Select Committee · Science and Technology Committee (Commons)

Delivering nuclear power

Status: Closed Opened: 19 Jul 2022 Closed: 28 May 2024 25 recommendations 38 conclusions 1 report
Inquiry scopeDue to rising fuel prices, securing the UK’s energy supply is currently a top priority for the Government and is of great interest to the public. The Government’s Energy Security Strategy , published in April 2022, emphasised that nuclear power would play a key part in supplying the UK with baseload electricity, however there is currently great uncertainty about how quickly new nuclear power plants can be built, when fusion technologies might be available and what the costs of these large infrastructure projects will be. The Committee will examine the Government’s approach to developing new nuclear power.

Reports

1 report

Recommendations & Conclusions

63 items
1 Conclusion Eighth Report - Delivering nuclear power

Life extensions for EDF reactors reasonable if deemed safely operational by regulator

Conclusion · source text

We conclude that it is reasonable for EDF to seek life extensions to extend their contribution to the grid if, and only if, the Office for Nuclear Regulation’s judgement is that they can be safely operational as is currently the case.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
3 Conclusion Eighth Report - Delivering nuclear power

Publish detailed nuclear project pipeline to enable timely investments in new generation capacity

Conclusion · source text

Gigawatt-scale nuclear power stations use a known and well understood technology that can deliver dependable low carbon baseload electricity to the grid. Nuclear power is therefore an important option and could be used to produce a domestic supply of baseload power to the UK as part of the low carbon energy mix required to achieve the Government’s goals of increasing energy security and achieving net zero by 2050. However, the question of energy security must engage with the questions of sourcing of fuel and the risks of having a concentration of generating capacity in very large plants, which could be susceptible to outages as a result of technical problems or as a target for malign actors. The Government’s aim to bring up to 24 gigawatts of nuclear-powered electricity to the grid by 2050 is commensurate with its net zero ambitions but currently lacks a comprehensive plan to achieve it. We welcome the Government’s intention of “building a project pipeline” of nuclear projects but agree with industry that the details of this pipeline must be published by Government, if investments in new nuclear are to proceed in time.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
4 Recommendation Eighth Report - Delivering nuclear power

Publish clear Nuclear Strategic Plan with detailed figures and interim targets for project pipeline

Recommendation · source text

Setting a notably stretching target requires a credible pathway towards its delivery. The Government should publish a clear delivery plan, a Nuclear Strategic Plan, for its nuclear project pipeline, backed up by detailed figures of projected energy production from nuclear for the years leading up to 2050, and be developed in collaboration with and engaging the confidence of the whole sector. This Nuclear Strategic Plan should include interim targets for nuclear energy production in 2035, 2040 and 2045.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
6 Recommendation Eighth Report - Delivering nuclear power

Publish Simon Bowen's report on Great British Nuclear's purpose with Government response

Recommendation · source text

The Government should publish the report and recommendations submitted by Simon Bowen, industrial adviser to Great British Nuclear, and his team on the purpose of Great British Nuclear, alongside the Government response to this report.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
7 Conclusion Eighth Report - Delivering nuclear power

Great British Nuclear's remit and activities remain unclear beyond the SMR competition.

Conclusion · source text

The 2050 target for nuclear of 24 GW needs a plan to achieve it, which must include clarity on the bodies and institutions that will deliver it. After asking the Department to provide more clarity on what legislation will be required to ensure that Great British Nuclear can operate as intended, we are pleased to see that the Government has tabled amendments to the Energy Bill 2022–23 to include this legislation. Having said this, there are still some points of ambiguity over exactly how Great 100 Delivering nuclear power British Nuclear will function and what activities it will carry out beyond running a small modular reactor competition. We expected further clarity to given in the Government’s launch of GBN in July 2023, but the announcement only included details of the SMR competition and the allocation of funds that had already been announced.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
8 Recommendation Eighth Report - Delivering nuclear power

Publish secondary legislation clarifying Great British Nuclear's remit, funding model, and role in future projects.

Recommendation · source text

In response to this Report, the Government should set out additional detail on how Government will intersect with Great British Nuclear, including details of Great British Nuclear’s exact remit and funding model, and the formal split of responsibilities with the Department for Energy Security and Net Zero. To aid this, the Government should publish the required secondary legislation that will support the creation of Great British Nuclear. Within this detail, the Government should clearly define what the role for Great British Nuclear will be on supporting new nuclear projects beyond the initial small modular reactors competition, including in relation to gigawatt size projects beyond Sizewell C and deployment of advanced modular reactors when technologically ready.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
9 Conclusion Eighth Report - Delivering nuclear power

SMR Final Investment Decision timeline risks delaying new reactors beyond early 2030s.

Conclusion · source text

In its July 2023 announcement on Great British Nuclear, the Government said that it would use the small modular reactor technology selection process (SMR TSP) to identify those reactor companies best able to reach a project Final Investment Decision (FID) by the end of 2029. The FID would include funding to support site access and site-specific design. Therefore, some of the more time-consuming aspects of building new nuclear projects, namely site-specific regulation and relevant licencing, would not begin for any successful SMR design until after 2029. This new timeline would go beyond the dates that many of the SMR developers have proposed is possible for SMR reactors to supply energy to the grid, namely the early 2030s.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
10 Recommendation Eighth Report - Delivering nuclear power

Advance SMR Final Investment Decisions before 2029 and provide detailed electricity supply timeline.

Recommendation · source text

The Government should take steps to advance the ability for FIDs to be taken before 2029 and provide a detailed timeline of when it expects the winner or winners of GBN’s SMR technology selection process to begin commercially supplying electricity to the UK.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
11 Conclusion Eighth Report - Delivering nuclear power

Diverse operators of small and advanced nuclear technologies offer future market benefits.

Conclusion · source text

Gigawatt-scale nuclear power plants require UK experience—of the supply chain, regulatory processes and the wider energy sector—to deliver projects efficiently. However, the UK may benefit in the future from multiple operators of small and advanced, nuclear power technologies as they have the potential to provide market competition, collaboration opportunities and prevent a groupthink mentality.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
12 Recommendation Eighth Report - Delivering nuclear power

Provide sufficient resources to nuclear regulators to support new SMR and AMR operators.

Recommendation · source text

The Government should provide sufficient resources to nuclear regulators, to support potential new operators of small and advanced modular reactor technologies to enter the UK energy market. (Paragraph 64) Delivering nuclear power 101

Link to this item · Read item and full response

Department for Science, Innovation and Technology
13 Recommendation Eighth Report - Delivering nuclear power

Provide clarity on achieving the 24 GW aim, including reactor mix and project timeline.

Recommendation · source text

The Government should provide clarity on how it plans to achieve its 24 gigawatt aim, and the expected timeline for these. This should include details of: a) the target mix of reactor technologies, including the desired number of future gigawatt scale reactors, that the Government will support; and b) a detailed timeline for when new projects are expected to be completed.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
14 Conclusion Eighth Report - Delivering nuclear power

Standardised nuclear fleets offer potential cost benefits with mitigated operational risks.

Conclusion · source text

An essential requirement will be to resolve of the questions of whether a standardised fleet of nuclear power plants, using serial versions of the same reactor technology, has the potential to benefit the UK as new knowledge and resources can be transferred from one project to the next, reducing the risk of construction and cost overruns. The inevitable objection that such a strategy embeds the risk that operational issues identified with one power plant could affect the entire fleet can be mitigated be using tried and tested underlying technologies and engineering and careful sequencing of any innovation.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
15 Conclusion Eighth Report - Delivering nuclear power

Choose between standardised nuclear fleets for cost or diverse reactor designs for security.

Conclusion · source text

The Government, through Great British Nuclear, must choose between the potential cost benefits of a standardised nuclear fleet of gigawatt reactors and the energy security and resilience that a diversity of reactor designs provides.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
16 Conclusion Eighth Report - Delivering nuclear power

UK nuclear fuel sector leads globally, with potential for increased enrichment and exports.

Conclusion · source text

The UK is an international market leader in the manufacture of nuclear fuels and is uniquely positioned with the capability of delivering the entire nuclear fuel cycle. The nuclear fuel sector in the UK has the potential to increase enrichment capacity, which can provide security for domestic nuclear fuel supply chain and further export opportunities.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
17 Recommendation Eighth Report - Delivering nuclear power

Publish a detailed Nuclear Strategic Plan to expand nuclear fuel manufacturing capacity and secure supply.

Recommendation · source text

By publishing a detailed Nuclear Strategic Plan, as we recommend, which includes the types and number of reactors to be built in the UK, the Government should provide a signal to the nuclear fuel industry to step up and increased its end-to-end fuel manufacturing capacity. The Government should set out in the Nuclear Strategic Plan how it will capitalise on the strengths of the UK’s nuclear fuel supply chain to secure a resilient supply of nuclear fuel for any new planned reactors and develop further export opportunities. (Paragraph 90) Advanced nuclear technologies

Link to this item · Read item and full response

Department for Science, Innovation and Technology
18 Conclusion Eighth Report - Delivering nuclear power

Government policy on Small Modular Reactors (SMRs) remains at a critical crossroads.

Conclusion · source text

The Government is at a cross-roads in its policy on small modular reactors (SMRs). So far it has funded a consortium led by Rolls-Royce with over £210 million of research and development funds to develop a concept SMR design, and now, to further develop the design to the extent that it can pass the generic design assessment process. That public funding was matched with £280 million from the private sector. It has subsequently announced that Great British Nuclear will launch and administer a competition in which other vendors’ technology would be assessed. What is then required is a set of pivotal decision on the actual deployment of, rather than research into, SMRs.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
19 Conclusion Eighth Report - Delivering nuclear power

Deferring nuclear strategic decisions risks wasted investment and increased costs.

Conclusion · source text

It is not uncommon, in the face of an unclear strategy or unresolved internal arguments about financing, for governments to defer decisions rather than take them. But this would be the wrong course. The UK risks losing the advantage of 102 Delivering nuclear power the public investment that has already been made; as well as contributing to the ambiguity in our future energy supply; and perpetuating a level of policy risk that is likely to drive a risk premium on costs, to the detriment of the taxpayer and billpayer.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
20 Recommendation Eighth Report - Delivering nuclear power

Answer key questions on SMR deployment, technology, sites, and financial models in the Nuclear Plan.

Recommendation · source text

In developing a Nuclear Strategic Plan the Government should answer the questions of: • what deployment of SMRs it wants to see, if any; • what technologies and vendors it intends to deploy, and whether they will be from a single supplier or multiple suppliers; • what sites should SMRs be located at; and • what financial model would be used to support the contribution of SMRs to electricity supply?

Link to this item · Read item and full response

Department for Science, Innovation and Technology
21 Conclusion Eighth Report - Delivering nuclear power

UK possesses a strong and valuable capability in nuclear research and development.

Conclusion · source text

From the commissioning of Calder Hall in the 1950s, the UK has always had a strong capability in nuclear research and development. At a time where there is a global commitment to reduce carbon emissions and to reduce dependence on fossil fuels for reasons of energy security, the UK’s capability in new nuclear technologies is a strength.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
22 Conclusion Eighth Report - Delivering nuclear power

Regulatory environment and incentives crucial for private investment in Advanced Modular Reactors (AMRs).

Conclusion · source text

Whilst investment by Government in early stage and demonstrator reactors will drive forward innovation for advanced modular reactors (AMRs), bringing them closer to commercialisation, what is also important is the UK having a regulatory environment and incentives for private investment. This has been demonstrated to work in the UK’s fusion sector, where as well as strong Government funded demonstrator programme, the regulatory system, skills environment and developing supply chain, is attracting private companies and private investment to the UK.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
23 Conclusion Eighth Report - Delivering nuclear power

Government funding decisions on Advanced Modular Reactor (AMR) technologies are critical for progress.

Conclusion · source text

AMRs may offer new advantages in terms of cost and the potential for co-generation. But if they are to advance the research and development needs to move from the desk and the lab towards demonstrators, and this will require the Government to make decisions as to which technologies to fund.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
24 Recommendation Eighth Report - Delivering nuclear power

Continue support for AMR R&D programme and make timely funding decisions to keep pace.

Recommendation · source text

The Government should continue its support for the Advanced Modular Reactor Research, Development and Demonstration programme and ensure that it takes decisions on funding particular technologies and projects without delay, so that it keeps pace with competitors.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
25 Conclusion Eighth Report - Delivering nuclear power

UK is a global leader in nuclear fuel with potential to replace Russia's supply.

Conclusion · source text

The UK is a leading global player in uranium enrichment and nuclear fuel fabrication and has the potential to replace Russia’s contribution to the global supply chain of advanced fuels. We welcome the launch and allocation of funding from the Nuclear Fuel Fund to support the development of the capabilities needed to meet current and future nuclear fuel demands. (Paragraph 128) Delivering nuclear power 103 Fusion

Link to this item · Read item and full response

Department for Science, Innovation and Technology
26 Conclusion Eighth Report - Delivering nuclear power

UKAEA's work created a thriving fusion R&D cluster, attracting global private investment.

Conclusion · source text

The work of the UK Atomic Energy Authority has resulted in a thriving research and development fusion cluster at the Culham Science Centre in Oxfordshire. As well as operating the world’s leading torus and spherical fusion reactors, the Culham facility benefits from being part of a consortium of 30 fusion research organisations and universities from 25 European countries and has attracted private companies from around the world, many of which plan to build demonstrator reactors at Culham.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
27 Conclusion Eighth Report - Delivering nuclear power

Fusion research unlikely to meet net-zero targets by 2050 given current challenges.

Conclusion · source text

Since 2010, the UK public investment into fusion research and development has totalled around £970 million. All such investment of taxpayer funds has alternative uses, whether in science, energy, or other fields. Sceptics of fusion argue, in the much-repeated phrase, that the benefits of fusion are always 20 years away—with the implication that such funds could be better spent elsewhere. It is true that fusion is highly unlikely to make a material contribution to electricity generation by 2050, in the time to contribute to our net zero commitment being met. It is also true that there are many risks, uncertainties, and dependencies—such as the development of materials—that mean that fusion may not in the foreseeable timeframe realise it tantalising potential.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
28 Conclusion Eighth Report - Delivering nuclear power

Recent breakthroughs and UK leadership indicate growing optimism for fusion research.

Conclusion · source text

However, in recent months breakthroughs have been made in fusion research, including doubling of the record for power generated in a tokamak; there is a growing number of private fusion companies clustered in Culham and the UK is a leading nation in the ITER project.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
29 Conclusion Eighth Report - Delivering nuclear power

Long-standing commitment to fusion essential due to recent optimism and strategic benefits.

Conclusion · source text

We believe that it is not the time to abandon our long-standing commitment to fusion, just at the point when it is giving cause for optimism; when the zero- carbon imperative is strong; when we have an internationally admired and well- run organisation in the UK Atomic Energy Authority, and when positive spill-over effects are being felt from the research.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
30 Recommendation Eighth Report - Delivering nuclear power

Integrate fusion research and development into the Government's long-term energy plan.

Recommendation · source text

To maximise the benefits that we gain from investment in fusion requires a long-term approach to give confidence and stability to investors and international partners and so we recommend that fusion is a part of the Government’s long-term energy plan. (Paragraph 146) Nuclear skills gap

Link to this item · Read item and full response

Department for Science, Innovation and Technology
31 Conclusion Eighth Report - Delivering nuclear power

Nuclear sector perceived as unattractive for STEM career specialists in recent decades.

Conclusion · source text

It is not surprising that the nuclear sector has not been the industry of choice for many STEM specialists embarking on a career. At a time when no new nuclear plants had been approved for decades, this was a sector thought by some not to be one with a bright future in which to contemplate a lifetime career specialisation.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
32 Conclusion Eighth Report - Delivering nuclear power

Stable, long-term nuclear growth plan could significantly boost STEM recruitment.

Conclusion · source text

However, if the Government and the nuclear industry credibly adopt a stable, long term plan of growing the nuclear sector, there are very significant attractions to recruitment: new build and new technologies involve innovation and technical 104 Delivering nuclear power advances; the timescales of nuclear commitments offers the prospect of enduring careers; the global revival of nuclear power offers international opportunities; and financial rewards are likely to remain high.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
33 Recommendation Eighth Report - Delivering nuclear power

Promote advantages of nuclear industry careers to school-leavers, graduates and career changers.

Recommendation · source text

As part of a strategic approach to nuclear, the Government and the industry should set out steps deliberately to communicate to school-leavers, graduates and to those changing careers, the particular advantages of choosing to work in the nuclear industry.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
34 Conclusion Eighth Report - Delivering nuclear power

Broadening nuclear sector employment to other industries prevents insularity and groupthink.

Conclusion · source text

It is highly desirable that, in expanding employment in the sector, opportunities should continue to be broadened to people from sectors other than nuclear. Apart from the wider pool of talent available, it is important there should be flows into and out of the nuclear industry from other industries. The risk for any industry that is too insulated from others is that it can be insular and impervious to different ways of thinking that are practiced in other industries. At a time of such rapid technological change and innovation, it is important that the nuclear industry participates in this movement, and avoids the degrees of groupthink in which a relatively small number of people move between a relatively small number of organisations within the same sector.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
36 Conclusion Eighth Report - Delivering nuclear power

Develop clear protocol for funding employer-specific nuclear curriculum and teaching materials.

Conclusion · source text

We were impressed by the obviously effective working relationship between the National College for Nuclear and the Hinkley Point C Project. In this case, the training provided, and the apprenticeships offered, are clearly tied to a specific employer and site. We were concerned that there was a lack of clarity on who should fund the development of the curriculum and teaching materials for courses mounted exclusively to serve the needs of a particular employer. The Government and the Nuclear Skills Strategic Groups should develop a clear protocol on this. Should further nuclear new build proceed, with multiple organisations in the developer and in the supply chain requiring apprenticeships, there must be no delay in developing courses arising from ambiguity on who pays for that development.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
37 Recommendation Eighth Report - Delivering nuclear power

Apply consistent pay flexibilities across public sector research bodies, maintaining financial discipline through budgets.

Recommendation · source text

In line with Sir Paul Nurse’s recommendations for greater flexibility on pay with conditions for Public Sector Research Establishments, we recommend that a consistent set of pay flexibilities should be applied to public bodies in the sector with financial discipline applied through the overall budgets for bodies. (Paragraph 185) Financing

Link to this item · Read item and full response

Department for Science, Innovation and Technology
38 Conclusion Eighth Report - Delivering nuclear power

Gigawatt-scale nuclear projects face formidable financing challenges, cost overruns, and construction delays.

Conclusion · source text

Gigawatt-scale nuclear projects cost tens of billions of pounds to plan and construct before a single unit of electricity is generated. Their long period of construction, complexity, and subordination to potentially variable regulatory standards have been associated with large cost-over runs and delays. For all of these reasons, and more, the financing of gigawatt-scale new nuclear power has proved formidably challenging. Most civil nuclear nations have built new nuclear power stations on the public sector balance sheet, as did the UK for all of its existing nuclear power stations. Hinkley Point C has been financed off the Government balance sheet by Delivering nuclear power 105 the French Government-owned utility EDF and Chinese CGN. Its construction is proceeding in return for a 35 year Contract for Difference (CfD) fixed at £92.50/ MWh in 2012 prices. The conceived cost of construction has increased from £18 billion at the time of the final investment decision to £32 Billion in 2023 and its completion date is now forecast to be 2027, around two years after EDF’s estimate at the time of Final Investment Decision (FID). It is important to note that the estimates of that cost overrun as result of the CfD model are not to be met by UK consumer or taxpayer, but by the companies. The CfD runs for 35 years from start- up during the 2025–2029 period. If the plant is not generating electricity by 2029 then the contract would be shortened by one year up until 2033 after which the contract will be cancelled and EDF will not receive any top-up revenues from the CfD.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
39 Conclusion Eighth Report - Delivering nuclear power

Public-private risk sharing for gigawatt nuclear transfers significant cost overrun risks to taxpayers.

Conclusion · source text

Given the demonstrated unwillingness of private investors to take on all of the construction risk of gigawatt scale nuclear plants through the CfD model, it is inevitable that a public-private risk sharing model should be contemplated if new gigawatt-scale plants are to be constructed. The Regulated Asset Base (RAB) model— which has been given Royal Assent in the Nuclear Energy (Financing) Act is one such. However, the model entails significant uncertainties and downsides. Chief among these is that although the financing of a plant should be cheaper in headline terms than a model in which the private sector shoulders all construction risk, the extent to which this represents value for money depends on the financial value of the construction risk being absorbed by the public balance sheet. The consumer or taxpayer is taking an unknown and uncertain risk of cost overruns, yet disburses funds from day one without earning a return.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
40 Recommendation Eighth Report - Delivering nuclear power

Demonstrate value for money to taxpayers for gigawatt nuclear, including full construction risk estimates.

Recommendation · source text

The Government should show how this offers value for money to taxpayers and should be open to other alternative partnerships between the public and private sectors as practised in other countries (including those set out in Table 2). The choice to proceed with gigawatt-scale nuclear power should not be made without robust estimates of its value for money, including the financial value of the construction risk being assumed by taxpayers or billpayers. A headline lower cost than Hinkley Point C is not justified if the value of the risk is too great. This is true even if it forces a conclusion that—for all its other advantages—gigawatt scale new nuclear is not financeable on defensible terms, and that the UK’s nuclear ambition would need to be pursued through other nuclear technologies.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
41 Recommendation Eighth Report - Delivering nuclear power

Publish detailed financial figures on construction risk and cost to taxpayers for new gigawatt nuclear.

Recommendation · source text

So far, the Government has not published financial figures which allow the cost of this risk transfer to be known. The Government must publish figures, before signing contracts for new gigawatt-scale nuclear, which allow a proper assessment of value for money to be made, including setting out the level and potential cost of construction risk to be borne by the consumer or taxpayer.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
42 Recommendation Eighth Report - Delivering nuclear power

Disclose best estimate of public risk value and management plan for gigawatt nuclear projects.

Recommendation · source text

It may be the case that the size of capital outlay means that private investors will not repeat a CfD contract for new nuclear, whatever the price. But the lack of alternative choices should not mean that any terms will be acceptable for a RAB financed plant. The Government should make, and disclose, its best estimate of the value of the risk that would be taken on by the public, and a clear plan of how those risks can be managed through incentives during the development, construction and operational phase of the project’s lifetime. (Paragraph 220) 106 Delivering nuclear power

Link to this item · Read item and full response

Department for Science, Innovation and Technology
43 Recommendation Eighth Report - Delivering nuclear power

Publish Sizewell C RAB model savings calculations and Heads of Terms for funding structure clarity.

Recommendation · source text

The Government should publish details of how the estimated savings from using the RAB model for funding Sizewell C were calculated, and provide clarity for the funding structure, by publishing the Heads of Terms for the agreed RAB funding model for that project.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
44 Conclusion Eighth Report - Delivering nuclear power

Clarity needed on SMR deployment plans and suitable financing models given CfD limitations.

Conclusion · source text

This is an important moment for the future of small modular reactors (SMRs) as we set out in Chapter 3. Following the £500 million Government and investor funded development of an SMR concept through to the beginning stages of regulatory approval. Clarity is needed on the Government’s plans to deploy the technology if it completes the generic design assessment. This includes deciding on what financing model will be made available should the policy be to deploy SMRs in supplying power to the grid. The Contracts for Difference (CfD) model has proved successful in financing and driving down the costs of clean energy. Key to the success of CfDs for renewables to date has been competition between potential operators which has driven down the price paid for electricity generation.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
45 Recommendation Eighth Report - Delivering nuclear power

Communicate a clear financial model for initial SMR deployment, as CfD is unsuitable.

Recommendation · source text

If a single supplier of SMRs were to be available, either through Government choice or following the Generic Design Assessment process, the CfD auction model will not be suitable. As part of a clear and specific strategy for SMRs, the Government should come to a view quickly on what financial model would be available for the initial deployment and communicate this clearly to developers.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
46 Conclusion Eighth Report - Delivering nuclear power

Inclusion of nuclear in UK Green Taxonomy welcomed for low-carbon contribution and investor appeal.

Conclusion · source text

We welcome the proposed inclusion of nuclear energy generation in the UK Green Taxonomy as it reflects the low-carbon contribution of nuclear power and may make new building projects more attractive to private investors as with other low-carbon energy generators.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
47 Recommendation Eighth Report - Delivering nuclear power

Conduct and publish consultation results quickly, reviewing nuclear energy's Green Financing access

Recommendation · source text

The Government should conduct and publish the results of its consultation quickly, and during this time review nuclear energy’s access to the Green Financing Framework with a view to ensuring consistency and addressing the contradiction between the two. (Paragraph 235) Regulation and location

Link to this item · Read item and full response

Department for Science, Innovation and Technology
48 Conclusion Eighth Report - Delivering nuclear power

ONR's Generic Design Assessment approach is internationally well-regarded and adaptable for new reactors

Conclusion · source text

The Office for Nuclear Regulation (ONR) Generic Design Assessment’s (GDA) goal- based approach is well regarded internationally and is intended to be adaptable for any new technology. We welcome the work that the ONR has done to modify the GDA to allow more flexibility for new reactor designs that seek to enter the UK market.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
49 Conclusion Eighth Report - Delivering nuclear power

Generic Design Assessment process faces capacity constraints, expense, and international overlap concerns

Conclusion · source text

Some witnesses are concerned that the GDA has capacity constraints and is a lengthy and expensive process given that there are no site-specific guarantees afterwards. Whilst acknowledging the need for UK sovereignty over regulations, witnesses pointed out the considerable overlap of the technical approval process for new reactors between established nuclear nations.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
50 Recommendation Eighth Report - Delivering nuclear power

Reduce GDA application timelines through international collaboration and recognise partner country safety approvals

Recommendation · source text

The Government should consider how it could reduce the GDA application timelines and the required resources through international collaborations between regulators, and should provide access to pre-engagement for new nuclear developers prior to Delivering nuclear power 107 entering the GDA. The ONR should examine ways to recognize, in whole or part, safety approvals for mature reactor designs granted by partner countries with similarly high standards to capitalise on work previously done.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
51 Recommendation Eighth Report - Delivering nuclear power

Ensure nuclear regulators possess sufficient resources to process increasing applications promptly

Recommendation · source text

The Government should ensure as part of a specific and detailed nuclear strategy that the ONR, the Environment Agency and Natural Resources Wales have the necessary resources to process applications from the growing range and number of applicants in a reasonable timeframe.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
52 Conclusion Eighth Report - Delivering nuclear power

Reflect on GDA lessons for SMR efficiency and safety cases following first completion

Conclusion · source text

Whilst the ONR has recently adapted the GDA to be more suitable for small modular reactor (SMR) technologies, to date no SMR design has completed the entire three step process. The ONR should reflect, both during and after the first SMR has completed the GDA, on the lessons to be learned on efficiency and applying appropriate safety cases for these smaller technologies, from other similar bodies, such as the Environment Agency and Health and Safety Executive that regulate Fusion energy facilities.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
53 Conclusion Eighth Report - Delivering nuclear power

Nuclear regulation efficiency can improve by running GDA and site licensing in parallel

Conclusion · source text

Although the reputation and integrity of UK nuclear regulation must be maintained, there are opportunities to improve the efficiencies of nuclear regulation by running processes such as the Generic Design Assessment (GDA), and site licencing, in parallel.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
54 Recommendation Eighth Report - Delivering nuclear power

Streamline planning and environmental requirements, running DCOs and GDA in parallel where possible

Recommendation · source text

The Government should work with regulators, devolved administrations, local authorities, industry leaders, and others to streamline planning and environmental requirements wherever possible. The Office for Nuclear Regulation should look for opportunities to run the Development Consent Orders and the GDA in parallel for experienced vendors who have already successfully completed the GDA with other reactor designs or who have reactor technology that has been approved by other regulators.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
55 Conclusion Eighth Report - Delivering nuclear power

Concerns exist regarding creeping delays in updating the Nuclear National Policy Statement

Conclusion · source text

Given that the Minister envisaged a three-year timeline to develop, consult upon, and designate a new nuclear National Policy Statement (NPS), and that as of 18 July 2023 the consultation stage had not even started, we are concerned that there may be a creeping delay in updating the NPS for new nuclear. This would not only send the wrong signal to a sector poised for investment but could cause delays in deployment. New nuclear developers require knowledge of where a reactor can be built if they are to advance their plans.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
56 Recommendation Eighth Report - Delivering nuclear power

Progress new nuclear NPS EN-7 consultation, meet deadline, and identify all reactor sites

Recommendation · source text

The Government should progress the consultation on the new NPS EN-7 for nuclear power and should meet its previously stated deadline of early 2025, and ideally publish the new NPS earlier than the deadline. Any update should identify where reactors smaller than 1 GW can be sited, as well as sites for larger reactors. (Paragraph 267) Nuclear decommissioning and waste

Link to this item · Read item and full response

Department for Science, Innovation and Technology
57 Conclusion Eighth Report - Delivering nuclear power

Require Government and Parliament to maintain close review of NDA performance and relationships.

Conclusion · source text

Decades of mismanagement of nuclear decommissioning in the UK—from inadequate provision for decommissioning costs, to record keeping so negligent as to have left ponds of radioactive waste whose content in unknown—has made the responsibilities of the Nuclear Decommissioning Authority (NDA) some of the most challenging, complex and consequential of any organisation in Britain today. The 108 Delivering nuclear power NDA has made progress in the last five years in simplifying its structure, making more credible estimates of the costs of decommissioning, and replacing complex and opaque subcontractor arrangements with more straightforward ones. The vast annual budget for the NDA—necessarily between £3.5 billion and £4 billion—and the critical importance of its work means that the performance of the NDA must be kept under close review by the Government and Parliament, and that it should have a strong relationship with the Department for Energy Security and Net Zero, the Treasury and the Prime Minister’s office.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
58 Conclusion Eighth Report - Delivering nuclear power

UK's Nuclear Decommissioning Authority possesses world-leading expertise with significant global export potential.

Conclusion · source text

The experience and expertise which the NDA has in civil nuclear decommissioning is more than any other country in the world, as a result of the head start the UK has had in being the world’s first civil nuclear nation. As countries who were later in constructing civil nuclear power stations have to turn to safely and economically decommission them, the NDA’s expertise can be deployed globally. This is a tremendous export opportunity for the UK expertise which can raise revenue.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
60 Conclusion Eighth Report - Delivering nuclear power

Existing nuclear waste constitutes majority; SMR and AMR waste may require distinct handling.

Conclusion · source text

Most of the nuclear waste that the UK must safely handle and dispose of has already been produced by previous nuclear installations. The incremental waste generated by new nuclear power plants is not likely to be a material factor in decisions on approving new gigawatt-scale plants. We note, however, evidence presented to us that indicated that small modular reactors and advanced modular reactors would produce waste which may require different handling.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
61 Conclusion Eighth Report - Delivering nuclear power

Require clear understanding of waste consequences, handling, and cost for new nuclear technology approval.

Conclusion · source text

It is imperative that a clear understanding of the waste consequences of new nuclear technologies, how it will be dealt with and at what cost, should be part of the decision- making on approving the case of these technologies.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
62 Conclusion Eighth Report - Delivering nuclear power

Establishment of a Geological Disposal Facility faces significant delays and cost uncertainties.

Conclusion · source text

Since 2006, Government policy has been to establish a Geological Disposal Facility (GDF) for the long-term storage of nuclear waste. Despite this, Nuclear Waste Services, which is the body responsible for establishing a GDF, is not at the point of having found a community willing to host a GDF or to be able to conduct the detailed geological investigation required to establish a suitable site for a GDF. The timelines and costs for building a GDF are also uncertain.

Link to this item · Read item and full response

Department for Science, Innovation and Technology
63 Recommendation Eighth Report - Delivering nuclear power

Accelerate identifying a safe GDF site with community confidence, without halting new nuclear development.

Recommendation · source text

The first waste is not expected to be placed into a Geological Disposal Facility (GDF) until the 2050s and until then, there is sufficient interim storage for both current and predicted future nuclear waste. The Government should continue work to identify a site for a GDF which will be geologically safe, and which will enjoy the confidence of the local community. Given that interim storage has been used for over 50 years and that waste from new nuclear facilities would be a small addition to the stock of waste held, we do not believe that new nuclear plants should be halted until a GDF facility has been established. (Paragraph 297) Delivering nuclear power 109

Link to this item · Read item and full response

Department for Science, Innovation and Technology

Oral evidence sessions

5 sessions

On smaller screens, scroll horizontally to read every column. Keyboard users can focus the table region and use the arrow keys.

Date Session and witnesses Source
18 Jan 2023
Oral evidence session
David Peattie · Nuclear Decommissioning Authority, Declan Burke · Department for Business, Energy and Industrial Strategy, Mark Foy · UK Office for Nuclear Regulation, Rt Hon Graham Stuart MP · Department for Business, Energy and Industrial Strategy, Simon Bowen · Great British Energy – Nuclear
View ↗
14 Dec 2022
Oral evidence session
Claes Thegerström · Swedish Nuclear Fuel and Waste Management Co, Clive Nixon · Nuclear Decommissioning Authority, Corhyn Parr · Nuclear Waste Services, Dr Robin Taylor · National Nuclear Laboratory, Janne Mokka · Posiva Oy, Professor Claire Corkhill · Committee on Radioactive Waste Management, Professor Katherine Morris · Dalton Nuclear Institute
View ↗
23 Nov 2022
Panel One; Panel Two; Panel Three
Dr Fiona Rayment OBE · National Nuclear Laboratory, Dr Ian Scott · MoltexFLEX Limited, Gethin Jenkins · Last Energy, John Eldridge · U-Battery, Laurent Odeh · Urenco, Tim Abram · University of Manchester, Tom Samson · Rolls-Royce SMR
View ↗
9 Nov 2022
Panel One; Panel Two
Corhyn Parr · Nuclear Waste Services, Dawn James · Jacobs, Dr Tim Stone CBE · Nuclear Industry Association, Ivan Baldwin · Bechtel, James Richardson · National Infrastructure Commission, Michael Drury · Terrestrial Energy, Michelle Catts · GE Hitachi Nuclear Energy
View ↗
2 Nov 2022
Panel One; Panel Two; Panel Three
Dr Paul Dorfman · Nuclear Consulting Group (NCG) and Associate Fellow, Science Policy Research Unit (SPRU), Sussex Energy Group, University of Sussex, Julia Pyke · Sizewell C, Paul Spence · EDF, Professor Francis Livens · Dalton Institute, Professor Laurence Williams · Imperial College London, Professor Michael Grubb · UCL, Professor Paul Norman · Birmingham Centre for Nuclear Education and Research
View ↗

Who gave evidence

32 witnesses

On smaller screens, scroll horizontally to read every column. Keyboard users can focus the table region and use the arrow keys.

WitnessOrganisationSessions
Corhyn Parr · Chief Executive Officer Nuclear Waste Services 2
Claes Thegerström · Former President Swedish Nuclear Fuel and Waste Management Co 1
Clive Nixon · Group Chief Nuclear Strategy Officer Nuclear Decommissioning Authority 1
David Peattie · Group Chief Executive Officer Nuclear Decommissioning Authority 1
Dawn James · Vice-President of Nuclear Power Jacobs 1
Declan Burke · Director, Nuclear Projects & Development Department for Business, Energy and Industrial Strategy 1
Dr Fiona Rayment OBE · Chief Scientific Officer National Nuclear Laboratory 1
Dr Ian Scott · Chief Scientist MoltexFLEX Limited 1
Dr Paul Dorfman · Chair Nuclear Consulting Group (NCG) and Associate Fellow, Science Policy Research Unit (SPRU), Sussex Energy Group, University of Sussex 1
Dr Robin Taylor · Senior Research Fellow National Nuclear Laboratory 1
Dr Tim Stone CBE · Chairman Nuclear Industry Association 1
Gethin Jenkins · Head of Safety and Licensing Last Energy 1
Ivan Baldwin · Business Development Director Bechtel 1
James Richardson · Chief Economist National Infrastructure Commission 1
Janne Mokka · President and CEO Posiva Oy 1
John Eldridge · Principal Engineer U-Battery 1
Julia Pyke · Joint Managing Director Sizewell C 1
Laurent Odeh · Chief Commercial Officer Urenco 1
Mark Foy · Chief Executive and Chief Nuclear Inspector UK Office for Nuclear Regulation 1
Michael Drury · Managing Director of UK Operation Terrestrial Energy 1
Michelle Catts · Senior Vice President, Nuclear Programs GE Hitachi Nuclear Energy 1
Paul Spence · Director of Strategy and Corporate Affairs EDF 1
Professor Claire Corkhill · Member Committee on Radioactive Waste Management 1
Professor Francis Livens · Director Dalton Institute 1
Professor Katherine Morris · Lead for Nuclear Environment and Waste Theme Dalton Nuclear Institute 1
Professor Laurence Williams · Visiting Professor Imperial College London 1
Professor Michael Grubb · Professor of Energy and Climate Change and Director of UCL Centre for Net Zero Market Design UCL 1
Professor Paul Norman · Professor of Nuclear Physics and Energy Director Birmingham Centre for Nuclear Education and Research 1
Rt Hon Graham Stuart MP · Minister of State (Minister for Climate) Department for Business, Energy and Industrial Strategy 1
Simon Bowen · Chair Great British Energy – Nuclear 1
Tim Abram · Westinghouse Chair in Nuclear Fuel Technology University of Manchester 1
Tom Samson · CEO Rolls-Royce SMR 1

Correspondence

3 letters

On smaller screens, scroll horizontally to read every column. Keyboard users can focus the table region and use the arrow keys.