Future of the Advanced Gas-cooled Reactors
Closed
What the inquiry looked at
“The UK’s nuclear power is generated primarily by seven advanced gas-cooled reactor (AGR) stations, owned by EDF Energy. The AGRs are scheduled to stop generating electricity during this decade, at which point fuel will be removed and transferred to Sellafield for safe storage. The AGRs will then be transferred to the Nuclear Decommissioning Authority. The cost of defueling and decommissioning AGRs will be met from the Nuclear Liabilities Fund, and the government will guarantee any funding shortfall. In June 2021, the Department for Business, Energy & Industrial Strategy announced revised commercial and delivery arrangements for the defueling and decommissioning process. The Committee will question senior officials at BEIS and the Nuclear Decommissioning Authority on : the estimated cost of decommissioning AGRs and the funding available to do so; the revised agreements covering the defueling and decommissioning of AGRs; and progress with planning for defueling and decommissioning the stations, and risks to value for money. If you have evidence on these questions please submit it here by Monday 31 January 2022 18:00.”
The committee's words, from the inquiry page on parliament.uk ↗.
What it found
Despite government already having had to provide additional funding of £10.7 billion, there remains a strong likelihood that more taxpayers’ money will be required to meet the costs of decommissioning the seven Advanced Gas-cooled Reactor nuclear power stations. The Nuclear Liabilities Fund, which was set up to meet the decommissioning costs of these stations, has not kept up with the increased costs of decommissioning or met its investment targets. In response, government has chosen to top up the Fund with taxpayers’ money, providing an injection of capital of £5.1 billion in 2020–21 with a further £5.6 billion expected in 2021–22. HM Treasury and the Department for Business, Energy & Industrial Strategy have opted to maintain an investment strategy for the Fund whereby around 80% of its assets are invested in the National Loans Fund currently earning minimal returns. Estimated decommissioning costs on the other hand have almost doubled since March 2004, estimated at £23.5 billion in March 2021, and there remains a significant risk that the costs could rise further putting strain on the Fund.
The Department has recently reached agreement with EDF Energy (EDFE) that after EDFE defuels the AGR stations the ownership of the stations will be transferred from the company to the Nuclear Decommissioning Authority (NDA) to complete decommissioning. As part of the agreement the Department has introduced financial incentives to encourage cost-efficient defueling and station transfer: with EDFE potentially earning or paying out up to £100 million depending on its performance.
The pace at which the stations can be defueled could have a big impact on the costs borne by the Fund, with the cost estimated to be between £3.1 billion and £8.0 billion depending on the time taken. However, the incentive on EDFE to potentially earn or lose £100 million does not appear sufficiently strong to fully incentivise cost efficiency and ensure a smooth transfer of defueled stations to the NDA. The NDA has a substantial amount of work to do in advance of taking ownership of the stations. We have previously commented on the scale of existing activities the NDA is undertaking, and are concerned about the organisation’s workload now that it is being asked to take on the seven AGR stations in addition to the decommissioning of the Magnox reactors, the treatment of radioactive material at Sellafield and the procurement of a deep underground nuclear storage facility. The Department will need to pay close attention to the NDA’s performance across the full span of its wide responsibilities to ensure it has the capacity and capability in place to deliver in the best interests of the taxpayer.
What the government said
The government responded on 2 September 2022. The deadline was 20 July 2022.
The government states that it agrees with most of the Committee's recommendations and sets target dates for responses, but disagrees with the recommendation on reviewing life extensions of the operating stations 'as currently drafted'.
- On the Nuclear Liabilities Fund's investment strategy, the government "agrees"; the Department and HM Treasury will work with the Fund on a review and write to the Committee "by May 2023".
- On life extensions, the government disagrees as drafted because the decision rests with EDF and the Office for Nuclear Regulation. It says it "will ask EDF" to set out its plans and "will aim to provide further detail" to the Committee "by the end of 2022".
- On the transfer of stations to the NDA, the government agrees. It says a "sufficiently detailed transfer plan for Hunterston B will be available in May 2023", with plans for later stations "completed in the years thereafter".
- On the incentives for EDFE and the NDA, the government "accepts" the recommendation and will respond by November 2022, outlining governance and oversight for monitoring the impact of the incentive.
Read the government's response ↗ Read the report ↗ Report an error
How the inquiry ran
Each dot is a dated item listed on this page, from the inquiry's opening on 12 January 2022 to its close on 2 September 2022. The dashed mark is the deadline Parliament records for the government's response.
- Oral evidence 7 Feb 2022
- Report 20 May 2022
- Government response 2 Sep 2022
- Correspondence 28 Feb 2022
What it recommended 10 recommendations · 21 conclusions
2The estimated cost of decommissioning has nearly doubled since 2004–05 and there remains a significant...
3The terms of the 2009 sale of the nuclear stations agreed by the Department with...
4EDFE’s timetable for the closure of the stations will result in a significant reduction in...
5We are not convinced the Department has struck the right balance in incentivising the NDA...
6Arrangements for transferring nuclear stations to NDA are worryingly under- developed, and there is a...
7Given the scale and complexity of decommissioning the AGR stations, we are concerned that the...
1On the basis of a report by the Comptroller and Auditor General, we took evidence...
8The Committee has previously identified significant uncertainty regarding the estimation of decommissioning costs.
9The estimated cost of decommissioning the AGR stations, plus the PWR at Sizewell B, increased...
10There remain significant uncertainties which if managed poorly could increase decommissioning costs further.
11EDFE has recently brought forward the closure date for five out of the seven AGR...
12In 2015, the then Shareholder Executive, on behalf of the Department undertook a review of...
13A review commissioned by the Department during the negotiations suggested that the £100 million potential...
14The Department told us it did have other rights to direct EDFE, for example it...
15The assets of the Fund have been created from the contributions made by the station...
16We asked why, given the amount of uncertainty surrounding the costs, and concerns about the...
17The Department emphasised that it was applying significant learning from the experience of decommissioning the...
18Nuclear power contributed around 16% of the UK’s electricity in 2020.
19The Department acknowledged there will be a production gap between existing nuclear stations closing and...
20We asked whether there could be value in reusing the AGR sites, given the existing...
21After the AGR stations are defueled EDFE will transfer the stations to NDA who will...
22There are still some important aspects of transfer that are yet to be agreed.
23The Department’s business case estimates that the transfer of the stations will cost £300 million,...
24We were concerned by the number of issues still to be resolved in the time...
25We wrote to the Department and HM Treasury number of times (see Annex 1) after...
26The long-term benefits of transferring the AGR stations into public ownership will depend on the...
27Delivering the benefits intended from the new arrangements will require a clear long- term delivery...
28The AGR decommissioning programme is complex, and key organisations already have substantial portfolios of work.
29The Department told us that following its experience of the Magnox contract, it had undertaken...
30Decommissioning the AGR stations is an unusual programme compared with others in government as no...
31Given the centrality of its role we asked the Department whether its own role was...
Evidence
Oral evidence sessions 1
- 7 Feb 2022Future of the Advanced Gas-cooled Reactors4 witnesses, listed belowparliament.uk ↗
Who gave evidence 4 witnesses
- David PeattieGroup Chief Executive Officer, Nuclear Decommissioning Authority
- Jerry HallerNuclear Decommissioning Director, EDF Energy
- Sarah MunbyPermanent Secretary, Department for Business, Energy and Industrial Strategy
- Umran NazirDeputy Director for Decommissioning, Department for Business, Energy & Industrial Strategy