LFB to attend construction meetings, register risks, relocate affected equipment
Fennell Inquiry · Fennell Inquiry — Final Report · Issued 10 November 1988 · Addressed to: London Fire Brigade
Government responseNot tracked (historical inquiry)
DeliveryNo statement from London Fire Brigade found
Recommendation, verbatim from the inquiry
●Inquiry recommendation
The London Fire Brigade shall attend all pre-start meetings and important later meetings in relation to construction works on the Underground. Details of the works shall be included on the Fire Brigade's central risks register. Fire equipment and London Fire Brigade plan boxes affected must be relocated before work starts.
Fennell Inquiry, Fennell Inquiry — Final Report · 10 Nov 1988 Source PDF →
Government response
●No formal government response recorded
The Index has not yet recorded a verbatim government response to this recommendation.
Delivery
No statement on delivery from London Fire Brigade has been found in the sources searched. This is separate from the response above.
How this page is built
The recommendation and the government responses are verbatim from primary documents. Delivery statements and other bodies' findings are shown in their own words, each with its source. The summary is written by this site and labelled as such. The Index does not paraphrase sources or characterise intent; it records what has been published.