Mr C owns a flat in a block of six, half of which are owned by the council and half of which are privately owned. Mr C complained that the council failed to write to him to advise of repairs that needed to be carried out in communal areas and that as a consequence no estimates were obtained and he had not been aware that work had taken place.

The council invoiced Mr C in March 2016 for work carried out in April 2015 and August 2015. He complained about the delay in receiving the invoice and asked for a breakdown of costs, which the council said they were unable to provide. The council instructed a debt collection agency to recover the debt, and Mr C complained that the council had failed to notify him that this would be their next step.

The council provided evidence showing that they had notified owners of planned repairs, allowing them time to obtain alternative estimates. Mr C accepted that in the case of emergency repairs the council did not need to notify owners in advance. We considered that the council had not unreasonably failed to notify Mr C in advance of repairs that required to be carried out, and did not uphold this complaint.

We found that the delay in issuing the invoice for repairs in April and August 2015 was unacceptable, and recommended that the council apologise for this.

With regards to providing a breakdown of costs, the council's position was that repairs are often carried out by sub-contractors, who invoice the council in batched accounts. We considered it reasonable for the council not to provide a breakdown of costs in these situations but recommended that when possible, for example when repairs are carried out by council tradespeople, the council should provide a breakdown of costs.

Mr C complained that the council gave him no notice that they would be instructing a debt collection agency to recover sums owed. However, the council provided evidence showing that there had been a clear statement to that effect on the overdue invoice sent to Mr C. We did not uphold this complaint.

We noted Mr C's frustration at not being able to communicate with the council, especially regarding emergency repairs. We recommended that the council nominate a key contact for communication about any matters relating to communal parts of the building and provide Mr C with contact details.

Recommendations

We recommended that the council: apologise to Mr C for the delay in issuing an invoice; provide a breakdown of costs on invoices where possible, and confirm to us that this will be implemented; and nominate a key contact for communication regarding communal areas of the building, and provide Mr C with contact details.

Related reading

View Decision Report 201605800 as a PDF (14.13 KB) Updated: March 13, 2018

View original on SPSO (Scottish Publ… website

Other decisions involving Aberdeen City Council

Reference Date Summary Outcome
202401558 01 Mar 2025 C complained about the council’s handling of communal repairs at a tenement in which C owned a property. Extensive work … Upheld
202208569 01 Dec 2024 C and their autistic child took up their tenancy, having been offered the property following assessment for priority for allocation. … Partly Upheld
202209886 01 Nov 2024 C complained that the council and school staff failed to reasonably respond or act when C told them about domestic … Upheld
202302784 01 Oct 2024 C complained about communication from the council's social work department relating to C’s involvement in the Looked After Child (LAC) … Not Upheld
202106027 01 Jun 2024 C complained about the council’s handling of a planning application. C’s next door neighbour made a retrospective application for planning … Upheld
View all decisions for this organisation