Source · Select Committees · Public Accounts Committee
Recommendation 8
8
The Sponsor Body did not want to commit to when the Programme might commence construction...
Conclusion
The Sponsor Body did not want to commit to when the Programme might commence construction work until the business case is complete.14 However, the Clerk of the House of Commons told us that “doing nothing is very expensive” and that any further unnecessary delay is costly to the taxpayer and puts the deteriorating building at greater risk from a catastrophic event.15 The strategic review
Government Response
A response document is linked to this report, dated 18 November 2020. Response attribution to this conclusion has not been verified. Read the response document ↗