A solicitors firm complained on behalf of their client (Ms A) about the management of asbestos at a property she had rented from the council, and the time taken to provide her with a decant from the property.

Ms A's former property was constructed with asbestos containing materials. The council had surveyed these materials and considered that they were of low risk. Ms A was made aware of this when she moved in to the property. Approximately one year later, Ms A said the council's contractor undertook works at the property, and she was concerned that they damaged the flooring. Ms A said she reported this to the council. Approximately three years later, Ms A contacted the council to raise concerns about the flooring at the property and the council arranged an inspection. The council did not consider that the asbestos containing materials presented any risk. However, a decision was subsequently made to decant Ms A to another property. The council said that they offered one property, however, Ms A did not wish to move there. A number of months passed before Ms A was decanted to another property.

Regarding the management of asbestos at the property, we found that the council had conducted a survey that established this was low risk and in good condition. We found that the council followed their asbestos management plan. We found no evidence that the council's contractor carried out works inappropriately, and the council had no records of being contacted at that time. When Ms A raised concerns about the property approximately three years later, we found that the council organised an inspection, and relied on the professional expertise of their officer in concluding that there was no risk from the asbestos. We found this to be reasonable and we did not uphold this aspect of the complaint.

In relation to the time taken to provide a decant, we noted the council's records indicated that one was initially offered, but Ms A did not wish to move. The council explained that there were limited properties available that were suitable. The property that Ms A was eventually moved to required works before it was ready. In these circumstances, we considered that there was no unreasonable delay by the council and we did not uphold this aspect of the complaint.

Related reading

View Decision Report 201607207 as a PDF (11.56 KB) Updated: March 13, 2018

View original on SPSO (Scottish Publ… website

Other decisions involving East Renfrewshire Council

Reference Date Summary Outcome
201911240 01 Sep 2022 C complained about the council's handling of a planning application. C's neighbour was granted planning consent for an outbuilding in … Partly Upheld
201602629 01 May 2017 Mr C was unhappy with the way the council handled a request for a non-material variation (NMV) to a planning … Partly Upheld
201605670 01 May 2017 Mr C reported problems with the behaviour of his neighbour, who is a private tenant, including a number of reports … Not Upheld
201507810 01 Feb 2017 Mr C complained that the council unreasonably failed to follow their Unacceptable Actions Policy when restricting his communication with them. … Upheld
201407841 01 Oct 2015 Mr C complained that the council failed to follow their anti-bullying policies when they were informed of incidents of bullying … Upheld
View all decisions for this organisation