Select Committee · Public Accounts Committee

Future of the Advanced Gas-cooled Reactors

Status: Closed Opened: 12 Jan 2022 Closed: 2 Sep 2022 10 recommendations 21 conclusions 1 report

The UK’s nuclear power is generated primarily by seven advanced gas-cooled reactor (AGR) stations, owned by EDF Energy. The AGRs are scheduled to stop generating electricity during this decade, at which point fuel will be removed and transferred to Sellafield for safe storage. The AGRs will then be transferred to the Nuclear Decommissioning Authority. The … Show more

Clear

Reports

1 report
Title HC No. Published Items Response
Third Report - The future of the Advanced Gas-cooled Reacto… HC 118 20 May 2022 31 Responded

Recommendations & Conclusions

13 items
2 Recommendation Third Report - The future of the Advanc… Accepted

The estimated cost of decommissioning has nearly doubled since 2004–05 and there remains a significant...

The estimated cost of decommissioning has nearly doubled since 2004–05 and there remains a significant risk that the costs will rise further. The estimated cost of decommissioning the AGR stations, plus the PWR at Sizewell B, has increased from £12.6 billion in 2004–05 to £23.5 billion in 2020–21 in real … Read more

Government response AI summary
The Department, working with the trustees of the Fund, should ensure the estimates make explicit allowance for the risk of optimism bias and report back to the Committee on the new estimates when they are available. They will reflect the revised costs for defueling/deconstruction and …
Read full response →
HM Treasury
3 Recommendation Third Report - The future of the Advanc… Accepted

The terms of the 2009 sale of the nuclear stations agreed by the Department with...

The terms of the 2009 sale of the nuclear stations agreed by the Department with EDFE placed a disproportionate amount of risk for meeting future decommissioning costs on the taxpayer. The negotiations surrounding the sale of the stations to EDFE in 2009 were focused on maintaining operations, with less attention … Read more

Government response AI summary
The department agrees to respond by August 2022, but states that FDP policies for new nuclear stations already build upon lessons learned from the AGR stations, highlighting the Energy Act 2008 requirements and periodic reviews of sufficiency.
Read full response →
HM Treasury
5 Recommendation Third Report - The future of the Advanc… Accepted

We are not convinced the Department has struck the right balance in incentivising the NDA...

We are not convinced the Department has struck the right balance in incentivising the NDA and EDFE to deliver safe and efficient defueling of the AGR stations on time while reducing costs. The Department has introduced financial incentives to encourage cost-efficient defueling and station transfer with EDFE potentially earning or … Read more

Government response AI summary
The government agrees to write to the Committee by November 2022 outlining the governance and oversight for monitoring the impact of the incentive on delivery and how that indicates effectiveness of the mechanism.
Read full response →
HM Treasury
6 Recommendation Third Report - The future of the Advanc… Accepted

Arrangements for transferring nuclear stations to NDA are worryingly under- developed, and there is a...

Arrangements for transferring nuclear stations to NDA are worryingly under- developed, and there is a risk that transfer negotiations between EDFE and NDA could drag on and increase the costs to the taxpayer. The first of the stations could transfer to the NDA as early as 2026. The NDA and … Read more

Government response AI summary
The government agrees to provide a detailed transfer plan for Hunterston B by May 2023 and will share it with the committee, along with a summary of progress for other stations.
Read full response →
HM Treasury
10 Conclusion Third Report - The future of the Advanc… Accepted

There remain significant uncertainties which if managed poorly could increase decommissioning costs further.

There remain significant uncertainties which if managed poorly could increase decommissioning costs further. The estimated cost of defueling the seven stations, for example, ranges between £3.1 billion and £8 billion depending upon how quickly they can be defueled and how soon defueling starts once a station closes after stopping electricity … Read more

Government response AI summary
The government agrees with the recommendation to ensure estimates make explicit allowance for the risk of optimism bias as part of the 2022 revaluation. The department will respond by July 2023.
Read full response →
HM Treasury
11 Recommendation Third Report - The future of the Advanc… Accepted

EDFE has recently brought forward the closure date for five out of the seven AGR...

EDFE has recently brought forward the closure date for five out of the seven AGR stations. EDFE told us it expects the stations to stop operating at their current closure dates but acknowledged that early closure was always a risk. Dungeness B was due to close in 2028 but due … Read more

Government response AI summary
The government agrees to ensure the 2022 revaluation of decommissioning liabilities makes explicit allowance for the risk of optimism bias and will report back to the Committee on the new estimates by July 2023.
Read full response →
HM Treasury
12 Conclusion Third Report - The future of the Advanc… Accepted

In 2015, the then Shareholder Executive, on behalf of the Department undertook a review of...

In 2015, the then Shareholder Executive, on behalf of the Department undertook a review of the arrangements with EDFE for decommissioning the AGR stations. It concluded that the existing agreements did not incentivise EDFE to look at more innovative or cost- effective ways to minimise decommissioning costs. Between late 2017 … Read more

Government response AI summary
The government agrees with the Committee’s recommendation and will respond to the Committee by November 2022, outlining the governance and oversight for monitoring the impact of the incentive on delivery and how that indicates effectiveness of the mechanism.
Read full response →
HM Treasury
13 Conclusion Third Report - The future of the Advanc… Accepted

A review commissioned by the Department during the negotiations suggested that the £100 million potential...

A review commissioned by the Department during the negotiations suggested that the £100 million potential fee might not be enough incentive for EDFE to place greater focus on the AGR stations given the potential value of its other UK interests.20 We therefore queried whether the £100 million financial incentive was … Read more

Government response AI summary
The government agrees with the Committee’s recommendation and will respond to the Committee by November 2022, outlining the governance and oversight for monitoring the impact of the incentive on delivery and how that indicates effectiveness of the mechanism.
Read full response →
HM Treasury
14 Recommendation Third Report - The future of the Advanc… Accepted

The Department told us it did have other rights to direct EDFE, for example it...

The Department told us it did have other rights to direct EDFE, for example it has the power to change decommissioning plans. If the Department, for example, identified material cost saving opportunities of more than £5 million it told us it could instruct EDFE to do things in a different … Read more

Government response AI summary
The government refers to its response to recommendation 5, stating it needs to assure itself that the incentives are working and will act accordingly.
Read full response →
HM Treasury
16 Conclusion Third Report - The future of the Advanc… Accepted

We asked why, given the amount of uncertainty surrounding the costs, and concerns about the...

We asked why, given the amount of uncertainty surrounding the costs, and concerns about the adequacy of the Fund to cover this, the risks of decommissioning were being entirely borne by the taxpayer. The Department said that the £100 million agreed with EDFE was a meaningful financial incentive to manage, … Read more

Government response AI summary
The government refers to its response to recommendation 3, stating that the terms of the 2009 sale placed a disproportionate amount of risk on the taxpayer.
Read full response →
HM Treasury
17 Conclusion Third Report - The future of the Advanc… Accepted

The Department emphasised that it was applying significant learning from the experience of decommissioning the...

The Department emphasised that it was applying significant learning from the experience of decommissioning the Magnox and AGR stations. For new nuclear stations a funded decommissioning plan has to be in place before construction begins. The Department told us that it was “building from the start with decommissioning in mind” … Read more

Government response AI summary
The department agrees with the committee’s recommendation and will respond by August 2022 and states that the funded decommissioning plan (FDP) policies in place to support the development of new nuclear stations already build upon what was learnt from the AGR stations. It highlights aspects …
Read full response →
HM Treasury
18 Conclusion Third Report - The future of the Advanc… Accepted

Nuclear power contributed around 16% of the UK’s electricity in 2020.

Nuclear power contributed around 16% of the UK’s electricity in 2020. As at January 2022, five of the seven AGR stations and the Pressurised Water Reactor at Sizewell B are the only nuclear power stations in the UK currently generating electricity; two of the AGRs, Dungeness B and Hunterston B, … Read more

Government response AI summary
The government refers to its response to recommendation 3, stating that the FDP policies in place to support the development of new nuclear stations already build upon what was learnt from the AGR stations.
Read full response →
HM Treasury
21 Recommendation Third Report - The future of the Advanc… Accepted

After the AGR stations are defueled EDFE will transfer the stations to NDA who will...

After the AGR stations are defueled EDFE will transfer the stations to NDA who will be responsible for completing the rest of the decommissioning process. The first 30 Qq 3, 7; C&AG’s Report para 1.2–1.3 31 Qq 3–5 32 Q 7 33 Qq 78–79, 82–83 The future of the Advanced … Read more

Government response AI summary
The government agrees to complete a feasibility study within 12 months and report back to the Committee regarding the future use of nuclear land.
Read full response →
HM Treasury

Oral evidence sessions

1 session
Date Witnesses
7 Feb 2022 David Peattie · Nuclear Decommissioning Authority, Jerry Haller · EDF Energy, Sarah Munby · Department for Business, Energy and Industrial Strategy, Umran Nazir · Department for Business, Energy & Industrial Strategy View ↗

Who gave evidence

4 witnesses
WitnessOrganisationSessions
David Peattie · Group Chief Executive Officer Nuclear Decommissioning Authority 1
Jerry Haller · Nuclear Decommissioning Director EDF Energy 1
Sarah Munby · Permanent Secretary Department for Business, Energy and Industrial Strategy 1
Umran Nazir · Deputy Director for Decommissioning Department for Business, Energy & Industrial Strategy 1

Correspondence

1 letter
DateDirectionTitle
28 Feb 2022 Correspondence from Sarah Munby Permanent Under-Secretary of State, Department …