Source · Select Committees · Public Accounts Committee
Recommendation 11
11
Deferred
The Programme is at an early stage with a large number of uncertainties.
Conclusion
The Programme is at an early stage with a large number of uncertainties. The actual condition of the Palace, for which there is a lack of documentation, is unknown.22 For Parliament to return to the refurbished Palace in the 2030s as planned, a series of interdependent projects, currently under the control of the parliamentary estates team rather than the Sponsor Body, must be delivered in sequence and on time, including decant arrangements for Members, Peers and staff.23 In addition, as the Sponsor Body does not yet have agreement in the form of a business case for what the Programme is required to undertake, it is currently unable to produce cost and time ranges for the Programme delivery.24 Palace condition
Government response summary AI-generated
The government states that the Sponsor Body is not a government body and will provide responses directly to the Committee.
Summary of the government's response below — read the verbatim text to verify.
Government Response
Deferred
HM Government · verbatim extract
Deferred
Responses to the Committee The Sponsor Body is not a government body so will provide responses to the recommendations in the PAC report directly to the Committee.
Read the full response on Parliament ↗