Linc Cymru Housing Association

PSOW (Public Services Ombudsman for Wales) Resolved / Early Resolution Reference PSOW-202408303 Sector Housing Category Damp and mould Decided 14 February 2025

Full decision

Mr A complained about the action taken by Linc Cymru Housing Association (“the Housing Association”) to address issues with damp and mould in his property. He said that other residents living on the ground floor of the same building had raised concerns about similar issues. Mr A also raised concerns that he had not been provided with information regarding his options for alternative accommodation.

The Ombudsman found that although the Housing Association had taken some action to investigate the concerns reported by Mr A, there did not seem to be a clear plan to further address the ongoing issues. The Ombudsman decided to settle the complaint without an investigation.

The Ombudsman sought and gained the Housing Association’s agreement to, within 3 weeks, complete a full investigation into the concerns raised by Mr A about the condition of his property and to consider his request for an independent thermal survey and an inspection of ducts and floors. In addition, to consider the concerns Mr A raised about other residents’ complaints regarding the ground floor of the building. Within 6 weeks, the Housing Association agreed to provide a formal complaint response, to include the outcome of the investigations, confirm the action plan and outline the options available to Mr A for alternative accommodation.

View original on PSOW (Public Servic… website

Other decisions involving Linc Cymru Housing Association

Reference Date Summary Outcome
PSOW-202500564 04 Jul 2025 Ms A complained that Linc Cymru Housing Association (“the Housing Association”) failed to act appropriately to her reports of antisocial … Resolved / Early Resolution
PSOW-202405211 23 Dec 2024 Mr B complained that the Association carried out work on his kitchen that was substandard and did not meet his … Resolved / Early Resolution
PSOW-202403262 30 Jul 2024 Miss D complained that Linc Cymru Housing Association failed to remedy the mould in her property. The Ombudsman found that … Resolved / Early Resolution
PSOW-202301539 21 Jun 2023 Mr N complained that Linc Cymru Housing Association has failed to complete the structural repair works despite him temporarily moving … Resolved / Early Resolution
PSOW-202208371 12 May 2023 Ms I complained that Linc Cymru Housing Association failed to take proactive action to resolve issues of repairs in her … Resolved / Early Resolution
View all decisions for this organisation