Thirty-Ninth Report - Lessons from major projects and programmes

Public Accounts Committee HC 694 Published 29 January 2021
Report Status
Government responded
Conclusions & Recommendations
29 items (6 recs)
Government Response
AI assessment · 29 of 29 classified
Accepted 21
Acknowledged 2
Not Addressed 2
Rejected 4
Government response
Treasury minutes: Government response to the Committee of Public Accounts on the Thirty ninth report from Session 2019-21 · published 26 Mar 2021
Read the government response ↗ Response on the Index
Filter by: Clear

Recommendations & Conclusions

2 items
1 Conclusion Not Addressed

On the basis of a report by the Comptroller and Auditor General, we took evidence...

Conclusion
On the basis of a report by the Comptroller and Auditor General, we took evidence from the Infrastructure and Projects Authority (the IPA) about the delivery and assurance of government major programmes.1
Government Response Summary
The government acknowledges the committee's procedural opening statement, confirming the report's basis and the evidence-taking process.
HM Treasury
View Details →
9 Conclusion Not Addressed

Within the National Infrastructure Strategy, the government also announced the initiatives that had come out...

Conclusion
Within the National Infrastructure Strategy, the government also announced the initiatives that had come out of Project Speed, which it set up over the summer to review the infrastructure project life cycle and identify where improvements could be made in … Read more
Government Response Summary
The government described Project Speed as an initiative to deliver infrastructure projects better, greener, and faster, mentioning 85 reforms announced in November 2020, and stated its focus on implementing these, but did not address the committee's concern about hindering scrutiny.
HM Treasury