The Ombudsman's final decision

Summary: We will not investigate this complaint about the Council’s failure to enforce the terms of a section 278 legal agreement. The Council has confirmed the outstanding work is scheduled to be completed. Therefore, further investigation is not likely to lead to a different outcome, and it is not a good use of public resources to investigate failings in the complaints process alone.

The complaint

Mrs X complains the Council has: Failed to enforce the terms of a section 278 legal agreement with the developer of the road where she lives.

Failed to act on the misrepresentations made by the developer.

Allowed the developer to pursue new planning applications without fulfilling existing obligations.

Failed to respond to complaints within the correct timeframe.

The Ombudsman’s role and powers

We investigate complaints about ‘maladministration’ and ‘service failure’, which we call ‘fault’. We must also consider whether any fault has had an adverse impact on the person making the complaint, which we call ‘injustice’. We provide a free service but must use public money carefully. We do not start or continue an investigation if we decide further investigation would not lead to a different outcome.

(Local Government Act 1974, section 24A(6), as amended, section 34(B))

How I considered this complaint

I considered information provided by Mrs X and the Council.

I considered the Ombudsman’s Assessment Code.

My assessment

In response to my enquiries, the Council confirmed some of the outstanding works have been completed. A timetable is in place for the remaining works to be carried out. It also confirms it will continue to chase the developer for progress. Therefore, I consider further investigation will not lead to a different outcome.

We expect councils to respond to complaints according to their published complaints procedures. However, we consider it is not a good use of public resources to investigate a complaint about the complaint process alone when we are not considering the substantive issue.

Final decision

We will not investigate Mrs X’s complaint because we consider that further investigation will not lead to a different outcome.

Investigator's decision on behalf of the Ombudsman

View original on LGO (Local Governme… website

Other decisions involving North East Derbyshire District Council

Reference Date Summary Outcome
25-013-617 Other
25-017-257 Other
24-019-909 07 Apr 2025 Summary: We will not investigate this complaint about the Council’s decision to refuse the complainant’s application to remove a tree … Other
24-009-825 14 Nov 2024 Summary: We will not investigate this complaint about how the Council has dealt with breaches of planning control. This is … Other
24-008-715 15 Oct 2024 Summary: We will not investigate this complaint about an alledged failure by the Council for sending the complainant a warning … Other
View all decisions for this organisation