Sixty-Fourth Report - The Emergency Services Network

Public Accounts Committee HC 1006 Published 14 July 2023
Report Status
Government responded
Conclusions & Recommendations
30 items (6 recs)
Government Response
AI assessment · 29 of 30 classified
Accepted 18
Acknowledged 6
Not Addressed 5
Filter by: Clear

Recommendations

1 result
14 Acknowledged

Airwave extension requires uncosted investment in infrastructure and agreement with Motorola

Recommendation
The CMA has proposed a charge control on Airwave which, once implemented, will make Airwave cheaper for the Department and emergency services.41 The Department considers that it can extend Airwave without creating a gap in service and without any negotiation … Read more
Government Response Summary
The government acknowledges the implications of the CMA charge control on Airwave, stating it is reviewing the business case to reflect the ruling and engaging with users to support transition activities, but does not explicitly commit to issuing an extension notice or fully costing future Airwave investment needs.
HM Treasury
View Details →

Conclusions (5)

Observations and findings
7 Conclusion Acknowledged
The Department said it was not being complacent, but acknowledged that even with the best team and governance arrangements it could assemble there was both considerable risk and a lot of work to do before ESN would be ready.16 Nevertheless, it was determined to ‘crack on’ with ESN and was …
Government Response Summary
The government agrees with the committee’s observation regarding the risks and challenges of ESN and states it is fully focused on these, with ongoing involvement of the Independent Assurance Panel and progress towards a target completion date of June 2024 for the Lot 2 award.
View Details →
10 Conclusion Acknowledged
The emergency services contribute, alongside funding from the Department, the Department of Health & Social Care and the Scottish and Welsh governments, to the cost of ESN. Delays to ESN meant the Department itself has spent less than it expected on ESN.28 But emergency services have had to pay for …
Government Response Summary
The government agrees with the committee's observations, stating that if a CMA decision is upheld, there may be scope to reduce Airwave costs for users, and the department will engage to determine support for transition. However, central financial support is limited, and the ESMCP is reviewing the business case to reflect the CMA ruling and new suppliers.
View Details →
12 Conclusion Acknowledged
We asked the emergency services if they could quantify how much delays to ESN had cost them. The ambulance service interacts with ESN through the Ambulance Radio Programme (ARP) on which it had spent £9.5 million.34 The fire service said it had spent £6 million preparing for transition, and £2 …
Government Response Summary
The government agrees with the committee's findings on the costs incurred by emergency services due to ESN delays, but states that central financial support is limited. It notes potential future cost reductions for Airwave users if a CMA decision is upheld, and the department will engage with users for transition activities.
View Details →
13 Conclusion Acknowledged
We asked the Department how the transition from Airwave to ESN would be funded. It said it would work with users to make transition affordable, but the only way to do this was through usual ‘fiscal events’.37 Although it said it would try and minimise the financial impact, it acknowledged …
Government Response Summary
The government acknowledges the funding challenges for the Airwave to ESN transition, stating that future funding decisions are subject to HM Treasury spending reviews and that the ESMCP is reviewing the business case to incorporate CMA ruling impacts, expecting user savings from reduced Airwave costs.
View Details →
23 Conclusion Acknowledged
The Department recognised that the split of responsibilities between its ESN suppliers is suboptimal.76 The Independent Assurance Panel told us that the complexity had been increased in 2015, when amended contracts had made the Home Office responsible for systems integration, a task it did not have the skills to do.77 …
Government Response Summary
The government agrees with the committee's observations regarding the suboptimal split of responsibilities, stating it has focused on addressing integration complexity. It will commission the IAP to monitor integration plans for the User Services contract and is strengthening its Programme Management team with specialist recruitment and external technical expertise.
View Details →