Source · Select Committees · Science, Innovation and Technology Committee

Eighth Report - Delivering nuclear power

Science, Innovation and Technology Committee HC 626 Published 31 July 2023
Report Status
Government responded
Conclusions & Recommendations
63 items (25 recs)
Government Response
AI assessment · 63 of 63 classified
Accepted 42
Acknowledged 13
Deferred 6
Not Addressed 1
Rejected 1
Filter by: Clear

Recommendations

1 result
41 Rejected
Para 219

Publish detailed financial figures on construction risk and cost to taxpayers for new gigawatt nuclear.

Recommendation
So far, the Government has not published financial figures which allow the cost of this risk transfer to be known. The Government must publish figures, before signing contracts for new gigawatt-scale nuclear, which allow a proper assessment of value for … Read more
Government Response Summary
The government stated that while capital costs are under scrutiny, publishing sensitive financial information, including construction risk costs, prior to a final investment decision (FID) could undermine negotiations. It reaffirmed its commitment to publish a value for money assessment before taking an FID for Sizewell C, having already published one at the designation stage.
Department for Science, Innovation and Technology
View Details →