Replace Buried Metallic LPG Pipes
ICL Inquiry · The ICL Inquiry Report: Explosion at Grovepark Mills, Maryhill, Glasgow, 11 May 2004 · Issued 16 July 2009 · Addressed to: Health and Safety Executive
Government responseDepartment for Work and Pensions: Accepted (Mar 2010)
DeliveryHealth and Safety Executive says partially delivered (Aug 2016)
Recommendation, verbatim from the inquiry
●Inquiry recommendation
An urgent programme of replacement of buried metallic LPG pipework with polyethylene piping should be implemented.
ICL Inquiry, The ICL Inquiry Report: Explosion at Grovepark Mills, Maryhill, Glasgow, 11 May 2004 · 16 Jul 2009 Source PDF →
Published evidence summary
AI-generated evidence summary
The Inquiry recommended urgently replacing buried metallic liquefied petroleum gas (LPG) pipework with polyethylene. In August 2016, UKLPG and the Health and Safety Executive reported that suppliers had replaced pipework at approximately 4,500 priority 1 sites by 2015, but explained that longer deadlines applied to lower-risk pipes while regulators addressed remaining resistant customers (UKLPG and Health and Safety Executive, Aug 2016). HM Government had agreed in March 2010 that metallic service pipework in industrial and commercial premises should be replaced (Department for Work and Pensions response, Mar 2010). In August 2009, Judith Hackitt CBE, Chair of the executive, had initially planned to complete the replacement programme by the end of 2015 (Judith Hackitt, Aug 2009).
AI-generated summary of the record on this page, checked by a second model and automatic checks, 1 Oct 2026.
About this summary
Government response
●Department for Work and Pensions · Accepted · 18 Mar 2010
The Government recognises that corrosion of the underground metallic service pipe supplying the factory was the key factor that contributed to the explosion at ICL Plastics Ltd and agrees with Lord Gill that there should be a programme of replacement of such pipework in industrial and commercial premises.
Extract from: The Government response to the ICL Inquiry Report: Explosion at Grovepark Mills, Maryhill, Glasgow, 11 May 2004
Delivery
●Health and Safety Executive says partially delivered · 4 Aug 2016
In 2011, the HSE appointed an Independent Expert Working Group (IEWG) to review progress and advise on the replacement timescale for the low priority premises. The IEWG categorised the low priority risk pipework into four risk groups (p 1 to 4) and came to a view that replacing all by the end of 2015 was not justifiable in terms of additional costs and resource implications. Its conclusions were agreed and accepted by the industry and regulator and meant that priority 1 (p1) low risk pipework was planned to be replaced by end of 2015 with longer deadlines given for even lower risk pipework. LPG suppliers completed work at approximately 4,500 p1 sites by the end of 2015, a small number of resistant or difficult customers are being dealt with by the regulators.
From: Safety changes in the industrial and commercial use of LPG: 2009-2015
Earlier statements on delivery (0)
●Health and Safety Executive · 27 Aug 2009
Current plans are to complete the LPG metallic pipeline programme by the end of 2015, with the highest risk pipework completed sooner.
How this page is built
The recommendation and the government responses are verbatim from primary documents. Delivery statements and other bodies' findings are shown in their own words, each with its source. The summary is written by this site and labelled as such. The Index does not paraphrase sources or characterise intent; it records what has been published.