Source · Select Committees · Welsh Affairs Committee

First Report - Railway Infrastructure in Wales

Welsh Affairs Committee HC 438 Published 14 July 2021
Report Status
Government responded
Conclusions & Recommendations
19 items (14 recs)
Government Response
AI assessment · 19 of 19 classified
Accepted 8
Accepted in Part 5
Acknowledged 1
Deferred 1
Not Addressed 1
Rejected 3
Government response
First Special Report - Railway infrastructure in Wales: Government response to the Committee’s First Report of Session 2021–22 · published 22 Sep 2021
Read the government response ↗ Response on the Index
Filter by: Clear

Recommendations & Conclusions

1 item
9 Recommendation Not Addressed
Para 75

While we welcome the positive working relationship between the Welsh and UK governments on rail...

Recommendation
While we welcome the positive working relationship between the Welsh and UK governments on rail infrastructure projects, we are concerned that the UK Government’s Rail Network Enhancements Pipeline (RNEP) is too slow and hampers, rather than helps, the evaluation of … Read more
Government Response Summary
The government's response, identical to the previous one, details plans to establish new governance boards to develop and deliver rail enhancements, but does not explicitly set out plans to reform the RNEP process itself.