressing utility location uncertainties, requiring route exposure and clearance before construction, has been identified to March 2026.
How was this evidence gathered?
Evidence searched by Claude (Anthropic) on 10 Apr 2026
Checked data held on this site (government responses, progress updates, independent evidence)
This recommendation applies across many organisations. The evidence above reflects central policy activity; adoption in individual organisations may vary.

Response — verbatim from government

Scottish Government

The Scottish Government stated it already operates in line with best practices for governance and light rail delivery. Source: Transport Secretary Statement, 2 November 2023.

Scottish Government · 2 Nov 2023 Written response →

Evidence trail — what's actually happened since

  • 2 Nov 2023 Initial status based on Scottish Government and City of Edinburgh Council responses to the Edinburgh Tram Inquiry Report (September 2023). Source →

Each entry above links to a primary source — gov.uk written statement, consultation response document, or inspection report. The Index does not characterise government intent; it tracks what has been published.

How this page is built

Source and Response are verbatim from primary documents. The Evidence trail records published activity since — written statements, consultation outcomes, inspection findings, parliamentary references. The Index does not paraphrase or characterise intent; it tracks what has been published. Where the evidence is the absence of action (a missed deadline, a slipped timetable), that absence is documented from primary sources rather than inferred.

This recommendation's data is verified periodically against primary sources. The Index is monitored for staleness weekly.