Source · SPSO (Scottish Public Services Ombudsman)

East Lothian Council

SPSO (Scottish Public Services Ombudsman) Upheld Reference 202409021 Sector Local Government Category Mould / damp Decided 01 June 2025

View East Lothian Council scorecard

Full decision

Summary

C complained that the council failed to reasonably respond to reports of damp and mould in their property. C also complained about the council’s handling of their complaint.

The council said that they had commissioned an independent survey of the property. They also apologised for delaying with some repairs.

We found that C was responsible for helping to manage the levels of humidity and the temperature in their home by maintaining ventilation and ensuring a reasonable temperature. However, it was clear that there were a number of repairs which the council were responsible for, some of which were delayed and which have generally occurred over an extended period of time. On review, it appeared that they had only been progressed or completed as a result of C’s persistence. Therefore, we upheld this part of C's complaint.

In terms of complaint handling, we found that the council acknowledged and responded to C's complaint in a timely manner. However, we found that they failed to provide a full and informed response to a later complaint. On balance, we upheld this part of C's complaint.

Recommendations

What we asked the organisation to do in this case: Apologise to C for the failings identified in this report. The apology should meet the standards set out in the SPSO guidelines on apology available at www.spso.org.uk/meaningful-apologies.

The council should clarify for C the works which are still to be completed and provide a timeframe for completion of the repairs.

In relation to complaints handling, we recommended: Complaint investigations should be managed in accordance with the Model Complaints Handling Procedure https://www.spso.org.uk/the-model-complaints-handling-procedures. Complaint investigations should fully investigate the matters of complaint made and, where appropriate, timeous action should be taken to rectify matters.

The council should have effective systems in place to ensure that repairs are completed timeously.

Related reading

View Decision Report 202409021 as a PDF (27.63 KB) Updated: June 18, 2025

View original on SPSO (Scottish Publ… website

Other decisions involving East Lothian Council

Reference Date Summary Outcome
202105316 01 Nov 2022 C complained that the council failed to respond reasonably to their enquiries. A planning application was submitted by a business … Partly Upheld
201806620 01 Feb 2021 Mr C complained that for over three years, the council failed to reasonably respond to his and his wife's (Mrs … Partly Upheld
201902383 01 Jan 2021 C made an application to the council for a row of trees neighbouring their property to be removed or reduced … Upheld
201901549 01 Dec 2020 C complained about the council's handling of a Statutory Nuisance under the Environmental Protection Act 1990 (the Act), which was … Not Upheld
201900063 01 Dec 2020 C complained about the actions of the council in carrying out roof repair works on a block of flats as … Upheld
View all decisions for this organisation