Select Committee · Public Accounts Committee

Restoration and renewal of Parliament

Status: Closed Opened: 26 Jan 2022 Closed: 2 Sep 2022 11 recommendations 29 conclusions 1 report

Over a year ago the Committee reported that every week of delayed repairs to crumbling Parliament was costing the taxpayer another £2 million . The Palace of Westminster Restoration and Renewal Programme, widely endorsed as a necessity to preserve a historically and politically significant building, is at a critical stage: its next formal milestone is … Show more

Clear

Reports

1 report
Title HC No. Published Items Response
Tenth Report - Restoration and Renewal of Parliament HC 49 29 Jun 2022 40 Responded

Recommendations & Conclusions

12 items
3 Recommendation Tenth Report - Restoration and Renewal … Acknowledged

Critical value for money risks, which we have previously highlighted, have still not been addressed.

Critical value for money risks, which we have previously highlighted, have still not been addressed. The NAO’s January 2022 report found that risks we identified in our October 2020 report remained. This included the Sponsor Body managing factors outside its control, with the most significant interdependent projects delayed or paused. … Read more

Government response AI summary
The Clerk of the House and the Clerk of the Parliaments agree with the Committee’s recommendation to ensure the relevant authorities address the recommendations made in previous PAC and NAO reports, though note it is for both Houses to ultimately agree the programme’s objectives and …
Read full response →
HM Treasury
1 Conclusion Tenth Report - Restoration and Renewal … Acknowledged

On the basis of a report by the Comptroller and Auditor General, we took evidence...

On the basis of a report by the Comptroller and Auditor General, we took evidence on the restoration and renewal of the Palace of Westminster (the Palace) from the Sponsor Body Chief Executive Officer, the Delivery Authority Chief Executive, the Clerk of the House and the Clerk of the Parliaments.2 … Read more

Government response AI summary
The government welcomes the Public Accounts Committee’s report of 29 June 2022 “Restoration and renewal of Parliament” and thanks the Committee for its consideration of the topic.
Read full response →
HM Treasury
10 Conclusion Tenth Report - Restoration and Renewal … Acknowledged

In March 2022, the Delivery Authority had already lost some newly recruited staff and access...

In March 2022, the Delivery Authority had already lost some newly recruited staff and access to technical contractor expertise. Then, in May 2022, the CEO of the Sponsor Body announced her resignation, along with two other senior members of Sponsor Body staff.27 The Clerk of the House of Commons told … Read more

Government response AI summary
The Clerk of the House and the Clerk of the Parliaments commit to implement this recommendation. The Delivery Authority will remain in place and independent and the CEO of the Delivery Authority will remain accountable for the skills and expertise to deliver the Programme.
Read full response →
HM Treasury
11 Conclusion Tenth Report - Restoration and Renewal … Acknowledged

We questioned the Clerk of the House of Commons on the timeframes and Parliamentary processes...

We questioned the Clerk of the House of Commons on the timeframes and Parliamentary processes required to make any changes and provide more certainty. He told us that the House Commissions had sought additional assurance work ahead of a June 2022 joint meeting to agree a report setting out their … Read more

Government response AI summary
The Clerks commit to implement the recommendation where it is within their powers to do so. They note the timeframe for debates has been achieved, and that they are committed to meeting the indicative timeframe in the Commissions' Report, but that laying regulations is not …
Read full response →
HM Treasury
23 Conclusion Tenth Report - Restoration and Renewal … Acknowledged

In June 2022, the independent review panel recommended that bringing the sponsor function in-house should...

In June 2022, the independent review panel recommended that bringing the sponsor function in-house should be viewed as a pragmatic measure – the sponsor body governance model could be made to work but was unlikely to be viable given the “extent of lost confidence and momentum for bringing the sponsor … Read more

Government response AI summary
The government acknowledges the Panel's conclusion that the governance model for the delivery phase will need to be separately considered and confirmed after the scope and preferred delivery strategy is agreed, stating that governance structures will be considered in the development of the strategic case.
Read full response →
HM Treasury
26 Conclusion Tenth Report - Restoration and Renewal … Acknowledged

The Clerk of the House of Commons recognised the challenge of the Programme’s clients—including Members...

The Clerk of the House of Commons recognised the challenge of the Programme’s clients—including Members and the Commissions—not having a single voice.66 In our view, until Parliament can provide a clear steer on what it wants, it is almost impossible for anything to be delivered.67 We are concerned that the … Read more

Government response AI summary
The Clerks of both Houses agree with the Committee’s recommendation to achieve a single set of objectives and requirements, noting it is for both Houses to ultimately agree. The target implementation date for the new two-tier governance structure is the end of the calendar year, …
Read full response →
HM Treasury
28 Conclusion Tenth Report - Restoration and Renewal … Acknowledged

In our October 2020 report, we noted that success for the Programme depended on factors...

In our October 2020 report, we noted that success for the Programme depended on factors outside the Sponsor Body’s control.73 The NAO’s January 2022 report reported 64 Committee of Public Accounts, Restoration and renewal of the Palace of Westminster, Nineteenth Report of Session 2019–21, HC 549, 2 October 2020 65 … Read more

Government response AI summary
The Clerks of both Houses agree with the recommendation to achieve a single set of objectives and requirements, noting it is for both Houses to ultimately agree. The target implementation date for the new two-tier governance structure is the end of the calendar year, subject …
Read full response →
HM Treasury
29 Conclusion Tenth Report - Restoration and Renewal … Acknowledged

When we last examined the Programme, the House of Commons planned to decant to Richmond...

When we last examined the Programme, the House of Commons planned to decant to Richmond House, creating a temporary chamber.78 We heard that of the £70 million written off when the Commons decided not to pursue this plan, most was related to the planning permission. The Clerk of the House, … Read more

Government response AI summary
The Clerks of both Houses agree with the Committee’s recommendation regarding risks of interdependent programmes, and the target implementation date for implementing the new two-tier governance structure is the end of the calendar year, subject to endorsement by both Houses of Parliament. The programme board …
Read full response →
HM Treasury
33 Conclusion Tenth Report - Restoration and Renewal … Acknowledged

The Delivery Authority has now been tasked with developing new options for undertaking the work...

The Delivery Authority has now been tasked with developing new options for undertaking the work that will involve some continued presence.87 We asked the Clerks if they could manage the risks to users of the building should the House of Commons maintain a presence in the Palace during the works. … Read more

Government response AI summary
The Clerk of the House and the Clerk of the Parliaments agree with the Committee’s recommendation, and the articulation of threshold for risk during the works, acceptability of trade-offs and impact on the approach to works will accompany the strategic case that will be put …
Read full response →
HM Treasury
35 Conclusion Tenth Report - Restoration and Renewal … Acknowledged

Through our work we often see a lack of openness and transparency about programme progress,...

Through our work we often see a lack of openness and transparency about programme progress, performance and decision-making. In January 2021, we concluded it was vital that Parliament’s own major project, the Restoration and Renewal Programme, was an exemplar of an open and transparent project which welcomes full scrutiny.93 84 … Read more

Government response AI summary
The Clerk of the House and the Clerk of the Parliaments agree with the Committee’s recommendation regarding sponsor reporting, stating that quarterly R&R progress reports will continue to be published after the new two-tier governance structures are implemented.
Read full response →
HM Treasury
36 Conclusion Tenth Report - Restoration and Renewal … Acknowledged

For government major programmes, Accounting Officers are expected to assess the delivery risks, publishing a...

For government major programmes, Accounting Officers are expected to assess the delivery risks, publishing a summary of this assessment, and seek a ministerial direction should they consider a decision they are being asked to implement compromises value for money.94 In 2020 the Speaker of the House introduced a procedure, modelled … Read more

Government response AI summary
The Clerks broadly agree with the Committee’s recommendation and are aware of the importance of their roles as Accounting Officers. The government commits to publishing the outcome of any future Independent Advice and Assurance Panels that they commission subject to the agreement of the Commissions.
Read full response →
HM Treasury
38 Conclusion Tenth Report - Restoration and Renewal … Acknowledged

To work quickly, Parliament and the Sponsor Body agreed that parliamentary domestic committees, such as...

To work quickly, Parliament and the Sponsor Body agreed that parliamentary domestic committees, such as the finance committees for each house who support the Commissions, would not scrutinise and endorse the Programme’s assessment of the Programme costs and the impact of continued presence before this material was shared with the … Read more

Government response AI summary
The CEO of the Sponsor Body and the CEO of the Delivery Authority accept this recommendation and state that the domestic committees of the two Houses are key stakeholders and they intend to build on previous positive examples of engagement with domestic committees and will …
Read full response →
HM Treasury

Oral evidence sessions

2 sessions
Date Witnesses
11 May 2022 David Goldstone CBE · Palace of Westminster Restoration and Renewal Delivery Authority, Dr John Benger · House of Commons, Indra Morris · Children’s Services, Communications & Strategy Group, Sarah Johnson · Palace of Westminster Restoration and Renewal Sponsor Body, Simon Burton · House of Lords, Stephanie Brivio · Department for Education, Susan Acland-Hood · The Department for Education View ↗
14 Mar 2022 David Goldstone · HM Treasury, Dr John Benger · House of Commons, Sarah Johnson · Palace of Westminster Restoration and Renewal Sponsor Body, Simon Burton · House of Lords View ↗

Who gave evidence

8 witnesses
WitnessOrganisationSessions
Dr John Benger · Clerk of the House House of Commons 2
Sarah Johnson · Chief Executive Palace of Westminster Restoration and Renewal Sponsor Body 2
Simon Burton · Clerk of the Parliaments House of Lords 2
David Goldstone · Independent Chair at The Office for Value for Mon… HM Treasury 1
David Goldstone CBE · Chief Executive Palace of Westminster Restoration and Renewal Delivery Authority 1
Indra Morris · Director General Children’s Services, Communications & Strategy Group 1
Stephanie Brivio · Director, Safeguarding and Children’s Social Care Department for Education 1
Susan Acland-Hood · Permanent Secretary The Department for Education 1

Correspondence

4 letters
DateDirectionTitle
6 Jul 2022 Correspondence from the House of Commons, House of Lords, Restoration & Renewal…
24 May 2022 Joint Correspondence from Simon Burton, Clerk of the Parliaments, House of Lord…
25 Apr 2022 Public Accounts Committee—follow-up update on the Restoration and Renewal Prog…
30 Mar 2022 Correspondence from Dr John Benger, Clerk of the House of Commons Palace of Wes…