Recommendation 24
Third Report - “We’re going to need a bigger Navy”
Published 14 Dec 2021
Paragraph 156
Addressed to Ministry of Defence
Defence Committee The Navy: purpose and procurement All items in this report Report on parliament.uk ↗ Inquiry on parliament.uk ↗
Recommendation (the committee's words)
Proper scrutiny is essential to ensure programmes are delivered on time. In order to allow for proper scrutiny of ongoing programmes, the Ministry of Defence should emulate the US Department of Defense and provide Parliament with an annual shipbuilding plan, including the number of ships planned to enter and leave service each year in the next 30 years. We ask that the Senior Responsible Owners for the Type 26, Type 31, Astute and Dreadnought programmes provide the Committee with an annual report on each of their programmes within six months of the publication of this report, and then annually. If necessary, we will expect the SROs to answer additional questions on their programmes in a public evidence session.
From: Defence Committee, Third Report - “We’re going to need a bigger Navy” (HC 168), paragraph 156, 14 December 2021
Government response
The government responded to the whole report on 25 February 2022 (deadline 14 February 2022).
Summary written by Accountability Index from the government's response. It is not the government's own words.The government welcomes the Defence Committee's report and sets out the Integrated Review commitments it says address the Royal Navy's role, fleet and shipbuilding, while declining to guarantee a pipeline of work for UK yards.
- On fleet size, the MOD says it is "confident it can realise the ambitious plans outlined in the IR", including up to five Type 32 frigates alongside five Type 31s, so that by 2030 frigates and destroyers "will increase beyond the current 18".
- On reporting, the department "will provide a single annual update to the Defence Committee" covering surface fleet availability and shipbuilding plans. On submarine availability it says it does not comment, as this "would, or would be likely to, prejudice" security.
- On Fleet Solid Support ships, the final manufacture contract "will be awarded to a UK business, either solely or as part of a consortium", with all three ships integrated in UK shipyards. The Contract Notice requires all three to be in service by 2032.
- On Carrier Strike, the government says it remains "on course" for Full Operating Capability in December 2023 and intends to "routinely deploy a CSG annually", with each deployment to be "bespoke" in composition and objectives.