Select committee: Public Accounts Committee
Conclusion 20
17th Report - The Remediation of Dangerous Cladding
Published 21 Mar 2025
Addressed to HM Treasury
Public Accounts Committee The Remediation of Dangerous Cladding All items in this report Report on parliament.uk ↗ Inquiry on parliament.uk ↗
Conclusion (the committee's words)
We asked witnesses if the construction industry had the capacity to support the acceleration of remediation. The HBF told us acceleration was happening, but that it would be challenging. It outlined some of the challenges facing the sector, including an ageing construction workforce and Brexit, where stricter visa requirements have meant that some European builders have been unable to work in the UK. The Local Government Association (LGA) told us that developers, local councils and housing authorities were competing for the same limited pool of resources and that developers could probably outbid the others. MHCLG told us that it had not seen a shortfall in the capacity of the construction industry but said it was working closely with the Construction Leadership Council to provide modular training, for example, on façade engineering and cladding.32
From: Public Accounts Committee, 17th Report - The Remediation of Dangerous Cladding (HC 362), 21 March 2025
Government response
Latest Treasury Minutes progress report to the Committee of Public Accounts on the Seventeenth Report of Session 2024-26
The government responded to the whole report on 4 June 2026.
Treasury minutes: Government response to the Committee of Public Accounts on the Seventeenth report from Session 2024-25
Published 16 May 2025.
Summary written by Accountability Index from the government's response. It is not the government's own words.The government agrees with most of the Committee's recommendations on the remediation of dangerous cladding, with target dates between summer and December 2025, but disagrees with the recommendation on construction manufacturers paying a share of remediation costs.
- On the Remediation Acceleration Plan, the government agrees to update the Committee in Autumn 2025. It says it "has not seen significant evidence that non-cladding defects are slowing down remediation" but is committed to removing blockers.
- On construction manufacturers paying a share of remediation costs, the government disagrees. It says it is consulting on redress routes in the Construction Products Reform Green Paper and that leaseholders and tenants are protected from the cost of cladding remediation.
- The government will publish latest building number estimates "by the summer", but the timing of cost and completion date estimates "will depend on the outcome of the forthcoming Spending Review".
- On insurance, the government agrees and will share an update on progress by the end of 2025. It is gathering data on premiums and is considering whether government "might support industry to reduce fire related liabilities".