Source · SPSO (Scottish Public Services Ombudsman)

East Lothian Council

SPSO (Scottish Public Services Ombudsman) Partly Upheld Reference 201602127 Sector Local Government Category improvements and renovation Decided 01 December 2017

View East Lothian Council scorecard

Full decision

Summary

Mrs C complained that the council had unreasonably failed to act in line with their responsibilities in overseeing a programme of works that was carried out in the area by a third party company. Mrs C considered that the works carried out at her home had not been done to a reasonable standard and also complained that the council had not handled her complaint about this appropriately.

After investigating Mrs C's concerns about the oversight of the programme of works, we did not uphold her complaint. We found that the council had used a managing agent to oversee the programme of works and there was evidence that a supervisory service was provided by them. While the council had no liability or responsibility for the works, we found that when issues arose at Mrs C's property, they took an active co-ordination role to work towards resolving these. However, we found that in responding to Mrs C's official complaint, the council failed to respond within the 20 working days specified in their complaints handling procedure. Therefore, we upheld this aspect of Mrs C's complaint and made recommendations to the council.

Recommendations

What we asked the organisation to do in this case: Apologise to Mrs C for failing to respond to her concerns or give an appropriate update within the timescales laid out in their complaints handling procedure. This apology should comply with SPSO guidelines on making an apology, available at www.spso.org.uk/leaflets-and-guidance.

In relation to complaints handling, we recommended: Complaints should be handled in line with the complaints handling procedure. Any revised timescale should be agreed with the complainant or approved by senior staff in line with the policy and the reasons for this explained to the complainant.

We have asked the organisation to provide us with evidence that they have implemented the recommendations we have made on this case by the deadline we set.

Related reading

View Decision Report 201602127 as a PDF (12.78 KB) Updated: March 13, 2018

View original on SPSO (Scottish Publ… website

Other decisions involving East Lothian Council

Reference Date Summary Outcome
202409021 01 Jun 2025 C complained that the council failed to reasonably respond to reports of damp and mould in their property. C also … Upheld
202105316 01 Nov 2022 C complained that the council failed to respond reasonably to their enquiries. A planning application was submitted by a business … Partly Upheld
201806620 01 Feb 2021 Mr C complained that for over three years, the council failed to reasonably respond to his and his wife's (Mrs … Partly Upheld
201902383 01 Jan 2021 C made an application to the council for a row of trees neighbouring their property to be removed or reduced … Upheld
201901549 01 Dec 2020 C complained about the council's handling of a Statutory Nuisance under the Environmental Protection Act 1990 (the Act), which was … Not Upheld