Restoration and renewal
Closed
What the inquiry looked at
“In January 2018, following 20 years of discussion, Parliament approved the Restoration and Renewal programme, with an Act establishing the programme and overarching governance receiving Royal Assent in October 2019. It aims to address maintenance issues, with the Palace described as soon to become ‘uninhabitable,’ and wider objectives. The NAO’s report ‘Palace of Westminster Restoration and Renewal Programme’ sets out the scope and position of the programme, and the main risks that need to be managed as it progresses. The report finds that Parliament has made slow progress establishing the programme, this and the challenges undertaking maintenance, have meant a ‘make-do-and-mend’ maintenance approach, increasing costs and risks. The programme is still in the early stages, with an outline business case expected in summer 2022. To oversee and deliver the programme, Parliament has created a Sponsor Body, a delivery authority structure which has worked well elsewhere, but does not guarantee success. It is now transitioning responsibilities to the Sponsor Body which is, for example, responsible for setting the programme’s high-level requirements. Correct structures at this stage will be critical to success. The NAO concludes that the Sponsor Body is learning from other programmes on how to establish effective governance arrangements; identify and manage risks; and be clear about the interdependent projects such as Northern Estates, which need to be delivered on time.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
The Palace of Westminster continues to be badly in need of repair. Failing mechanical and electrical systems, falling masonry and the constant risk of a catastrophic fire requires expensive round-the-clock remedial work to ensure the safety of the 5,000 Members, Peers and staff who work in the building, as well as the million visitors who come to the Palace in a typical year. For more than 20 years, Parliament has been talking about undertaking significant works to restore the Palace, but the building work has yet to begin. However, the Sponsor Body, responsible for overseeing the Restoration and Renewal Programme on Parliament’s behalf, has only just been established and a business case to take forward the work is still almost two years away.
The Programme is made ever-more complex by the number of uncertainties which underpin it, including the condition of the building, interdependencies with other parliamentary building projects, the lack of consensus over where Parliamentarians and staff will relocate to while the work is undertaken, and what people want from a modern parliament building. This Committee has seen time and time again how these uncertainties can lead to increased costs and delays to projects. While making sure the Sponsor Body understands the opinions and needs of current Members of the House of Commons and the House of Lords is sensible, we are concerned that its decision to commission a formal review will reopen previous decisions and cause further delay.
The Sponsor body must learn lessons from past projects and make use of existing expertise to reduce these uncertainties and so reduce the risk to taxpayer money. The current ‘make do and mend’ approach to maintaining the Palace is both unsustainable and does not constitute value for money. Every week of delay costs the taxpayer £2 million and puts the safety of employees and visitors at risk. Further delays are a risk to the Programme that it can ill-afford. It is essential that it now moves quickly to avoid further unnecessary costs to the taxpayer and ensures a safe, modern Parliament.
What the government said
The government responded on 18 November 2020. The deadline was 2 December 2020.
The government states that the Sponsor Body is not a government body, so it will provide responses to the Committee's recommendations on the Restoration and Renewal report directly to the Committee.
- The document sets out no government position on the individual recommendations; the Sponsor Body, not the government, is to respond to them.
- Under the Parliamentary Buildings (Restoration and Renewal) Act 2019, the Sponsor Body is responsible for the strategic direction of the Programme and oversees a Delivery Authority, which undertakes the works.
- The document states that Parliament will not run the Programme itself, but members of both Houses will be asked to approve the Sponsor Body's business case and will be responsible for approving and scrutinising the funding.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 23 June 2020 to its close on 2 December 2020. The dashed mark is the deadline Parliament records for the government's response.
- Oral evidence 21 Jul 2020
- Report 5 Oct 2020
- Government response 18 Nov 2020
- Correspondence 3 Nov 2020
What it recommended 9 recommendations · 15 conclusions
2We are concerned that re-opening decisions made earlier in the Programme risks further delays.
3Successful delivery of the Programme is heavily reliant on many factors which are still uncertain.
4The Programme is also dependent on several factors outside the Sponsor Body’s control.
5The Sponsor Body has not made it clear how it will balance Parliament’s range of...
6The Sponsor Body has not engaged sufficiently with the public and other Palace users to...
1On the basis of a report by the Comptroller and Auditor General, we took evidence...
7Since the establishment of the Programme in 2012, it has taken 8 years to the...
8The Sponsor Body did not want to commit to when the Programme might commence construction...
9In May 2020, the Sponsor body announced a strategic review; it expects to report in...
10The continual re-opening of decisions risks delaying the Programme even further with the concomitant risks...
11The Programme is at an early stage with a large number of uncertainties.
12The Sponsor Body considers that the current biggest risk to the Programme is uncertainty on...
13The current expectation is that during the Programme, the Commons will decant to Richmond House.
14The Sponsor Body told us that there is currently no clarity “about whether some, all...
15In addition to the NEP, the parliamentary estates team is currently managing other projects, such...
16The Director General of the House of Commons told us that the House and the...
17As a Parliamentary rather than government project, the Infrastructure and Projects Authority (IPA) has no...
18The Sponsor Body has not yet developed cost and time estimates as it is unclear...
19While almost all Members of Parliament agree that restoration is necessary, there is not agreement...
20Most recently, in July 2020, the Prime Minister wrote to the Sponsor Body and the...
21The Sponsor Body told us that it has established a challenge panel, as part of...
22In May, the Sponsor Body published its Member consultation strategy as required under the legislation,...
23The Sponsor Body has not finalised its overarching engagement strategy and has yet to develop...
24The Sponsor Body is currently considering how it might best approach a public engagement strategy.53...
Evidence
Oral evidence sessions 1
- 21 Jul 2020Restoration and renewal5 witnesses, listed belowparliament.uk ↗
Who gave evidence 5 witnesses
- David GoldstoneIndependent Chair at The Office for Value for Money, HM Treasury
- Dr John BengerClerk of the House, House of Commons
- Ed OllardAccounting Officer, House of Lords
- Ian AillesDirector General, House of Commons
- Sarah JohnsonCEO, Parliamentary Works Sponsor Body