Select committee: Public Accounts Committee
Conclusion 28
67th Report - NS&I’s transformation programme
Published 13 Feb 2026
Addressed to HM Treasury
Public Accounts Committee NS&I’s transformation programme All items in this report Report on parliament.uk ↗ Inquiry on parliament.uk ↗
Conclusion (the committee's words)
The Treasury had applied its usual scrutiny to the Programme’s Outline Business Case in 2020 and Full Business Case in 2023, approving each subject to conditions.80 The Treasury said it had been satisfied by the spend data in the business case it approved, but the NAO found that there were errors in the spend reported.81 The Treasury told us it had thought it had clarity on the programme spend when approving the business case, but between business case approvals it had less clarity over spend, the Treasury agreed that money spent on the Programme is not available for other public service.82 The Treasury noted that determining whether the programme is within budget depends on the plan being developed by NS&I.83
From: Public Accounts Committee, 67th Report - NS&I’s transformation programme (HC 1237), 13 February 2026
Government response
The government responded to the whole report on 7 April 2026 (deadline 13 April 2026).
Summary written by Accountability Index from the government's response. It is not the government's own words.The government states that it "agrees with the Committee's recommendation" on each of the recommendations in the report, and sets target implementation dates between June and Autumn 2026.
- On the integrated plan, the government agrees that NS&I should prepare a realistic plan. NS&I is developing costed options, which will form the basis of a revised Full Business Case in the second quarter of 2026-27, "subject to Treasury and Ministerial process timings".
- NS&I will write to the Committee "within six months" setting out the integrated plan, including timelines and a revised estimated cost, and will provide a written update on its risk management framework "by June 2026".
- On culture, a business-wide programme of cultural change activity will be developed, with an initial plan to go to the Board and the Treasury in early Summer 2026 for "rolling implementation over the coming 12-18 months".
- The Treasury says it will evaluate NS&I's agreed plan through a full Treasury Approval Panel process and will write to the Committee in the Autumn on lessons learned from its oversight.